Putting the award page together from the records…
Putting the award page together from the records…
TEST AND EVALUATION NON-KINETIC DELIVERY ORDER AIRBORNE NON-KINETIC SYSTEMS FOR TEST, LABOR, MATERIALS, TRAVEL, AND OTHER DIRECT COSTS
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
3 subawards totaling $6.92M (39.7% of what was obligated), as Verus Research, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| General Atomics Aeronautical Systems, Inc. | $6.42M | 1 | CA | 2024-12-19 | 2024-12-19 |
| Zivko Aeronautics Inc | $463.9K | 1 | OK | 2024-03-14 | 2024-03-14 |
| Fortis Strategic Consulting, LLC | $36.0K | 1 | FL | 2024-10-03 | 2024-10-03 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-12-19 | General Atomics Aeronautical Systems, Inc. | $6.42M | THE SUBJECT WORK ADDRESSES KEY ELEMENTS OF THE RRAE PROJECT TO DEVELOP FOR THE DOD AN AIRBORNE HPM PAYLOAD. THIS PAYLOAD WILL SERVE AS A TEST AND EVALUATION SURROGATE FOR COUNTER-ELECTRONICS ENGAGEMENTS. |
| 2024-03-14 | Zivko Aeronautics Inc | $463.9K | THE OBJECTIVES OF THIS WORK ARE TO PROVIDE SUPPORT FOR MULTIPLE ASPECTS OF THE RRAE PROGRAM BY LEVERAGING THE ZAI€„¢S EXPERTISE IN THE AREAS OF:SYSTEMS ENGINEERING, €¢ AEROSPACE POD DESIGN, DEVELOPMENT, AND… |
| 2024-10-03 | Fortis Strategic Consulting, LLC | $36.0K | TEN-K DO8 SUPPORT AGILE SOURCES ADVANCEMENT (SOW 2.B) 10/01/2024-09/30/2025 |
13 actions since 2024-02-15. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-17 | P00012 | Administrative change | $0 | AIRBORNE NON-KINETIC SYSTEMS FOR TEST (ANKST) |
| 2026-07-15 | P00011 | Funding only | $4.01M | AIRBORNE NON-KINETIC SYSTEMS FOR TEST (ANKST) |
| 2026-06-04 | P00010 | Funding only | $1.69M | AIRBORNE NON-KINETIC SYSTEMS FOR TEST (ANKST) |
| 2026-05-04 | P00009 | Administrative change | $0 | AIRBORNE NON-KINETIC SYSTEMS FOR TEST (ANKST) |
| 2025-09-23 | P00008 | Funding only | $1.35M | MODIFICATION TO INCREMENTALLY FUND ADD 1.5M ON SLIN 000114 AND UPDATE ALLOTMENT OF FUNDS. |
| 2025-05-22 | P00007 | Funding only | $1.50M | MODIFICATION TO INCREMENTALLY FUND ADD 1.5M ON SLIN 000114 AND UPDATE ALLOTMENT OF FUNDS. |
| 2025-01-17 | P00006 | Administrative change | $0 | ADD GROUND FLIGHT RISK CLAUSE |
| 2024-12-12 | P00005 | Funding only | $1.80M | INCREMENTAL FUNDING FOR LABOR, MATERIALS, TRAVEL |
| 2024-09-25 | P00004 | Funding only | $4.55M | INCREMENTAL FUNDS ADDED. NO OTHER CHANGES. |
| 2024-08-22 | P00003 | Administrative change | $0 | DELIVERY ORDER PROVIDES AIRBORNE NON-KINETIC SYSTEMS FOR TESTING. MODIFICATION CORRECTS ROUTING TABLES UNDER THE WIDE AREA WORKFLOW PAYMENT CLAUSE 252.232-7006 |
| 2024-07-18 | P00002 | Funding only | $1.54M | DELIVERY ORDER PROVIDES AIRBORNE NON-KINETIC SYSTEMS FOR TEST (ANKST) TEST AND EVALUATION NON-KINETIC SUPPORT. MODIFICATION PROVIDES INCREMENTAL FUNDING AND MAKES OTHER ADMINISTRATIVE UPDATES. |
| 2024-03-15 | P00001 | Administrative change | $0 | CORRECT DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE ACTIVITY ADDRESS DIRECTORY CODE IN THE WIDE AREA WORKFLOW CLAUSE. |
| 2024-02-15 | 0 | $1.00M | TEST AND EVALUATION NON-KINETIC DELIVERY ORDER AIRBORNE NON-KINETIC SYSTEMS FOR TEST, LABOR, MATERIALS, TRAVEL, AND OTHER DIRECT COSTS |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗