BASE - A DESIGN-BID-BUILD PACKAGE FOR AN ACCESS CONTROL POINT AT ANNISTON ARMY DEPOT, AL
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2024-01-03. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-10-08 | P00003 | Option exercised | $2.27M | EXERCISE OPTION 1 |
| 2024-06-04 | P00002 | Supplemental agreement (work within scope) | $118.2K | WITHIN SCOPE MODIFICATION FOR ACCESS CONTROL POINT ANNISTON ARMY DEPOT AL |
| 2024-03-29 | P00001 | Supplemental agreement (work within scope) | $110.9K | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE WORK FOR TASK ORDER W9127824F0024, CONTRACT W9127821D0006. |
| 2024-01-03 | 0 | $1.48M | BASE - A DESIGN-BID-BUILD PACKAGE FOR AN ACCESS CONTROL POINT AT ANNISTON ARMY DEPOT, AL |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗