Olsson Industrial Electric, Inc received this contract from W071 Endist Seattle, Department of the Army: $14.13M obligated so far for construction of other non-building facilities. It runs to 2028-05-03.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award W912DW25C0003, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W912DW25C0003_9700_-NONE-_-NONE-
Olsson Industrial Electric, Inc: all federal awards · Department of Defense: spending · W071 Endist Seattle: what it buys · The follow-on: recompete brief
REPLACEMENT, DEMOLITION, INSTALLATION, AND/OR REFURBISHMENT OF ISOLATED PHASE BUS SECTIONS AT CHIEF JOSEPH DAM, BRIDGEPORT, WA.
Up for re-bid: ends 2028-05-03. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
2 subawards totaling $5.66M (40.1% of what was obligated), as Olsson Industrial Electric, Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| RMS Energy Co LLC | $3.20M | 1 | MN | 2025-03-20 | 2025-03-20 |
| Arkgalv, LLC | $2.46M | 1 | MS | 2025-03-25 | 2025-03-25 |
| Date | To | Amount | For |
|---|---|---|---|
| 2025-03-20 | RMS Energy Co LLC | $3.20M | REFURBISHMENT AND TESTING OF REMAINING SECTIONS OF ISO- PHASE BUS FOR UNITS 1-16 |
| 2025-03-25 | Calvert Company, Inc., the | $2.46M | FURNISH NEW AND REFURBISH REMAINING PARTS ISO-PHASE BUS FOR UNITS 1-16 |
6 actions since 2024-12-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-01-29 | P00005 | Funding only | $7.38M | CHIEF JOSEPH DAM (CJD) ISO-PHASE POWERBUS UNITS 1-16, BRIDGEPORT, WA |
| 2026-01-09 | P00004 | Supplemental agreement (work within scope) | $579.6K | CHIEF JOSEPH DAM (CJD) ISO-PHASE POWERBUS UNITS 1-16, BRIDGEPORT, WA |
| 2025-06-26 | P00003 | Administrative change | $0 | REPLACEMENT, DEMOLITION, INSTALLATION, AND/OR REFURBISHMENT OF ISOLATED PHASE BUS SECTIONS AT CHIEF JOSEPH DAM, BRIDGEPORT, WA. |
| 2025-05-01 | P00002 | Subcontracting plan added | $0 | REPLACEMENT, DEMOLITION, INSTALLATION, AND/OR REFURBISHMENT OF ISOLATED PHASE BUS SECTIONS AT CHIEF JOSEPH DAM, BRIDGEPORT, WA. |
| 2025-04-07 | P00001 | Funding only | $5.51M | REPLACEMENT, DEMOLITION, INSTALLATION, AND/OR REFURBISHMENT OF ISOLATED PHASE BUS SECTIONS AT CHIEF JOSEPH DAM, BRIDGEPORT, WA. |
| 2024-12-10 | 0 | $654.7K | REPLACEMENT, DEMOLITION, INSTALLATION, AND/OR REFURBISHMENT OF ISOLATED PHASE BUS SECTIONS AT CHIEF JOSEPH DAM, BRIDGEPORT, WA. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗