General Constructors Inc. of the Quad Cities received this contract from W07V Endist Rock Island, Department of the Army: $39.75M obligated so far for construction of restoration of real property (public or private). It runs to 2029-01-23.
Key facts · data as of Oct 22, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award W912EK26CA016, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_W912EK26CA016_9700_-NONE-_-NONE-
General Constructors Inc. of the Quad Cities: all federal awards · Department of Defense: spending · W07V Endist Rock Island: what it buys
CEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT, REACH 4 PHASE 1 DOWNSTREAM RIVER FLOODWALL AND PUMP STATION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
2 actions since 2026-05-01. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-08 | P00001 | Administrative change | $0 | CEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT, REACH 4 PHASE 1 DOWNSTREAM RIVER FLOODWALL AND PUMP STATION. MODIFICATION TO SE THE CONTRACT COMPLETION DATE BASED ON THE CONTRACTOR'S ACKNOWLEDGED NTP AND ADD CLAUSE RFO FAR 52.222-90 |
| 2026-05-01 | 0 | $39.75M | CEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT, REACH 4 PHASE 1 DOWNSTREAM RIVER FLOODWALL AND PUMP STATION |