ADVANCED CONTRACT INITIATIVE (ACI) TEMPORARY EMERGENCY POWER (TEP) - QUADRANT III - SUPPORT FOR HURRICANE FRANCINE
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
5 subawards totaling $431.5K (44.8% of what was obligated), as WSP USA Solutions Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Macro Companies, Inc. | $148.8K | 1 | LA | 2024-09-11 | 2024-09-11 |
| Roy & Dot'S Towing | $132.4K | 1 | CA | 2024-09-09 | 2024-09-09 |
| Acp, LLC | $58.0K | 1 | LA | 2024-09-13 | 2024-09-13 |
| Procemx LTD | $50.0K | 1 | 2024-09-09 | 2024-09-09 | |
| Grand Electric, Inc | $42.3K | 1 | FL | 2024-09-09 | 2024-09-09 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-09-11 | Macro Companies, Inc. | $148.8K | EMERGENCY RESPONSE LABOR AND EQUIPMENT FOR INSTALLING FEMA GENERATORS. |
| 2024-09-09 | Roy & Dot'S Towing | $132.4K | EMERGENCY RESPONSE LABOR AND EQUIPMENT FOR INSTALLING FEMA GENERATORS |
| 2024-09-13 | Acp, LLC | $58.0K | EMERGENCY RESPONSE LABOR AND EQUIPMENT FOR INSTALLING FEMA GENERATORS |
| 2024-09-09 | Procemx LTD | $50.0K | EMERGENCY RESPONSE LABOR AND EQUIPMENT FOR INSTALLING FEMA GENERATORS |
| 2024-09-09 | Grand Electric, Inc | $42.3K | EMERGENCY RESPONSE LABOR AND EQUIPMENT FOR INSTALLING FEMA GENERATORS |
4 actions since 2024-09-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-01-31 | P00003 | Supplemental agreement (work within scope) | -$335.7K | ADVANCED CONTRACT INITIATIVE (ACI) TEMPORARY EMERGENCY POWER (TEP) - HURRICANE FRANCINE - QUADRANT III |
| 2024-10-16 | P00002 | Change order | -$2.10M | ACI TEP - HURRICANE FRANCINE - DEOBLIGATION |
| 2024-09-12 | P00001 | Change order | $2.57M | ACI TEP - HURRICANE FRANCINE - MOD FOR POP AND TRANSFER TO TYPE II AND POP EXTENSION |
| 2024-09-10 | 0 | $828.0K | ADVANCED CONTRACT INITIATIVE (ACI) TEMPORARY EMERGENCY POWER (TEP) - QUADRANT III - SUPPORT FOR HURRICANE FRANCINE |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗