W9126G22C0005↗

Shimmick Construction Company, Inc. received this contract from W076 Endist FT Worth, Department of the Army: $15.31M obligated so far for repair or alteration of dams. It runs to 2026-10-31.

Key facts · data as of Oct 25, 2026

Recipient
Shimmick Construction Company, Inc.
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W076 Endist FT Worth (W9126G)
Obligated to date
$15.31M
Potential value
$91.42M
Ends
2026-10-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award W9126G22C0005, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W9126G22C0005_9700_-NONE-_-NONE-

LEWISVILLE DAM LAKE REPAIRS

Definitive Contract · Department of the Army · to Shimmick Construction Company, Inc. (UEI PNF1UVJ6YE96) · data as of 2026-10-25

Obligated to date$15.31M43 actions
Current value$91.42Mwith options exercised
Period2022-05-24 → 2026-10-31current end date

Up for re-bid: ends 2026-10-31. Recompete brief → · Joe Pool Dam Slide Repairs ↗

What it is

Product or service
Repair or Alteration of Dams (PSC Z2KA)
Industry
Other Heavy and Civil Engineering Construction (NAICS 237990)
Contracting office
W076 Endist FT Worth (W9126G)
Competition
Full and open competition · 3 offers received
Pricing
Firm fixed price
How it was bought
Standalone contract
Solicitation
W9126G21R0004
Where the work is
Denton, TX · district TX-26
Funding law
Other emergency or disaster supplementals

Obligations by fiscal year

FY2023$271.1K
FY2024$1.47M
FY2025$3.78M
FY2026$9.79M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

43 actions since 2023-05-31. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-08P00010Supplemental agreement (work within scope)$1.31MBORROW PIT CREDIT
2026-06-18A00036Supplemental agreement (work within scope)-$20.8KBORROW PIT CREDIT
2026-04-23A00035Supplemental agreement (work within scope)$0EAST SLIDE REPAIR
2026-03-19A00034Supplemental agreement (work within scope)$172.6KEAST SLIDE REPAIR
2026-03-17P00009Supplemental agreement (work within scope)$1.89MTHIS MODIFICATION COMPENSATES THE CONTRACTOR FOR COST IN REA-0009 PART 3. SEE SUMMARY OF CHANGES.
2026-03-05P00008Supplemental agreement (work within scope)$6.28MTHIS MODIFICATION COMPENSATES THE CONTRACTOR FOR COST IN REA-0009 PART 2. SEE SUMMARY OF CHANGES.
2026-01-22A00033Supplemental agreement (work within scope)$13.7K11. THIS ITEM APPLIES ONLY TO AMENDMENTS OF SOLICITATIONS THE ABOVE NUMBERED SOLICITATION IS AMENDED AS SET FORTH IN ITEM 14. THE HOUR AND DATE SPECIFIED FOR RECEIPT OF OFFERS IS EXTENDED, IS NOT EXTENDED OFFERS MUST ACKNOWLEDGE RECEIPT OF THIS AMEN
2025-10-21A00032Supplemental agreement (work within scope)$138.1KREMOVE EMERGENCY BACKFILL PLACED IN TRENCHES IN JUNE 2024.
2025-09-11P00007Administrative change$0CONTRACT W9126G22C0005 WAS INITIALLY AWARDED WITH THE INCORRECT FAR CLAUSE 52.222-55. THIS MODIFICATION REPLACES THE ERRONEOUSLY INCLUDED CLAUSE WITH THE CORRECT FAR CLAUSE 52.222-55 TO ENSURE COMPLIANCE WITH CURRENT REGULATIONS.
2025-09-04P00006Change order$3.04MTHIS MODIFICATION PARTIALLY COMPENSATES THE CONTRACTOR FOR COSTS IN REA-0009, SPECIFICALLY ADDRESSING A DESIGN/SPECIFICATION DEFECT. THE ORIGINAL SPECIFICATION REQUIRED SHOTCRETING A 6-FOOT TRENCH WITHIN 6 HOURS OF EXCAVATION.
2025-07-16A00031Supplemental agreement (work within scope)$66.9KPAYS CONTRACTOR FOR ENGINEER AND DAM SAFETY SUBMITTAL NEEDED TO COMPLY WITH USACE POLICY. REDUCES PAYMENT FOR DRILLED PIERS DUE TO LOCATIONS BEING OUT-OF-TOLERANCE BUT STILL FUNCTIONAL.
2025-06-03P00005Administrative change$0THE PURPOSE OF THIS MODIFICATION IS TO IMPLEMENT EXECUTIVE ORDER 14173 AND 14148.
2025-05-16A00030Supplemental agreement (work within scope)$12.9KCONTRACTING OFFICER REQUIRED CONTRACTOR TO HEAT CONSTRUCTION JOINT CONCRETE TO 50 DEGREES.
2025-05-13A00029Supplemental agreement (work within scope)-$74.2KADJUSTS RIP RAP QUANTITIES TO MATCH AMOUNT PLACED AND ADJUSTS PRICE.
2025-05-05A00028Supplemental agreement (work within scope)$0EXTENDS CONTRACT COMPLETION BECAUSE OF WEATHER DELAYS
2025-05-01A00027Supplemental agreement (work within scope)$5.8KCHANGES ROUTE FOR DRAINAGE FROM BEHIND TRAINING WALL.
2025-04-30A00026Supplemental agreement (work within scope)$30.1KCOMPENSATES CONTRACTOR FOR REVISING GRADING PLAN AT BORROW PIT DUE TO 2 DIFFERING SITE CONDITIONS
2025-04-01A00025Supplemental agreement (work within scope)$9.8KREMOVES PASSING PERMEABILITY TESTING AS REQUIREMENT FOR ACCEPTANCE ALLOWS KTR TO USE ADDITIONAL CONCRETE TO MAKE UP FOR UNEVEN SUBGRADE REPLACES 6" PIPE WITH 4" PIPE DUE TO UNEVEN SUBGRADE.
2025-03-24A00024Supplemental agreement (work within scope)$26.2KADDITIONAL WORK REQUIRED TO DEMO CONCRETE IN TRENCH WHICH WAS NOT IDENTIFIED IN THE PLANS
2025-01-02A00023Supplemental agreement (work within scope)$86.8KREMOVAL OF CONCRETE PLACED IN TRENCHES AS EMERGENCY BACKFILL DUE TO HIGH WATER
2024-11-14A00022Supplemental agreement (work within scope)$330.7KPILE ORIENTATION SURVEY
2024-11-04A00021Supplemental agreement (work within scope)$37.7KEXTRA GRAVITY BLOCK CONCRETE PLACED TO HOLD SAND LAYER THAT WAS THICKER THAN SHOWN IN BORINGS.
2024-10-23A00020Supplemental agreement (work within scope)$209.7KPROVIDES ANCHORS TO SUPPORT SHOTCRETE IN A TRENCH
2024-09-20P00004Change order$523.0KAPRON OVERLAY
2024-09-16A00018Supplemental agreement (work within scope)$11.4KAPRON OVERLAY
2024-08-23A00017Change order$353.6KAPRON OVERLAY
2024-07-19A00016Supplemental agreement (work within scope)$95.8KEXTRA MUD MAT CONCRETE WAS NEEDED DUE TO EXTRA EXCAVATION OF UNSOUND SHALE FOUNDATION.
2024-07-16A00015Supplemental agreement (work within scope)$0EXTENDS PERIOD OF PERFORMANCE 18 DAYS BECAUSE CONTRACTOR COULD NOT WORK ON CRITICAL ACTIVITIES DUE TO FLOODING.
2024-07-10A00014Supplemental agreement (work within scope)$33.6KCOMPENSATES CONTRACTOR FOR ADDITIONAL DEMO WORK PERFORMED DUE TO ERROR IN DRAWINGS.
2024-07-10A00013Supplemental agreement (work within scope)$155.6KADDITIONAL CORROSION PROTECTION FOR EXPOSED PORTION OF ROCK DOWELS
2024-06-18A00012Supplemental agreement (work within scope)$0TIME EXTENSION FOR UNUSUALLY SEVERE WEATHER IN MAY 2024.
2024-06-17A00011Supplemental agreement (work within scope)$26.8KCHANGES BATTEN STRIP TO SECURE GEOMEMBRANE, COMPENSATES CONTRACTOR FOR ADDITIONAL GRAVEL BACKFILL, CREDIT FOR NOT HYDROSEEDING COFFERDAM SLOPE.
2024-05-23A00010Supplemental agreement (work within scope)$40.8KINCREASE QUANTITY MORE CONCRETE NEEDED TO BE GRINDED BEYOND WHAT WAS SHOWN IN THE CONTRACT.
2024-04-19A00009Supplemental agreement (work within scope)$29.7KREPLACE ADDITIONAL SECTION OF CONCRETE APRON.
2024-04-18A00008Supplemental agreement (work within scope)$5.5KADDS CHAMFERED EDGES TO CONCRETE WALL EXTENSION
2024-02-22P00003Administrative change$0THE PURPOSE OF THIS MODIFICATION IS TO ADD THE APPLICATION OF W AGE DECISIONS TO PROVIDE DETAIL DESCRIPTION TO DETERMINE W HICH W AGE DETERMINATION SCHEDULE TO APPLY BASED UPON THE AREA IN WHICH THE WORK IS BEING PERFORMED.
2024-02-01A00007Supplemental agreement (work within scope)$6.9KA00007 R00007 MI009 ROCK DOWEL PACKER TESTING
2023-10-23A00006Supplemental agreement (work within scope)-$35.0KDECREASE BY $35K AND NO TIME. THIS MOD ADDRESSES AND RESOLVES THE QC DEFICIENCIES 00012, 00013, & 00017. NO COST OR TIME CHANGE TO TRANSITION ROCK DOWELS IN ACCORDANCE WITH REVISED DRAWING SB-342 PROVIDED IN RFI 073 & 075
2023-10-12A00005Supplemental agreement (work within scope)$222.2KMI006 APRON, ROCK DOWEL & DRAIN RESTRICTIONS, INCREASE $222,169.72, NO TIME ADDED.
2023-08-28A00004Supplemental agreement (work within scope)$16.5KMI005 DRAINAGE SPEC CHANGE
2023-07-27A00003Supplemental agreement (work within scope)$34.9KINCREASE $34,858 & NO TIME. PERFORM TOPOGRAPHIC SURVEYING OF THE ABUTMENTS FOR THE ACROW BRIDGE.
2023-07-07A00002Supplemental agreement (work within scope)-$72.0KDECREASE $72,000.88 AND NO TIME. CHANGES RECESS DRILLING METHOD, ADDRESSES STAGING AREA CHANGES, ADDRESSES THE ACROW BRIDGE CLOSURES, AND COVERS COST ASSOCIATED WITH ADDITIONAL ASR TESTING.
2023-05-31A00001Supplemental agreement (work within scope)$291.7KINCREASE $291,746 AND NO TIME. INSTALL 1 LOAD CELL ON MONOLITHS C, 2, 4, 6, 8, 10, 12, AND D AND INSTALL 13 DYNAFORCE LOAD SENSORS ON MONOLITHS 1 THRU 13 AS SHOWN ON REVISED SHEET BI-102.A.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗