| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-21 | P00023 | Funding only | -$14.7K | THIS EFFORT WILL PROVIDE OPERATIONAL SUPPORT BY PROVIDING THE FACILITIES AND STAFF EXPERTISE TO SUCCESSFULLY EXECUTE REQUIRED TESTING AND EVALUATION AND OTHER TECHNOLOGIES AT FORT A.P. HILL. |
| 2026-06-15 | P00022 | Administrative change | $0 | THE EFFORT WILL PROVIDE OPERATIONAL SUPPORT BY PROVIDING THE FACILITIES AND STAFF EXPERTISE TO SUCCESSFULLY EXECUTE REQUIRED TESTING AND EVALUATION AND OTHER TECHNOLOGIES AT FORT A.P. HILL |
| 2026-05-20 | P00021 | Funding only | $0 | THE EFFORT WILL PROVIDE OPERATIONAL SUPPORT BY PROVIDING THE FACILITIES AND STAFF EXPERTISE TO SUCCESSFULLY EXECUTE REQUIRED TESTING AND EVALUATION AND OTHER TECHNOLOGIES AT FORT A.P. HILL, VIRGINIA. |
| 2025-07-15 | P00020 | Funding only | $54.9K | THE EFFORT WILL PROVIDE OPERATIONAL SUPPORT BY PROVIDING THE FACILITIES AND STAFF EXPERTISE TO SUCCESSFULLY EXECUTE REQUIRED TESTING AND EVALUATION AND OTHER TECHNOLOGIES AT FORT A.P. HILL, VIRGINIA. |
| 2025-06-04 | P00019 | Funding only | $86.5K | THE EFFORT WILL PROVIDE OPERATIONAL SUPPORT BY PROVIDING THE FACILITIES AND STAFF EXPERTISE TO SUCCESSFULLY EXECUTE REQUIRED TESTING AND EVALUATION AND OTHER TECHNOLOGIES AT FORT A. P. HILL, VA. |
| 2025-03-06 | P00018 | Funding only | $15.2K | FORT WALKER (FORMERLY A.P. HILL), VA - THIS SUPPORT MAY INCLUDE THE DESIGN AND BUILD OF VARIOUS TARGETS, DEVELOPMENT SUPPORT OF TEST PLANS AND EVALUATION EFFORTS FOR ELECTRO-OPTIC/INFRARED (EO/IR) AND OTHER SENSOR TECHNOLOGIES TESTED AT RANGES. |
| 2024-09-05 | P00017 | Administrative change | $386.7K | EXERCISE OY3 AND INCREMENTAL FUNDING |
| 2024-08-21 | P00016 | Funding only | $30.5K | INCREMENTAL FUNDING AND CEILING REALIGNMENT |
| 2024-06-06 | P00015 | Administrative change | $0 | ADMIN MOD |
| 2024-05-23 | P00014 | Funding only | $214.6K | INCREMENTAL FUNDING |
| 2024-04-25 | P00013 | Funding only | $4.4K | INCREMENTAL FUNDING |
| 2024-02-01 | P00012 | Administrative change | $23.7K | ADMIN MOD |
| 2024-01-05 | P00011 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO TRANSFER PURCHASING OFFICE RESPONSIBILITY FROM W909MY (W4GV CECOM ACQ CTR WASH OPS OF) TO W56KGU (ACC-APG DIVISION A). |
| 2023-09-20 | P00010 | Funding only | $200.0K | INCREMENTAL FUNDING |
| 2023-09-11 | P00009 | Option exercised | $238.3K | INCREMENTAL FUNDING |
| 2023-05-17 | P00008 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE UPDATED PWS TO INCLUDE THE TELEWORK AND MIRARS POLICY |
| 2023-02-16 | P00007 | Administrative change | $270.0K | INCREMENTAL FUNDING |
| 2022-11-17 | P00006 | Administrative change | $186.0K | INCREMENTAL FUNDING |