W9123722F0188↗
Amherst Madison, Inc. received this contract from W072 Endist Huntington, Department of the Army: -$786.9K obligated so far for construction of other non-building facilities. Its period of performance ended 2022-12-31.
Key facts · data as of Nov 13, 2026
- Recipient
- Amherst Madison, Inc.
- Awarding agency
- Department of the Army (Department of Defense)
- Contracting office
- W072 Endist Huntington (W91237)
- Obligated to date
- -$786.9K
- Potential value
- $796.7K
- Ends
- 2022-12-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 13, 2026.
Cite this page: SpendQuery, Award W9123722F0188, data as of Nov 13, 2026, https://spendquery.com/award?id=CONT_AWD_W9123722F0188_9700_W9123722D0003_9700
Amherst Madison, Inc.: all federal awards · Department of Defense: spending · W072 Endist Huntington: what it buys
2022 OHIO RIVER OPEN CHANNEL DREDGE
What it is
- Product or service
- Construction of Other Non-Building Facilities (PSC Y1PZ)
- Industry
- Other Heavy and Civil Engineering Construction (NAICS 237990)
- Funded by
- Corps of Engineers - Civil Works
- Contracting office
- W072 Endist Huntington (W91237)
- Competition
- Full and open competition · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under W9123722D0003
- Solicitation
- W9123721B0003
- Where the work is
- Clermont, OH · district OH-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
3 actions since 2022-10-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2023-10-27 | P00004 | Change order | -$374.3K | 2022 OHIO RIVER OPEN CHANNEL DREDGE DEOBLIGATION OF $374,299.62 FOR HUNTINGTON US ARMY CORP OF ENGINEERS (LRH) |
| 2022-11-17 | P00003 | Change order | -$177.6K | MODIFIED STATEMENT OF WORK AND REDUCTION OF $177,609.34 FOR 2022 OHIO RIVER OPEN CHANNEL DREDGE |
| 2022-10-31 | P00002 | Change order | -$235.0K | DE-OBLIGATION OF $235,000.00 FOR 2022 OHIO RIVER OPEN CHANNEL DREDGE |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-13). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗