DESIGN AND CONSTRUCTION CHARLIE PUMP STATION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
14 actions since 2024-05-07. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-26 | A00013 | Supplemental agreement (work within scope) | $0 | CONTRACT NO. W9126G20D0008 W9126G22F0085 CHARLIE 2 PUMP STATION MODIFICATION NO. A00011 WEATHER TIME EXTENSION JUL 25- JAN 26 |
| 2026-03-18 | A00012 | Supplemental agreement (work within scope) | $62.3K | CONTRACT NO. W9126G20D0008 W9126G22F0085 CHARLIE 2 PUMP STATION MODIFICATION NO. A00011 WEATHER TIME EXTENSION JUL 25- JAN 26 |
| 2026-02-24 | A00011 | Supplemental agreement (work within scope) | $0 | CONTRACT NO. W9126G20D0008 W9126G22F0085 CHARLIE 2 PUMP STATION MODIFICATION NO. A00011 WEATHER TIME EXTENSION JUL 25- JAN 26 |
| 2025-12-17 | P00003 | Supplemental agreement (work within scope) | $1.43M | CONTRACT NO. W9126G20D0008 W9126G22F0085 CHARLIE 2 PUMP STATION MODIFICATION NO. A00010 R00012 - DESCOPE LOWER LEVEE ROADDESCRIPTION OF AMENDMENT/MODIFICATION (ORGANIZED BY UCF SECTION HEADINGS, INCLUDING SOLICITATION/CONTRACT SUBJECT MATTER WHERE |
| 2025-11-21 | A00010 | Supplemental agreement (work within scope) | -$196.8K | CHANGE 12: DESCOPE OF LOWER LEVEE ROAD |
| 2025-10-14 | A00009 | Supplemental agreement (work within scope) | $0 | CHANGE 10: TIME DUE TO SUBSURFACE DEBRIS AND CHANGE 11: TIME DUE TO LATE RFI RESPONSE |
| 2025-07-11 | A00008 | Supplemental agreement (work within scope) | $0 | CONSTRUCTION |
| 2025-06-06 | A00007 | Supplemental agreement (work within scope) | $180.1K | CONSTRUCTION CHANGE REQUEST 00006: ORNAMENTAL SECURITY FENCING |
| 2025-04-04 | A00006 | Supplemental agreement (work within scope) | $0 | CONSTRUCTION CHANGE 00007: WEATHER DELAYS SEPTEMBER 2024- FEBRUARY 2025 |
| 2024-09-26 | A00005 | Supplemental agreement (work within scope) | $0 | CR0005 WEATHER TIME EXTENSION MAY 24- AUG 24 |
| 2024-07-03 | A00004 | Supplemental agreement (work within scope) | $28.4K | A00004 R00006 UNSOLICITED PROPOSAL - DIFFERING SOIL (1 APRIL - 15 JUNE 2024) |
| 2024-06-26 | A00003 | Supplemental agreement (work within scope) | $0 | CONSTRUCTION |
| 2024-05-29 | A00002 | Supplemental agreement (work within scope) | $205.8K | A00002 R00004 UNSOLICITED PROPOSAL - DIFFERING SOIL (1 JANUARY 2024 - 31 MARCH 2024) |
| 2024-05-07 | A00001 | Supplemental agreement (work within scope) | $177.3K | CONSTRUCTION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-05). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗