NEW RIVER CHAMBER AT MONTGOMERY LOCKS & DAM
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
37 actions since 2024-09-26. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-13 | A00017 | Change order | $16.6K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-07-09 | P00019 | Administrative change | $0 | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-07-08 | P00018 | Option exercised | $20.66M | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-07-01 | P00017 | Change order | -$2.52M | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-06-23 | P00016 | Supplemental agreement (work within scope) | $3.99M | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-06-16 | A00016 | Change order | $156.6K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-05-29 | P00015 | Supplemental agreement (work within scope) | $0 | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-05-18 | P00014 | Administrative change | -$775.0K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-05-06 | A00015 | Change order | -$112.6K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-04-28 | P00013 | Option exercised | $86.73M | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-04-20 | A00014 | Change order | $53.7K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-04-20 | A00013 | Change order | $331.6K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-04-16 | P00012 | Supplemental agreement (work within scope) | $523.2K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-04-03 | P00011 | Change order | $964.3K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-03-27 | A00012 | Change order | $103.2K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-03-26 | A00011 | Change order | $97.9K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-03-03 | A00010 | Change order | $291.8K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-02-26 | P00010 | Option exercised | $0 | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER. |
| 2026-02-19 | A00009 | Change order | $21.4K | REFERENCE NO. A00009 CHANGE AR ADDITIONAL SECURITY FENCE AND GATES |
| 2026-01-08 | P00009 | Option exercised | -$2.98M | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER EXERCISE OPTION 7. |
| 2025-11-17 | P00008 | Change order | $700.0K | UCO CRACK REPAIR - NEW RIVER CHAMBER AT MONTGOMERY |
| 2025-10-15 | A00008 | Change order | $154.3K | BASE - NEW RIVER CHAMBER AT MONTGOMERY REFERENCE NO. A00008 CHANGE AN "INSTALL ADDITIONAL CRACK METERS IN LW" |
| 2025-09-24 | P00007 | Change order | $507.3K | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER ADD FABRICATION OF 30 DEGREE Y PILE PLATE. |
| 2025-09-15 | A00007 | Change order | $111.3K | BASE - NEW RIVER CHAMBER AT MONTGOMERY REFERENCE NO. A00007 CHANGES AI, AP AND AQ |
| 2025-09-04 | A00006 | Change order | $190.1K | BASE - NEW RIVER CHAMBER AT MONTGOMERY REFERENCE NO A00006 CHANGE AA "WATER TREATMENT- SULFUR ODOR MITIGATION" AND AH "TRANSFORMER SECONDARY CONDUIT" |
| 2025-08-26 | A00005 | Change order | $325.8K | BASE - NEW RIVER CHAMBER AT MONTGOMERY REF NO A000005 CHANGE AL CHANGE 2C-1F3 CONVEYOR FOUNDATION |
| 2025-08-19 | P00006 | Administrative change | $0 | NEW RIVER CHAMBER FOR MONTGOMERY L/D, UPDATE CLIN 5001. |
| 2025-08-13 | A00004 | Change order | $369.0K | BASE - NEW RIVER CHAMBER AT MONTGOMERY REFERENCE A00004 CHANGE AE EXTRA GOVERNMENT FIELD OFFICE TRAILER |
| 2025-08-01 | A00003 | Change order | $73.6K | CONTRACT FOR NEW RIVER CHAMBER AT MONTGOMERY LOCKS AND DAM REFERENCE NO. A00003 CHANGE AD INCREASE INITIAL INSTRUMENTATION READING |
| 2025-07-11 | A00002 | Change order | $17.8K | BASE - NEW RIVER CHAMBER AT MONTGOMERY A00002 / CHANGE AK "ADJUST LWEB BOTTOM OF FOOTING ELEVATION" |
| 2025-06-06 | P00005 | Administrative change | $0 | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER TO UPDATE DELIVERY DATES |
| 2025-06-04 | P00004 | Administrative change | $0 | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER TO ADD DELIVERY DATE TO CONTRACT LINE ITEM NUMBERS. |
| 2025-05-16 | P00003 | Option exercised | $34.91M | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER TO EXERCISE OPTION 3001. |
| 2025-04-16 | P00002 | Change order | $0 | MONTGOMERY LOCKS AND DAM NEW RIVER CHAMBER MODIFICATION TO IMPLEMENT EXECUTIVE ORDER 14173 AND CLASS DEVIATION 2025-O0003. |
| 2025-03-13 | A00001 | Change order | $107.9K | BASE - NEW RIVER CHAMBER AT MONTGOMERY |
| 2025-02-21 | P00001 | Supplemental agreement (work within scope) | $0 | NEW RIVER CHAMBER AT MONTGOMERY LOCKS AND DAM MODIFICATION TO OPTIONS 7 AND 8 TO REVISE AWARD DATE. |
| 2024-09-26 | 0 | $769.93M | NEW RIVER CHAMBER AT MONTGOMERY LOCKS & DAM |