!!PR-POWERFY23!! TEMPORARY POWER GENERATION AT THE SAN JUAN POWER PLANT
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
14 subawards totaling $644.83M (96.4% of what was obligated), as Weston Solutions Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Nfenergia LLC | $512.23M | 4 | PR | 2023-04-19 | 2024-05-14 |
| Nfe Power PR LLC | $132.24M | 6 | PR | 2023-04-19 | 2024-04-12 |
| Decons Energy, LLC | $337.0K | 3 | FL | 2023-07-05 | 2023-08-28 |
| Pro-Energy, Corp. | $35.0K | 1 | PR | 2023-09-06 | 2023-09-06 |
| Date | To | Amount | For |
|---|---|---|---|
| 2023-04-19 | Nfenergia LLC | $407.68M | POWER GENERATION SERVICES |
| 2024-02-28 | Nfenergia LLC | $104.47M | CHANGE ORDERS 3-4 ADDITIONAL SERVICES |
| 2023-04-19 | Nfe Power PR LLC | $82.94M | POWER GENERATION SERVICES |
| 2023-06-14 | Nfe Power PR LLC | $16.20M | CHANGE ORDER 2 ADDITIONAL SERVICES |
| 2024-02-28 | Nfe Power PR LLC | $14.80M | CHANGE ORDER 5 ADDITIONAL SERVICES |
| 2023-08-15 | Nfe Power PR LLC | $12.69M | CHANGE ORDER 3 ADDITIONAL SERVICES |
| 2024-04-12 | Nfe Power PR LLC | $3.60M | CHANGE ORDER 6 ADDITIONAL SERVICES |
| 2023-11-27 | Nfe Power PR LLC | $2.00M | CHANGE ORDER 4 ADDITIONAL SERVICES |
| 2023-08-28 | Decons Energy, LLC | $151.0K | CHANGE ORDER 3 ADDITIONAL SERVICES |
| 2023-07-05 | Decons Energy, LLC | $138.0K | CHANGE ORDER 2 ADDITIONAL SERVICES |
| 2024-05-14 | Nfe Power PR LLC | $75.0K | CHANGE ORDER 7 ADDITIONAL SERVICES |
| 2023-08-22 | Decons Energy, LLC | $48.0K | CHANGE ORDER 1 ADDITIONAL SERVICES |
| 2023-09-06 | Pro-Energy, Corp. | $35.0K | SCADA EQUIPMENT |
| 2023-08-14 | Nfenergia LLC | $1.3K | CHANGE ORDER 2 ADDITIONAL SERVICES |
7 actions since 2023-04-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-26 | P00006 | Funding only | $75.05M | TEMPORARY POWER - SAN JUAN POWER PLANT - REA SETTLEMENT |
| 2025-12-30 | P00005 | Supplemental agreement (work within scope) | $0 | TEMPORARY POWER - SAN JUAN POWER PLANT - REA SETTLEMENT |
| 2025-07-15 | P00004 | Supplemental agreement (work within scope) | $0 | POP EXTENSION FOR ADMINISTRATIVE TASKS - TEMP. POWER GENERATION - SAN JUAN |
| 2024-04-19 | P00003 | Supplemental agreement (work within scope) | $0 | POP EXT, TEMP. POWER GENERATION - SAN JUAN |
| 2024-02-13 | P00002 | Funding only | $35.65M | UNDERRUN VARIANCE FOR LNG TO MAINTAIN OPERATIONS AT SAN JUAN POWER PLANT, SAN JUAN |
| 2023-08-10 | P00001 | Supplemental agreement (work within scope) | $35.41M | SAN JUAN PWR PLANT MODIFICATION, PUERTO RICO |
| 2023-04-10 | 0 | $522.84M | !!PR-POWERFY23!! TEMPORARY POWER GENERATION AT THE SAN JUAN POWER PLANT |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗