W9126G22C0005↗
Shimmick Construction Company, Inc. received this contract from W076 Endist FT Worth, Department of the Army: $15.31M obligated so far for repair or alteration of dams. It runs to 2026-10-31.
Key facts · data as of Oct 25, 2026
- Recipient
- Shimmick Construction Company, Inc.
- Awarding agency
- Department of the Army (Department of Defense)
- Contracting office
- W076 Endist FT Worth (W9126G)
- Obligated to date
- $15.31M
- Potential value
- $91.42M
- Ends
- 2026-10-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award W9126G22C0005, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W9126G22C0005_9700_-NONE-_-NONE-
Shimmick Construction Company, Inc.: all federal awards · Department of Defense: spending · W076 Endist FT Worth: what it buys · The follow-on: recompete brief
LEWISVILLE DAM LAKE REPAIRS
Up for re-bid: ends 2026-10-31. Recompete brief → · Joe Pool Dam Slide Repairs ↗
What it is
- Product or service
- Repair or Alteration of Dams (PSC Z2KA)
- Industry
- Other Heavy and Civil Engineering Construction (NAICS 237990)
- Contracting office
- W076 Endist FT Worth (W9126G)
- Competition
- Full and open competition · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- W9126G21R0004
- Where the work is
- Denton, TX · district TX-26
- Funding law
- Other emergency or disaster supplementals
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
43 actions since 2023-05-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-08 | P00010 | Supplemental agreement (work within scope) | $1.31M | BORROW PIT CREDIT |
| 2026-06-18 | A00036 | Supplemental agreement (work within scope) | -$20.8K | BORROW PIT CREDIT |
| 2026-04-23 | A00035 | Supplemental agreement (work within scope) | $0 | EAST SLIDE REPAIR |
| 2026-03-19 | A00034 | Supplemental agreement (work within scope) | $172.6K | EAST SLIDE REPAIR |
| 2026-03-17 | P00009 | Supplemental agreement (work within scope) | $1.89M | THIS MODIFICATION COMPENSATES THE CONTRACTOR FOR COST IN REA-0009 PART 3. SEE SUMMARY OF CHANGES. |
| 2026-03-05 | P00008 | Supplemental agreement (work within scope) | $6.28M | THIS MODIFICATION COMPENSATES THE CONTRACTOR FOR COST IN REA-0009 PART 2. SEE SUMMARY OF CHANGES. |
| 2026-01-22 | A00033 | Supplemental agreement (work within scope) | $13.7K | 11. THIS ITEM APPLIES ONLY TO AMENDMENTS OF SOLICITATIONS THE ABOVE NUMBERED SOLICITATION IS AMENDED AS SET FORTH IN ITEM 14. THE HOUR AND DATE SPECIFIED FOR RECEIPT OF OFFERS IS EXTENDED, IS NOT EXTENDED OFFERS MUST ACKNOWLEDGE RECEIPT OF THIS AMEN |
| 2025-10-21 | A00032 | Supplemental agreement (work within scope) | $138.1K | REMOVE EMERGENCY BACKFILL PLACED IN TRENCHES IN JUNE 2024. |
| 2025-09-11 | P00007 | Administrative change | $0 | CONTRACT W9126G22C0005 WAS INITIALLY AWARDED WITH THE INCORRECT FAR CLAUSE 52.222-55. THIS MODIFICATION REPLACES THE ERRONEOUSLY INCLUDED CLAUSE WITH THE CORRECT FAR CLAUSE 52.222-55 TO ENSURE COMPLIANCE WITH CURRENT REGULATIONS. |
| 2025-09-04 | P00006 | Change order | $3.04M | THIS MODIFICATION PARTIALLY COMPENSATES THE CONTRACTOR FOR COSTS IN REA-0009, SPECIFICALLY ADDRESSING A DESIGN/SPECIFICATION DEFECT. THE ORIGINAL SPECIFICATION REQUIRED SHOTCRETING A 6-FOOT TRENCH WITHIN 6 HOURS OF EXCAVATION. |
| 2025-07-16 | A00031 | Supplemental agreement (work within scope) | $66.9K | PAYS CONTRACTOR FOR ENGINEER AND DAM SAFETY SUBMITTAL NEEDED TO COMPLY WITH USACE POLICY. REDUCES PAYMENT FOR DRILLED PIERS DUE TO LOCATIONS BEING OUT-OF-TOLERANCE BUT STILL FUNCTIONAL. |
| 2025-06-03 | P00005 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO IMPLEMENT EXECUTIVE ORDER 14173 AND 14148. |
| 2025-05-16 | A00030 | Supplemental agreement (work within scope) | $12.9K | CONTRACTING OFFICER REQUIRED CONTRACTOR TO HEAT CONSTRUCTION JOINT CONCRETE TO 50 DEGREES. |
| 2025-05-13 | A00029 | Supplemental agreement (work within scope) | -$74.2K | ADJUSTS RIP RAP QUANTITIES TO MATCH AMOUNT PLACED AND ADJUSTS PRICE. |
| 2025-05-05 | A00028 | Supplemental agreement (work within scope) | $0 | EXTENDS CONTRACT COMPLETION BECAUSE OF WEATHER DELAYS |
| 2025-05-01 | A00027 | Supplemental agreement (work within scope) | $5.8K | CHANGES ROUTE FOR DRAINAGE FROM BEHIND TRAINING WALL. |
| 2025-04-30 | A00026 | Supplemental agreement (work within scope) | $30.1K | COMPENSATES CONTRACTOR FOR REVISING GRADING PLAN AT BORROW PIT DUE TO 2 DIFFERING SITE CONDITIONS |
| 2025-04-01 | A00025 | Supplemental agreement (work within scope) | $9.8K | REMOVES PASSING PERMEABILITY TESTING AS REQUIREMENT FOR ACCEPTANCE ALLOWS KTR TO USE ADDITIONAL CONCRETE TO MAKE UP FOR UNEVEN SUBGRADE REPLACES 6" PIPE WITH 4" PIPE DUE TO UNEVEN SUBGRADE. |
| 2025-03-24 | A00024 | Supplemental agreement (work within scope) | $26.2K | ADDITIONAL WORK REQUIRED TO DEMO CONCRETE IN TRENCH WHICH WAS NOT IDENTIFIED IN THE PLANS |
| 2025-01-02 | A00023 | Supplemental agreement (work within scope) | $86.8K | REMOVAL OF CONCRETE PLACED IN TRENCHES AS EMERGENCY BACKFILL DUE TO HIGH WATER |
| 2024-11-14 | A00022 | Supplemental agreement (work within scope) | $330.7K | PILE ORIENTATION SURVEY |
| 2024-11-04 | A00021 | Supplemental agreement (work within scope) | $37.7K | EXTRA GRAVITY BLOCK CONCRETE PLACED TO HOLD SAND LAYER THAT WAS THICKER THAN SHOWN IN BORINGS. |
| 2024-10-23 | A00020 | Supplemental agreement (work within scope) | $209.7K | PROVIDES ANCHORS TO SUPPORT SHOTCRETE IN A TRENCH |
| 2024-09-20 | P00004 | Change order | $523.0K | APRON OVERLAY |
| 2024-09-16 | A00018 | Supplemental agreement (work within scope) | $11.4K | APRON OVERLAY |
| 2024-08-23 | A00017 | Change order | $353.6K | APRON OVERLAY |
| 2024-07-19 | A00016 | Supplemental agreement (work within scope) | $95.8K | EXTRA MUD MAT CONCRETE WAS NEEDED DUE TO EXTRA EXCAVATION OF UNSOUND SHALE FOUNDATION. |
| 2024-07-16 | A00015 | Supplemental agreement (work within scope) | $0 | EXTENDS PERIOD OF PERFORMANCE 18 DAYS BECAUSE CONTRACTOR COULD NOT WORK ON CRITICAL ACTIVITIES DUE TO FLOODING. |
| 2024-07-10 | A00014 | Supplemental agreement (work within scope) | $33.6K | COMPENSATES CONTRACTOR FOR ADDITIONAL DEMO WORK PERFORMED DUE TO ERROR IN DRAWINGS. |
| 2024-07-10 | A00013 | Supplemental agreement (work within scope) | $155.6K | ADDITIONAL CORROSION PROTECTION FOR EXPOSED PORTION OF ROCK DOWELS |
| 2024-06-18 | A00012 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION FOR UNUSUALLY SEVERE WEATHER IN MAY 2024. |
| 2024-06-17 | A00011 | Supplemental agreement (work within scope) | $26.8K | CHANGES BATTEN STRIP TO SECURE GEOMEMBRANE, COMPENSATES CONTRACTOR FOR ADDITIONAL GRAVEL BACKFILL, CREDIT FOR NOT HYDROSEEDING COFFERDAM SLOPE. |
| 2024-05-23 | A00010 | Supplemental agreement (work within scope) | $40.8K | INCREASE QUANTITY MORE CONCRETE NEEDED TO BE GRINDED BEYOND WHAT WAS SHOWN IN THE CONTRACT. |
| 2024-04-19 | A00009 | Supplemental agreement (work within scope) | $29.7K | REPLACE ADDITIONAL SECTION OF CONCRETE APRON. |
| 2024-04-18 | A00008 | Supplemental agreement (work within scope) | $5.5K | ADDS CHAMFERED EDGES TO CONCRETE WALL EXTENSION |
| 2024-02-22 | P00003 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD THE APPLICATION OF W AGE DECISIONS TO PROVIDE DETAIL DESCRIPTION TO DETERMINE W HICH W AGE DETERMINATION SCHEDULE TO APPLY BASED UPON THE AREA IN WHICH THE WORK IS BEING PERFORMED. |
| 2024-02-01 | A00007 | Supplemental agreement (work within scope) | $6.9K | A00007 R00007 MI009 ROCK DOWEL PACKER TESTING |
| 2023-10-23 | A00006 | Supplemental agreement (work within scope) | -$35.0K | DECREASE BY $35K AND NO TIME. THIS MOD ADDRESSES AND RESOLVES THE QC DEFICIENCIES 00012, 00013, & 00017. NO COST OR TIME CHANGE TO TRANSITION ROCK DOWELS IN ACCORDANCE WITH REVISED DRAWING SB-342 PROVIDED IN RFI 073 & 075 |
| 2023-10-12 | A00005 | Supplemental agreement (work within scope) | $222.2K | MI006 APRON, ROCK DOWEL & DRAIN RESTRICTIONS, INCREASE $222,169.72, NO TIME ADDED. |
| 2023-08-28 | A00004 | Supplemental agreement (work within scope) | $16.5K | MI005 DRAINAGE SPEC CHANGE |
| 2023-07-27 | A00003 | Supplemental agreement (work within scope) | $34.9K | INCREASE $34,858 & NO TIME. PERFORM TOPOGRAPHIC SURVEYING OF THE ABUTMENTS FOR THE ACROW BRIDGE. |
| 2023-07-07 | A00002 | Supplemental agreement (work within scope) | -$72.0K | DECREASE $72,000.88 AND NO TIME. CHANGES RECESS DRILLING METHOD, ADDRESSES STAGING AREA CHANGES, ADDRESSES THE ACROW BRIDGE CLOSURES, AND COVERS COST ASSOCIATED WITH ADDITIONAL ASR TESTING. |
| 2023-05-31 | A00001 | Supplemental agreement (work within scope) | $291.7K | INCREASE $291,746 AND NO TIME. INSTALL 1 LOAD CELL ON MONOLITHS C, 2, 4, 6, 8, 10, 12, AND D AND INSTALL 13 DYNAFORCE LOAD SENSORS ON MONOLITHS 1 THRU 13 AS SHOWN ON REVISED SHEET BI-102.A. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗