W911KB23F0010↗

AECOM + Tetra Tech Joint Venture received this contract from W2SN Endist Alaska, Department of the Army: $1.94M obligated so far for architect and engineering- construction: missile system facilities. Its period of performance ended 2025-06-10.

Key facts · data as of Nov 19, 2026

Recipient
AECOM + Tetra Tech Joint Venture
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W2SN Endist Alaska (W911KB)
Obligated to date
$1.94M
Potential value
$1.94M
Ends
2025-06-10

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 19, 2026.

Cite this page: SpendQuery, Award W911KB23F0010, data as of Nov 19, 2026, https://spendquery.com/award?id=CONT_AWD_W911KB23F0010_9700_W912DY20D0013_9700

DESIGN SERVICES FTG 251

Delivery Order · Department of the Army · to AECOM + Tetra Tech Joint Venture (UEI XJTGR4AL3TH1) · data as of 2026-11-19

Obligated to date$1.94M8 actions
Current value$1.94Mwith options exercised
Period2022-12-19 → 2025-06-10current end date

What it is

Product or service
Architect and Engineering- Construction: Missile System Facilities (PSC C1BF)
Industry
Engineering Services (NAICS 541330)
Contracting office
W2SN Endist Alaska (W911KB)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under W912DY20D0013

Obligations by fiscal year

FY2023$2.15M
FY2024$29.7K
FY2025-$237.4K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

8 actions since 2022-12-20. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-06-18P00007Administrative change$0PURPOSE OF THE MODIFICATION IS TO REMOVE UNEXERCISED OPTIONS.
2025-06-02P00006Supplemental agreement (work within scope)-$237.4KPURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE TASK 8 AND TASK 10 FOR FTG251.
2025-01-22P00005Supplemental agreement (work within scope)$0FTG251 POP EXTENSION
2024-03-22P00004Supplemental agreement (work within scope)$0EXTEND PERIOD OF PERFORMANCE FROM 31 MARCH 2025 TO 10 OCTOBER 2025
2024-01-02P00003Funding only$29.7KTASK 2: 35% PRELIMINARY DESIGN
2023-05-23P00002Option exercised$308.0KMODIFICATION P00002 EXERCISE OPTION CLINS 0008 AND 0010
2023-03-08P00001Option exercised$66.4KMOD 0001 TO ADD ADDITIONAL TASK 9 & 10 TASK 9-15% DESIGN- EXERCISED OPTION TASK 10 SUPPORT TO THE IDAC CONTRACTOR- OPTION
2022-12-200$1.77MDESIGN SERVICES FTG 251