CHANNEL CLEANOUT EXCAVATION
Up for re-bid: ends 2026-08-06. Recompete brief → · Belle Fountain Ditch Cleanout Phase 2 ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
5 actions since 2025-01-17. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-27 | A00002 | Supplemental agreement (work within scope) | $187.6K | REVISE CERTAIN ESTIMATED QUANTITIES TO REFLECT THE CURRENT BEST ESTIMATE OF QUANTITIES REQUIRED TO COMPLETE THE WORK. THIS MODIFICATION IS FOR FUNDING AND PAYMENT PURPOSES ONLY AND DOES NOT CHANGE THE SUBSTANTIVE RIGHTS OF THE CONTRACTING PARTIES. |
| 2026-01-29 | A00001 | Supplemental agreement (work within scope) | $0 | THE CONTRACTOR PERIOD OF PERFORMANCE END DATE HAS INCREASED BY 25 CALENDAR DAYS FROM 480 DAYS TO 505 DAYS. |
| 2025-03-18 | P00002 | Funding only | $212.6K | REQUEST FOR EQUITABLE ADJUSTMENT MODIFICATION |
| 2025-01-27 | P00001 | Supplemental agreement (work within scope) | $0 | CHANNEL CLEANOUT EXCAVATION |
| 2025-01-17 | 0 | $2.53M | CHANNEL CLEANOUT EXCAVATION |