W9127826FA096↗

Ses Electrical LLC received this contract from W074 Endist Mobile, Department of the Army: $4.15M obligated so far for construction of hospitals and infirmaries. It runs to 2027-05-03.

Key facts · data as of Oct 25, 2026

Recipient
Ses Electrical LLC
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W074 Endist Mobile (W91278)
Obligated to date
$4.15M
Potential value
$4.15M
Ends
2027-05-03

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award W9127826FA096, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W9127826FA096_9700_W9127826DA026_9700

REPLACE THE EXISTING ROOF SYSTEM AT KELLER ARMY COMMUNITY HOSPITAL (KACH) AT WEST POINT, NEW YORK

Delivery Order · Department of the Army · to Ses Electrical LLC (UEI HNUQVSS87HA5) · data as of 2026-10-25

Obligated to date$4.15M2 actions
Current value$4.15Mwith options exercised
Period2026-03-31 → 2027-05-03current end date

Up for re-bid: ends 2027-05-03. Recompete brief → · Market Intelligence - Progressive Design-Build - Blood Donation Center ↗

What it is

Product or service
Construction of Hospitals and Infirmaries (PSC Y1DA)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
W074 Endist Mobile (W91278)
Competition
Full and open competition · 9 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under W9127826DA026
Solicitation
W9127825RA007
Where the work is
Orange, NY · district NY-18

Obligations by fiscal year

FY2026$4.15M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

2 actions since 2026-03-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-06-25P00001Funding only$0REPLACE THE EXISTING ROOF SYSTEM AT KELLER ARMY COMMUNITY HOSPITAL (KACH) AT WEST POINT, NEW YORK
2026-03-300$4.15MREPLACE THE EXISTING ROOF SYSTEM AT KELLER ARMY COMMUNITY HOSPITAL (KACH) AT WEST POINT, NEW YORK

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗