HSG Park Joint Venture 2, LLC received this contract from W07V Endist ST Paul, Department of the Army: $28.05M obligated so far for construction of dams. It runs to 2027-09-18.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award W912ES25C0003, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W912ES25C0003_9700_-NONE-_-NONE-
HSG Park Joint Venture 2, LLC: all federal awards · Department of Defense: spending · W07V Endist ST Paul: what it buys · The follow-on: recompete brief
FMM SE-3
Up for re-bid: ends 2027-09-18. Recompete brief → · Grand Encampment Island Unloading ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
10 actions since 2025-01-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-17 | P00006 | Administrative change | $0 | CORRECT THE WEATHER EXTENSION COMPLETION DATES UNDER "(R-006) EXTEND THE CONTRACT COMPLETION DATE BY 8 CALENDAR DAYS TO ACCOUNT FOR ADVERSE WEATHER BETWEEN APRIL 2025 THROUGH DECEMBER 2025." |
| 2026-02-09 | A00003 | Supplemental agreement (work within scope) | $0 | (R-006) EXTEND THE CONTRACT COMPLETION DATE BY 8 CALENDAR DAYS TO ACCOUNT FOR ADVERSE WEATHER BETWEEN APRIL 2025 THROUGH DECEMBER 2025. |
| 2026-02-09 | A00002 | Supplemental agreement (work within scope) | $18.8K | FMM SE-3 - (R-05) REPLACE EXISTING VALVES FOR THE SANITARY SEWER AND RURAL WATER CONNECTION TIE-INS. |
| 2026-01-28 | P00005 | Funding only | $0 | FMM SE-3 |
| 2026-01-07 | P00004 | Supplemental agreement (work within scope) | $5.69M | FMM SE-3 |
| 2025-12-11 | P00003 | Option exercised | $3.65M | FMM SE-3 |
| 2025-06-18 | A00001 | Change order | $0 | REMOVE THE DUCKBILL CHECK VALVES FROM THE STRUCTURE VENTS. |
| 2025-03-27 | P00002 | Administrative change | $0 | FMM SE-3 |
| 2025-03-03 | P00001 | Funding only | $0 | FMM SE-3 |
| 2025-01-02 | 0 | $18.69M | FMM SE-3 |