SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
23 subawards totaling $114.90M (76.9% of what was obligated), as Harper Construction Company, Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
17 actions since 2022-12-23. Each is a modification or amendment with the money it added or took back.
Date
Modification
Kind
Amount
What the agency wrote
2025-09-16
A00012
Supplemental agreement (work within scope)
$152.4K
5-COAT EPOXY ENHANCEMENT SYSTEM
2025-09-08
A00011
Change order
$0
INCREMENT 1
2025-05-30
A00010
Change order
$13.0K
GSE PAVING CHANGE
2025-05-08
A00009
Change order
$0
INCREMENT 1
2025-04-09
P00005
Administrative change
$0
MODIFICATION IS TO IMPLEMENT CLAUSE CHANGES DIRECTED BY EXECUTIVE ORDER.
2025-03-27
A00008
Change order
$0
INCREMENT 1
2024-11-25
A00007
Change order
$0
INCREMENT 1
2024-07-31
P00004
Change order
$35.0K
INCREMENT 1
2024-06-24
A00005
Supplemental agreement (work within scope)
$0
TG007 WEATHER TIME EXTENSION NOV 23 - MAR 24
2024-05-07
P00003
Funding only
$76.85M
MODIFICATION TO ADD THE FINAL FUNDING INCREMENT IN THE AMOUNT OF $76,848,819.00 FOR THE KC-46A 3-BAY DEPOT MAINTENANCE HANGAR AT TINKER AFB, OK.
2024-05-03
P00002
Option exercised
$6.28M
MODIFICATION TO EXERCISE OPTIONS 5, 6, & 7.
2024-04-03
A00004
Supplemental agreement (work within scope)
$183.8K
TG004 INSTALL LOW POINT DRAINS PITS
2024-02-16
A00003
Change order
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗