W912DY21F0490↗

M. C. Dean, Inc. received this contract from W2V6 USA Eng SPT CTR Huntsvil, Department of the Army: $165.6K obligated so far for installation of equipment- electrical and electronic equipment components. Its period of performance ended 2025-09-30.

Key facts · data as of Oct 25, 2026

Recipient
M. C. Dean, Inc.
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W2V6 USA Eng SPT CTR Huntsvil (W912DY)
Obligated to date
$165.6K
Potential value
$1.64M
Ends
2025-09-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award W912DY21F0490, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W912DY21F0490_9700_W912DY20D0034_9700

UPGRADE THE UTILITY MONITORING AND CONTROL SYSTEM (UMCS), SUPERVISORY CONTROL & DATA ACQUISITION (SCADA) SYSTEM, AND OTHER VARIOUS SYSTEMS AT CHIEVRES AIR BASE AND DAUMERIE CASERNE, BELGIUM

Delivery Order · Department of the Army · to M. C. Dean, Inc. (UEI RD55NEXJ5EW4) · data as of 2026-10-25

Obligated to date$165.6K3 actions
Current value$1.64Mwith options exercised
Period2021-09-30 → 2025-09-30current end date

What it is

Product or service
Installation of Equipment- Electrical and Electronic Equipment Components (PSC N059)
Industry
Computer Systems Design Services (NAICS 541512)
Contracting office
W2V6 USA Eng SPT CTR Huntsvil (W912DY)
Competition
Full and open competition · 2 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under W912DY20D0034
Solicitation
W912DY17R0014
Where the work is
BEL

Obligations by fiscal year

FY2023$154.4K
FY2024$0
FY2025$11.3K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2023-01-08. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-03-05P00003Supplemental agreement (work within scope)$11.3KMODIFICATION IS FOR ECO-02.
2024-01-03P00002Administrative change$0POP EXTENSION
2023-01-08P00001Additional work (new agreement)$154.4KECO-01 TASK 1: UMCS AND SCADA UPGRADE