W912EF22C0004↗
Knight Const. & Supply, Inc received this contract from US Army Engineer District Walla Wal, Department of the Army: $78.42M obligated so far for repair or alteration of dams. It runs to 2031-06-14.
Key facts · data as of Oct 23, 2026
- Recipient
- Knight Const. & Supply, Inc
- Awarding agency
- Department of the Army (Department of Defense)
- Contracting office
- US Army Engineer District Walla Wal (W912EF)
- Obligated to date
- $78.42M
- Potential value
- $141.62M
- Ends
- 2031-06-14
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award W912EF22C0004, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W912EF22C0004_9700_-NONE-_-NONE-
Knight Const. & Supply, Inc: all federal awards · Department of Defense: spending · US Army Engineer District Walla Wal: what it buys
MCNARY INTAKE GATES AND ISOPHSE BUS SYSTEMS
What it is
- Product or service
- Repair or Alteration of Dams (PSC Z2KA)
- Industry
- Other Heavy and Civil Engineering Construction (NAICS 237990)
- Contracting office
- US Army Engineer District Walla Wal (W912EF)
- Competition
- Full and open competition · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- W912EF21R0015
- Where the work is
- Umatilla, OR · district OR-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
5 subawards totaling $5.86M (7.5% of what was obligated), as Knight Const. & Supply, Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Piw TSG, LLC | $2.59M | 1 | OR | 2025-02-07 | 2025-02-07 |
| Fabrication Products Inc | $2.26M | 1 | WA | 2025-02-07 | 2025-02-07 |
| Innovative Hydraulics LLC | $726.8K | 1 | WI | 2025-07-17 | 2025-07-17 |
| Farwest Corrosion Control Co | $240.5K | 1 | CA | 2024-05-14 | 2024-05-14 |
| Haskins Steel Co Inc | $45.9K | 1 | WA | 2023-09-07 | 2023-09-07 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-02-07 | Piw TSG, LLC | $2.59M | HEAVY INDUSTRIAL MACHINING; GUIDE ROLLER, PINS, GATE CYLINDER SUPPORT AND ALIGNMENT BLOCKS |
| 2025-02-07 | Fabrication Products Inc | $2.26M | SUPPLY MCNARY SUPPORT BEAMS, ASSEMBLIES AND PRODUCT TESTING. |
| 2025-07-17 | Innovative Hydraulics LLC | $726.8K | CYLINDER TESTING |
| 2024-05-14 | Farwest Corrosion Control Co | $240.5K | ANODE VERIFICATION TESTING |
| 2023-09-07 | Haskins Steel Co Inc | $45.9K | CYLINDER STORAGE STRUCTURE MATERIALS |
Every action
36 actions since 2023-03-24. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-08 | A00024 | Supplemental agreement (work within scope) | $257.5K | ACCESS COVER IPB COND TO LV BUSHING FOR MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-06-04 | P00011 | Change order | $960.9K | ACCESS COVER IPB COND TO LV BUSHING FOR MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-05-14 | A00023 | Supplemental agreement (work within scope) | $230.3K | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-04-09 | A00022 | Supplemental agreement (work within scope) | $247.0K | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-03-19 | P00010 | Change order | $1.14M | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-03-12 | A00021 | Supplemental agreement (work within scope) | $409.8K | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-03-06 | A00020 | Supplemental agreement (work within scope) | $497.4K | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-03-03 | A00019 | Supplemental agreement (work within scope) | $455.9K | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM |
| 2026-01-28 | P00009 | Funding only | $25.17M | MNA INTAKE GATES AND ISOPHASE BUS SYSTEM FY26 INCREMENTAL FUNDING ADDED. |
| 2025-10-02 | A00018 | Supplemental agreement (work within scope) | $356.0K | CR065 TITLE: CORROSION INVESTIGATION PHASE 3 (TASK 3) |
| 2025-09-24 | A00017 | Supplemental agreement (work within scope) | $228.0K | A00017 (CR070 TUBULAR BUS WEEP HOLES & CR071 IHL STORAGE 2025 APRIL THROUGH AUGUST) |
| 2025-09-18 | A00016 | Supplemental agreement (work within scope) | $206.1K | CR043 LIFTING EYE PIN REMOVAL(GATE 02) CR067 CLEAN CYLINDERS 1-16 |
| 2025-09-12 | P00008 | Change order | $673.1K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2025-07-23 | A00015 | Supplemental agreement (work within scope) | $223.7K | A00015 - CR005, CR017, CR062 |
| 2025-07-15 | P00007 | Change order | $849.7K | MNA INTAKE GATE & ISOPHASE MODIFICATION FOR CYLINDER CORROSION TESTING PHASE 3 - TASK 2 |
| 2025-06-18 | A00014 | Administrative change | $222.6K | CR013-2, CR035, CR047, CR058 & CR059 |
| 2025-06-09 | P00006 | Change order | $3.94M | MNA ISOPHASE & INTAKE GATE - DISCONNECT SWITCHED MODIFICATION |
| 2025-04-29 | A00013 | Supplemental agreement (work within scope) | $3.9K | FINAL SF FOR SPARE GATE (#2) PAINT REPAIR |
| 2025-04-03 | A00012 | Administrative change | $19.9K | REA - 8/28/24 WORK STOPPAGE |
| 2025-03-31 | PP0001 | Administrative change | $0 | IMPLEMENT EXECUTIVE ORDER 14148 INITIAL RESCISSIONS OF HARMFUL EXECUTIVE ORDERS AND ACTIONS AND CLASS DEVIATION 2025-O0004-REVOCATION OF EXECUTIVE ORDER ON SUSTAINABILITY |
| 2025-03-21 | P00005 | Funding only | $10.28M | MCNARY INTAKE GATES & ISOPHASE BUS SYSTEM FY 25 INCREMENTAL FUNDS ADDED. |
| 2025-02-03 | A00011 | Administrative change | $125.0K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-09-30 | A00010 | Administrative change | $50.2K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-09-13 | A00009 | Administrative change | $39.9K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-08-14 | P00004 | Funding only | $9.51M | MODIFICATION TO PROVIDE FOR ADDITIONAL INCREMENTAL FUNDING. |
| 2024-08-06 | A00008 | Administrative change | $38.4K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-07-17 | A00007 | Administrative change | $479.3K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-06-18 | A00006 | Administrative change | $7.3K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-06-06 | P00003 | Supplemental agreement (work within scope) | -$3.51M | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-04-16 | A00005 | Administrative change | $13.8K | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-02-22 | A00004 | Administrative change | $3.66M | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-02-06 | A00003 | Administrative change | $0 | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2024-01-22 | P00002 | Funding only | $13.94M | MODIFICATION TO PROVIDE FOR ADDITIONAL INCREMENTAL FUNDING. |
| 2023-09-21 | A00002 | Change order | $137.5K | NITRONIC NUTS FOR INTAKE GATE SEALS |
| 2023-09-20 | A00001 | Administrative change | $0 | PRE-MAIN UNIT OUTAGE HYDRAULIC |
| 2023-03-24 | P00001 | Funding only | $7.55M | MODIFICATION TO ADD FISCAL YEAR 23 INCREMENTAL FUNDS. |