W912EK26CA004↗
J. F. Brennan Company, Inc. received this contract from W07V Endist Rock Island, Department of the Army: $113.85M obligated so far for construction of dams. It runs to 2029-04-29.
Key facts · data as of Oct 25, 2026
- Recipient
- J. F. Brennan Company, Inc.
- Awarding agency
- Department of the Army (Department of Defense)
- Contracting office
- W07V Endist Rock Island (W912EK)
- Obligated to date
- $113.85M
- Potential value
- $117.75M
- Ends
- 2029-04-29
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award W912EK26CA004, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W912EK26CA004_9700_-NONE-_-NONE-
J. F. Brennan Company, Inc.: all federal awards · Department of Defense: spending · W07V Endist Rock Island: what it buys
BRANDON ROAD INTERBASIN PROJECT, INCREMENT 1-A CONSTRUCTION
What it is
- Product or service
- Construction of Dams (PSC Y1KA)
- Industry
- Other Heavy and Civil Engineering Construction (NAICS 237990)
- Funded by
- Corps of Engineers - Civil Works
- Contracting office
- W07V Endist Rock Island (W912EK)
- Competition
- Full and open competition · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- W912EK25R0007
- Where the work is
- Will, IL · district IL-14
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
4 actions since 2026-04-11. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-23 | P00002 | Administrative change | $0 | BRANDON ROAD INTERBASIN PROJECT, INCREMENT 1-A CONSTRUCTION |
| 2026-07-15 | A00001 | Supplemental agreement (work within scope) | $0 | BRANDON ROAD INTERBASIN PROJECT, INCREMENT 1-A CONSTRUCTION |
| 2026-06-10 | P00001 | Administrative change | $0 | BRANDON ROAD INTERBASIN PROJECT, INCREMENT 1-A CONSTRUCTION. MODIFICATION TO SET THE CONTRACT COMPLETION DATE OF 04/29/29 BASED ON THE CONTRACTOR'S ACKNOWLEDGED NTP DATED 04/30/26 AND ADD CLAUSE RFO FAR 52.222-90 |
| 2026-04-11 | 0 | $113.85M | BRANDON ROAD INTERBASIN PROJECT, INCREMENT 1-A CONSTRUCTION |