Kiewit Infrastructure South Co received this contract from W076 Endist Tulsa, Department of the Army: $32.77M obligated so far for construction of highways, roads, streets, bridges, and railways. It runs to 2027-07-22.
Key facts · data as of Oct 22, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award W912BV25C0012, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_W912BV25C0012_9700_-NONE-_-NONE-
Kiewit Infrastructure South Co: all federal awards · Department of Defense: spending · W076 Endist Tulsa: what it buys · The follow-on: recompete brief
PROJECT REQUIRES DEMOLITION TENKILLER BRIDGE IN SEQUOYAH COUNTY, DESIGN/CONSTRUCTION OF TEMPORARY ELECTRICAL AND SAFETY WALKWAYS, CONSTRUCTION OF A NEW BRIDGE, NEW ELECTRICAL/CATWALKS/WATER LINES, AND FULL SITE RESTORATION.
Up for re-bid: ends 2027-07-22. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2025-05-15. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-23 | P00002 | Supplemental agreement (work within scope) | $2.89M | PART 1 OF THIS MODIFICATION WILL ALLOW THE CONTRACTOR TO PROCURE THE WIRE ROPES AND BEGIN OFFSITE FABRICATION OF THIS REQUIRED FEATURE. |
| 2026-03-26 | P00001 | Supplemental agreement (work within scope) | $1.18M | PART 1 OF THIS MODIFICATION WILL ALLOW THE CONTRACTOR TO PROCURE THE WIRE ROPES AND BEGIN OFFSITE FABRICATION OF THIS REQUIRED FEATURE. |
| 2026-03-20 | A00001 | Administrative change | $0 | MEET THE REQUIREMENTS LISTED IN THE SOLICITATION. |
| 2025-05-15 | 0 | $28.70M | PROJECT REQUIRES DEMOLITION TENKILLER BRIDGE IN SEQUOYAH COUNTY, DESIGN/CONSTRUCTION OF TEMPORARY ELECTRICAL AND SAFETY WALKWAYS, CONSTRUCTION OF A NEW BRIDGE, NEW ELECTRICAL/CATWALKS/WATER LINES, AND FULL SITE RESTORATION. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗