W9128F26CA012↗
Koontz Electric Company, Incorporated received this contract from W071 Endist Omaha, Department of the Army: $14.00M obligated so far for maintenance of dams. It runs to 2028-01-13.
Key facts · data as of Oct 25, 2026
- Recipient
- Koontz Electric Company, Incorporated
- Awarding agency
- Department of the Army (Department of Defense)
- Contracting office
- W071 Endist Omaha (W9128F)
- Obligated to date
- $14.00M
- Potential value
- $15.48M
- Ends
- 2028-01-13
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award W9128F26CA012, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W9128F26CA012_9700_-NONE-_-NONE-
Koontz Electric Company, Incorporated: all federal awards · Department of Defense: spending · W071 Endist Omaha: what it buys · The follow-on: recompete brief
PROJECT TITLE: POWERHOUSE 1 CUBICLE ROOM 15KV SWITCHGEAR UPGRADE, FORT PECK, MONTANA. PROJECT LOCATION: FORT PECK DAM, MONTANA
Up for re-bid: ends 2028-01-13. Recompete brief → · Two Phase Design-Build/Design-Bid-Build (DB/DBB) Multiple Award Task Order Contract (MATOC) for Construction of the Ground Based Strategic Deterrent (GBSD) Utility Corridor (UC) at Francis E. Warren Air Force Base (FEW AFB), Wyoming (WY) ↗
What it is
- Product or service
- Maintenance of Dams (PSC Z1KA)
- Industry
- Power and Communication Line and Related Structures Construction (NAICS 237130)
- Contracting office
- W071 Endist Omaha (W9128F)
- Competition
- Full and open competition · 7 offers received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Where the work is
- Valley, MT · district MT-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
3 actions since 2026-01-30. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-14 | A00001 | Supplemental agreement (work within scope) | $11.5K | PROJECT TITLE: POWERHOUSE 1 CUBICLE ROOM 15KV SWITCHGEAR UPGRADE, FORT PECK, MONTANA. PROJECT LOCATION: FORT PECK DAM, MONTANA |
| 2026-05-21 | P00001 | Supplemental agreement (work within scope) | $0 | PROJECT TITLE: POWERHOUSE 1 CUBICLE ROOM 15KV SWITCHGEAR UPGRADE, FORT PECK, MONTANA. PROJECT LOCATION: FORT PECK DAM, MONTANA |
| 2026-01-30 | 0 | $13.99M | PROJECT TITLE: POWERHOUSE 1 CUBICLE ROOM 15KV SWITCHGEAR UPGRADE, FORT PECK, MONTANA. PROJECT LOCATION: FORT PECK DAM, MONTANA |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗