Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
22 actions since 2024-05-23. Each is a modification or amendment with the money it added or took back.
Date
Modification
Kind
Amount
What the agency wrote
2026-06-11
P00005
Administrative change
$0
PHASE MAINTENANCE HANGER EXERCISE OPTION CLIN 0007 - PRECONDITIONED AIR UNITS. ENTIRE WORK COMPLETE FOR PROCUREMENT, INSTALLATION, COMMISSIONING, AND CYBERSECURITY OF PRECONDITIONED AIR UNITS.
2026-04-17
A00016
Supplemental agreement (work within scope)
$348.6K
PHASE MAINTENANCE HANGER EXERCISE OPTION CLIN 0007 - PRECONDITIONED AIR UNITS. ENTIRE WORK COMPLETE FOR PROCUREMENT, INSTALLATION, COMMISSIONING, AND CYBERSECURITY OF PRECONDITIONED AIR UNITS.
2026-03-18
P00004
Option exercised
$674.5K
PHASE MAINTENANCE HANGER EXERCISE OPTION CLIN 0007 - PRECONDITIONED AIR UNITS. ENTIRE WORK COMPLETE FOR PROCUREMENT, INSTALLATION, COMMISSIONING, AND CYBERSECURITY OF PRECONDITIONED AIR UNITS.
2026-03-06
A00015
Supplemental agreement (work within scope)
$207.3K
PROJECT INCLUDES 73K SF, PHASE MAINTENANCE HANGAR (PHASE HANGAR) WITH A 2 AIRCRAFT SERVICING BAYS, ALL ASSOCIATED BACK SHOP, ADMIN., FACILITY SUPPORT SPACES, AND AIRFIELD APRON. THIS PROJECT WILL INCLUDE SPACES CONSTRUCTED TO ICD/ICS 705 STANDARDS.
2026-02-09
A00014
Supplemental agreement (work within scope)
$7.8K
PROJECT INCLUDES 73K SF, PHASE MAINTENANCE HANGAR (PHASE HANGAR) WITH A 2 AIRCRAFT SERVICING BAYS, ALL ASSOCIATED BACK SHOP, ADMIN., FACILITY SUPPORT SPACES, AND AIRFIELD APRON. THIS PROJECT WILL INCLUDE SPACES CONSTRUCTED TO ICD/ICS 705 STANDARDS.
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
$499.7K
CD B-21 PHASE HANGAR - R00013 REROUTE COMM DUCTBANK & EXISTING UTILITIES
2025-09-09
A00010
Supplemental agreement (work within scope)
$96.6K
CD: B-21 PHASE MAINTENANCE HANGER {EAFB} - R00017 (R00015 REPAIR JET FUEL LINE AND R00017 LOWER WATER LINE)
2025-09-03
A00009
Supplemental agreement (work within scope)
$0
CD: B-21 PHASE MAINTENANCE HANGER {EAFB} - R00018 WEATHER DELAY THROUGH JULY 2025
THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE LINE ITEMS 0008, 0010, 0011 IN THE AMOUNT OF $1,003,423.00. AND COMPLIANCE WITH CLASS DEVIATION 2025-O0003
2025-02-21
A00003
Supplemental agreement (work within scope)
$432.0K
CD: B-21 PHASE MAINTENANCE HANGER {EAFB} - R00004 R/2 ADD UNIT HEATER AND R/4 ELEC RECEPTICLES FOR AGES