Forgen-Odin JV received this contract from W074 Endist Jacksnvlle, Department of the Army: $421.93M obligated so far for construction of dams. It runs to 2028-03-15.
Key facts · data as of Oct 21, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.
Cite this page: SpendQuery, Award W912EP22C0017, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_W912EP22C0017_9700_-NONE-_-NONE-
Forgen-Odin JV: all federal awards · Department of Defense: spending · W074 Endist Jacksnvlle: what it buys · The follow-on: recompete brief
CENTRAL EVERGLADES PLANNING PROJECT (CEPP) CONTRACT 11A, EVERGLADES AGRICULTURAL AREA (EAA) A-2 RESERVOIR FOUNDATION & CUTOFF WALL PROJECT
Up for re-bid: ends 2028-03-15. Recompete brief → · Water Resources Brach Quarterly Industry Day for Coastal and Navigation Projects ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
32 actions since 2022-11-30. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-20 | P00023 | Change order | -$739.6K | CENTRAL EVERGLADES PLANNING PROJECT (CEPP) CONTRACT 11A, EVERGLADES AGRICULTURAL AREA (EAA) A-2 RESERVOIR FOUNDATION AND CUTOFF WALL PROJECT, PALM BEACH COUNTY, FLORIDA |
| 2026-07-10 | P00022 | Change order | $0 | 370939 CEPP EAA CNT 11A A-2 FOUNDATION DEI MODIFICATION |
| 2026-06-12 | P00020 | Supplemental agreement (work within scope) | -$39.61M | 370939 CEPP EAA CNT 11A A-2 FOUNDATION |
| 2026-06-01 | P00019 | Supplemental agreement (work within scope) | $586.9K | 370939 CEPP EAA CNT 11A A-2 FOUNDATION |
| 2026-05-19 | P00018 | Supplemental agreement (work within scope) | $2.49M | 370939 CEPP EAA CNT 11A A-2 FOUNDATION |
| 2026-04-16 | P00017 | Supplemental agreement (work within scope) | -$524.7K | CONTRACT NO. W912EP22C0017 370939 CEPP EAA CNT 11A A-2 FOUNDATION EF027 INTERIM VEQ - CLINS 0085 AND 0087REFERENCE NO. R00028 |
| 2026-02-24 | A00010 | Supplemental agreement (work within scope) | $396.9K | CONTRACT NO. W912EP22C0017 370939 CEPP EAA CNT 11A A-2 FOUNDATION EF027 INTERIM VEQ - CLINS 0085 AND 0087REFERENCE NO. R00028 |
| 2026-01-27 | P00016 | Change order | $222.56M | CONTRACT NO. W912EP22C0017 370939 CEPP EAA CNT 11A A-2 FOUNDATION REDUCTION OF PERIOD OF PERFORMANCEREFERENCE NO. R00027 |
| 2025-09-12 | P00015 | Supplemental agreement (work within scope) | -$3.19M | CNT 11A A-2 FOUNDATION (TEMP. QA LAB DE-SCOPE AND ADD EQUIPMENT) |
| 2025-09-03 | P00014 | Supplemental agreement (work within scope) | $3.25M | CUTOFF WALL |
| 2025-08-22 | P00013 | Supplemental agreement (work within scope) | $7.70M | CUTOFF WALL |
| 2025-08-20 | P00012 | Supplemental agreement (work within scope) | $2.29M | CUTOFF WALL |
| 2025-07-31 | A00009 | Supplemental agreement (work within scope) | -$11.9K | CUTOFF WALL |
| 2025-07-30 | A00008 | Supplemental agreement (work within scope) | $0 | CUTOFF WALL |
| 2025-06-13 | P00011 | Change order | $1.25M | REA SETTLEMENT DUE TO STOP WORK ORDER. |
| 2025-04-30 | A00007 | Supplemental agreement (work within scope) | $87.0K | CUTOFF WALL |
| 2025-03-27 | P00010 | Supplemental agreement (work within scope) | $148.22M | MODIFICATION R00017 (EF015-2) ROCK FOUNDATION PREPARATION ALTERNATIVE, ADDITION |
| 2025-03-19 | P00009 | Supplemental agreement (work within scope) | -$127.91M | EF015-1 ROCK FOUNDATION PREPARATION ALTERNATIVE, REDUCTION OF CLSM LINE ITEMS |
| 2025-01-15 | P00008 | Vendor address changed | $0 | CUTOFF WALL |
| 2024-10-23 | A00006 | Supplemental agreement (work within scope) | $0 | CUTOFF WALL |
| 2024-09-27 | P00007 | Supplemental agreement (work within scope) | $1.11M | CEPP EAA CNT LLA A-2 FOUNDATION-INTERIM VEQ CLIN 0002 |
| 2024-09-19 | P00006 | Supplemental agreement (work within scope) | $1.83M | CEPP EAA CNT 11A A-2 FOUNDATION- DATA MANAGEMENT SPECIFICATION UPDATE |
| 2024-09-13 | P00005 | Supplemental agreement (work within scope) | $18.18M | CUTOFF WALL |
| 2024-08-02 | A00005 | Supplemental agreement (work within scope) | $0 | CUTOFF WALL |
| 2024-07-19 | A00004 | Supplemental agreement (work within scope) | $0 | CUTOFF WALL |
| 2024-04-10 | A00003 | Supplemental agreement (work within scope) | $5.3K | CUTOFF WALL |
| 2023-10-04 | A00002 | Supplemental agreement (work within scope) | $0 | CUTOFF WALL |
| 2023-08-09 | A00001 | Supplemental agreement (work within scope) | $48.7K | CUTOFF WALL |
| 2023-07-27 | P00004 | Option exercised | $61.87M | MOD TO EXERCISE OPTION 3 AND ADD FUNDING FOR CLINS UNDER OY3. |
| 2023-04-03 | P00003 | Option exercised | $122.03M | MOD TO EXERCISE OPTION 1 & 2 ADD FUNDING FOR CLINS UNDER EXERCISED OPTIONS |
| 2023-03-31 | P00002 | Administrative change | $0 | PERIOD OF PERFORMANCE FOR NTP 1 AND ISSUE NTP 2. |
| 2022-11-30 | P00001 | Administrative change | $0 | ISSUE FIRST NTP |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗