W912EE26CA003↗

Ses Constructors LLC received this contract from W07V Endist Vicksburg, Department of the Army: $6.82M obligated so far for construction of other non-building facilities. It runs to 2026-11-13.

Key facts · data as of Oct 25, 2026

Recipient
Ses Constructors LLC
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W07V Endist Vicksburg (W912EE)
Obligated to date
$6.82M
Potential value
$13.98M
Ends
2026-11-13

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award W912EE26CA003, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W912EE26CA003_9700_-NONE-_-NONE-

DESOTO AND TATE COUNTIES, MISSISSIPPI, ARKABUTLA DAM MAINTENANCE IRRM PHASE 2, FC/MRT, YAZOO RIVER BASIN, COLDWATER RIVER, ARKABUTLA LAKE

Definitive Contract · Department of the Army · to Ses Constructors LLC (UEI NM92J7GT4FG5) · data as of 2026-10-25

Obligated to date$6.82M7 actions
Current value$10.35Mwith options exercised
Potential value$13.98Mif every option is used
Period2025-11-08 → 2026-11-13current end date

Up for re-bid: ends 2026-11-13. Recompete brief → · CONCORDIA PARISH, LOUISIANA; FC/MR and T, WBMRL; LEVEE, ENLARGEMENT AND BERMS; UPPER LAKE CONCORDIA - VIDALIA, ITEM 367-R ↗

What it is

Product or service
Construction of Other Non-Building Facilities (PSC Y1PZ)
Industry
Other Heavy and Civil Engineering Construction (NAICS 237990)
Contracting office
W07V Endist Vicksburg (W912EE)
Competition
Not competed under simplified acquisition · 1 offer received
Set-aside
8(a) sole source
Pricing
Firm fixed price
How it was bought
Standalone contract
Where the work is
Warren, MS · district MS-02

Obligations by fiscal year

FY2026$6.82M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

7 actions since 2025-11-13. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-10P00002Option exercised$737.0KNO COST CHANGE
2026-06-03A00004Change order$0NO COST CHANGE
2026-05-20A00003Supplemental agreement (work within scope)$7.2KDRILLING PILOT HOLE CORES.
2026-04-24P00001Option exercised$433.2KADMINISTRATIVE CHANGE TO PERIOD OF PERFORMANCE
2026-04-07A00002Change order$0ADMINISTRATIVE CHANGE TO PERIOD OF PERFORMANCE
2026-03-11A00001Change order$0NO COST CHANGE
2025-11-130$5.64MDESOTO AND TATE COUNTIES, MISSISSIPPI, ARKABUTLA DAM MAINTENANCE IRRM PHASE 2, FC/MRT, YAZOO RIVER BASIN, COLDWATER RIVER, ARKABUTLA LAKE