W909MY23C0004↗

Raytheon Company received this contract from W6QK Acc-Apg Cont CT Wash Ofc, Department of the Army: $103.49M obligated so far for night vision equipment, emitted and reflected radiation. It runs to 2029-06-30.

Key facts · data as of Oct 25, 2026

Recipient
Raytheon Company
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W6QK Acc-Apg Cont CT Wash Ofc (W909MY)
Obligated to date
$103.49M
Potential value
$167.43M
Ends
2029-06-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award W909MY23C0004, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W909MY23C0004_9700_-NONE-_-NONE-

THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LRIP LOW RATE INITIAL PRODUCTION (LRIP) B-KIT

Definitive Contract · Department of the Army · to Raytheon Company (UEI HEBCLD22EJD1) · data as of 2026-10-25

Obligated to date$103.49M24 actions
Current value$105.64Mwith options exercised
Potential value$167.43Mif every option is used
Period2023-06-29 → 2029-06-30current end date
Passed on$14.11Mto 37 subcontractors

What it is

Product or service
Night Vision Equipment, Emitted and Reflected Radiation (PSC 5855)
Industry
Search, Detection, Navigation, Guidance, Aeronautical, and Nautical System and Instrument Manufacturing (NAICS 334511)
Contracting office
W6QK Acc-Apg Cont CT Wash Ofc (W909MY)
Competition
Not competed · 1 offer received
Pricing
Firm fixed price
How it was bought
Standalone contract
Solicitation
W909MY22R0002
Where the work is
Collin, TX · district TX-03

Obligations by fiscal year

FY2023$27.69M
FY2024$32.90M
FY2025$35.38M
FY2026$7.52M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

82 subawards totaling $14.11M (13.6% of what was obligated), as Raytheon Company reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubcontractorAmountSubawardsWhereFirstLast
FCG Inc$1.73M7PA2023-11-022025-11-12
Spartronics Logan LLC$1.70M1UT2023-09-072023-09-07
Janos Technology LLC$1.15M6NH2023-12-122025-12-12
G5 Infrared, LLC$1.04M8NH2023-11-162024-07-01
Vontier Corporation$957.7K5NH2023-11-092023-11-28
Attalon, Inc.$888.0K2CA2023-11-272025-12-22
Schleifring North America, LLC$754.6K5MA2023-10-102025-12-09
Reynard Corporation$732.8K2CA2023-11-102025-12-23
Schmiede Corporation$582.7K3TN2023-11-132026-01-29
Blue Line Engineering LLC$508.6K2CO2023-10-122025-03-13
CVD Ceramics, Inc.$450.8K1LA2025-11-142025-11-14
Micor Industries, LLC$401.8K4AL2023-11-092024-03-19
Camtron, Incorporated$286.9K2TX2023-10-022025-10-22
Fairfield Crystal Technology, LLC$246.4K2CT2023-10-242024-03-20
Lattice Materials LLC$244.5K1MT2023-12-202023-12-20
Clear Align LLC$212.7K3PA2023-11-092023-12-13
Learjet Inc$187.5K2CA2024-02-222026-01-14
The Captor Corporation$187.1K2OH2023-10-242024-03-12
Novotech Inc.$167.6K1MA2023-10-182023-10-18
Hardric Laboratories, Inc$158.0K1NH2023-11-202023-11-20
Era Industries, LLC$153.1K1IL2026-01-152026-01-15
Seiler Instrument and Manufacturing Company, Incorporated$145.9K2MO2024-01-262025-11-06
Mechatronics, Inc.$139.9K2WA2023-11-172024-07-09
CDP Fastener Group, Inc.$120.0K1MA2025-10-082025-10-08
Rotron Incorporated$117.6K1NY2023-10-192023-10-19

The 25 largest of 37; the rest are on USAspending.gov.

The largest single subawards
DateToAmountFor
2023-09-07Spartronics Logan LLC$1.70MCUSTOM CCA'S POWER SUPPLY ASSEMBLY CUSTOM CCA'S MECHANISM CONTROL ASSEMBLY CUSTOM CCA'S VIDEO PROCESSOR ASSEMBLY CUSTOM CCA'S TRU PERSONALITY MODULE ASSEMBLY NRE - FIRST ARTICLE NRE - FAI NRE - ALL NRE…
2025-11-12FCG Inc$732.6KFLEX ASSY(W/CONNECT),NRE- FIRST ARTICLE.
2023-11-14FCG Inc$497.7KNRE - FIRST ARTICLE, CUSTOM CCA'S, CUSTOM CCA'S.
2023-10-12Blue Line Engineering LLC$476.7KELECTROMECH-MJ ASSYS, NRE - ALL, NRE - FIRST ARTICLE.
2025-12-22Attalon, Inc.$457.0KLENSES.
2025-11-14CVD Ceramics, Inc.$450.8KOPTICAL RAW MATERIAL.
2023-11-27Attalon, Inc.$431.0KLENSES, NRE - FIRST ARTICLE, LENSES.
2023-11-17G5 Infrared, LLC$421.1KLENSES, NRE - FIRST ARTICLE, LENSES.
2025-12-23Reynard Corporation$420.2KLENSES,OPTICAL FILTERS,NRE - ALL.
2023-11-28Janos Technology LLC$391.2KLENSES, LENSES.
2023-12-12Janos Technology LLC$370.0KNRE - FIRST ARTICLE, LENSES.
2023-11-16Janos Technology LLC$314.6KLENSES, NRE - FIRST ARTICLE, LENSES.
2023-12-12Janos Technology LLC$314.6KNRE - FIRST ARTICLE, LENSES.
2023-11-10Reynard Corporation$312.6KLENSES, NRE - FIRST ARTICLE, OPTICAL FILTERS, LENSES, OPTICAL FILTERS.
2025-01-30Schleifring North America, LLC$302.4KNRE- FIRST ARTICLE,NRE- ENGINEERING.
2023-11-14Schmiede Corporation$264.5KNRE - ENGINEERING, NRE - TOOLING, PRECISION MACHINED.
2026-01-29Schmiede Corporation$245.0KPRECISION MACHINED,NRE - ALL.
2023-12-20Lattice Materials LLC$244.5KOPTICS.
2023-12-13Janos Technology LLC$221.6KNRE - FIRST ARTICLE, LENSES.
2025-07-17FCG Inc$206.6KCCA - CUSTOM,NRE- ENGINEERING.
2023-11-09Micor Industries, LLC$196.4KGEN STRUCTURAL ASSYS, NRE - FIRST ARTICLE, NRE - TOOLING, GEN STRUCTURAL ASSYS.
2023-11-27G5 Infrared, LLC$184.8KLENSES, NRE - FIRST ARTICLE.
2023-10-18Novotech Inc.$167.6KNRE - FIRST ARTICLE, OPTICS.
2023-10-10Schleifring North America, LLC$162.6KSLIP RINGS, SLIP RINGS.
2023-11-20Hardric Laboratories, Inc$158.0KMIRRORS, NRE - FIRST ARTICLE, MIRRORS.

Every action

24 actions since 2023-06-29. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-06-16P00023Funding only$4.00MTHIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
2026-05-13P00022Funding only$3.12MTHIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
2026-03-11P00021Funding only$393.2KTHIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
2026-02-26P00020Administrative change$0THIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
2025-12-05P00019Vendor address changed$0THE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER TWENTY-TWO (22) OF THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) B-KITS AND TWENTY-SIX (26) THERMAL RECEIVER UNITS (TRUS) IN ORDER TO MEET
2025-09-30P00018Supplemental agreement (work within scope)$0THE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER TWENTY-TWO (22) THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) B-KITS AND TWENTY- SIX (26) THERMAL RECEIVER UNITS (TRUS) IN TO MEET MSR REQUIREMENTS.
2025-08-20P00017Additional work (new agreement)$35.15MTHE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER TWENTY-TWO (22) 3GEN FLIR B-KITS AND TWENTY- SIX (26) TRUS AS SET FORTH IN TO MEET MSR REQUIREMENTS IN ACCORDANCE WITH (IAW) SECTION 3.1.8.5 OF THE PERFORMANCE WORK STATEMENT (PWS).
2025-07-02P00016Funding only$256.4KTHE PURPOSE OF THIS REQUIREMENT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
2025-06-03P00015Funding only$138.0KTEH PURPOSE OF THE REQUIREMENT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
2025-04-28P00014Administrative change-$160.8KTHE PURPOSE OF THE REQUIREMENT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
2025-04-17P00013Additional work (new agreement)$0THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW-RATE INITIAL PRODUCTION (LRIP) B-KIT AND TECHNICAL & ENGINERING SERVICES, TEST SERVICES, AND LOGISTICS SERVICES.
2024-12-05P00012Administrative change$0THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW-RATE INITIAL PRODUCTION (LRIP) B-KIT AND TECHNICAL & ENGINEERING SERVICES, TEST SERVICES, AND LOGISTICS SERVICES.
2024-10-31P00011Supplemental agreement (work within scope)$0THE OBJECTIVE OF THIS EFFORT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
2024-09-26P00010Funding only$829.3KTHIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW RATE INITIAL PRODUCTION (LRIP) B-KIT TECHNICAL & ENGINEERING SERVICES, TEST SERVICES, AND LOGISTICS SERVICES.
2024-09-04P00009Funding only$8.36MTHE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) B-KITS AND PROVIDE ASSOCIATED ENGINEERING SERVICES.
2024-08-05P00008Additional work (new agreement)$0THIS REQUIREMENT IS FOR THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW-RATE INITIAL PRODUCTION AS WELL AS TECHNICAL AND ENGINEERING SERVICES.
2024-06-17P00007Funding only$40.8KRE-OBLIGATING AND DE-OBLIGATING FUNDS TO CORRECT INVOICING
2024-05-16P00006Funding only-$240.8KDE-OBLIGATING FUNDS
2024-04-25P00005Funding only$2.13MINC FUNDING, INCORPORATE ECPS AND REVISED PWS
2024-02-16P00004Funding only$6.47MPROVIDING INC FUNDS, REDUCE CLIN 1001 AND REALIGN TO CLIN 1027, PROVIDE FUNDING TO SUPPORT YEAR 2 ANNUAL LABOR, AND RECEIVE GFP AND CAP FROM DO W909MY19F0054
2023-12-15P00003Funding only$6.57MADDING INC FUNDS, DELETE CLINS, REVISE OPTION CLIN 1014, REVISE DELIVERY DATES, INCORPORATE REVISED CDRLS AND PWS
2023-11-30P00002Supplemental agreement (work within scope)$8.74MINC FUNDING, EXERCISE OPTIONS, REVISE PRICING, REVISE DELIVERY SCHEDULE, REVISE SHIP TO, REVISE BILLING, DELETE CLINS, AND INCORPORATE REVISED PWS.
2023-09-26P00001Change order$311.5KINCREMENTAL FUNDING, UPDATING CLAUSES AND REVISE ATTACHMENTS
2023-06-290$27.38MTHE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LRIP LOW RATE INITIAL PRODUCTION (LRIP) B-KIT

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗