Bundesamt FÜR Bauwesen Und Raumordnung received this contract from W2SD Endist Europe, Department of the Army: $91.06M obligated so far for construction of miscellaneous buildings. It runs to 2032-09-30.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award W912GB20C0011, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W912GB20C0011_9700_-NONE-_-NONE-
Bundesamt FÜR Bauwesen Und Raumordnung: all federal awards · Department of Defense: spending · W2SD Endist Europe: what it buys
ABGX SOFA EDI OPERATIONAL READINESS TRAINING COMPLEX ORTC PHASE 1 EAST CAMP GRAFENWOEHR GERMANY
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
36 actions since 2023-04-14. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-17 | A00021 | Supplemental agreement (work within scope) | $63.1K | ABG5-28, LOOSEN SOIL AND STORMWATER PIPES, CONTRACT FOR ORTC PHASE 1.1A. REFERENCE NO. R00039. TOTAL CONTRACT PRICE INCREASED BY 55,048.85 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2026-07-09 | A00020 | Supplemental agreement (work within scope) | $23.2K | ABG5-14, FPCON EXERCISE IMPACTS, CONTRACT FOR ORTC PHASE 1.1A. REFERENCE NO. R00038. TOTAL CONTRACT PRICE INCREASED BY 20,165.58 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2026-07-06 | P00019 | Change order | $192.4K | REVISE ADDITIONAL SERVICES |
| 2026-04-23 | P00018 | Supplemental agreement (work within scope) | $534.5K | CR039-FURNISH ALL NECESSARY PLANT, LABOR, MATERIAL, EQUIPMENT, TRANSPORTATION, AND SUPERVISION TO COMPLETE THE SURFACE WATER DRAINAGE SYSTEM VIA DRAINAGE BASINS INTO THE WETLAND AREA EAST OF THE ORTC PROJECT SITE. |
| 2026-04-22 | A00019 | Supplemental agreement (work within scope) | $8.2K | CR 5C002-THE NEW WASTEWATER SEWAGE MANHOLE SHALL BE EQUIPPED WITH AN EXTERNAL PIPE DROP, WHICH ENSURES THE NECESSARY ACCESSIBILITY FOR REVISIONS, INSPECTIONS, MAINTENANCE, AND CLEANING WORK IN ACCORDANCE WITH THE APPLICABLE TECHNICAL REGULATIONS. |
| 2026-04-22 | A00018 | Supplemental agreement (work within scope) | $2.1K | CR 5C001-EXTERIOR GLAZING COMPONENTS INSTALLED IN OCCUPIED AREAS MUST PROVIDE A LOW LEVEL OF PROTECTION (L-LOP) IN ACCORDANCE WITH UFC 4-010-01. THE HAZARD RATING FOR THE PROPOSED EXTERIOR GLAZING COMPONENTS MUST BE NO LESS THAN VERY LOW RATING. |
| 2026-04-20 | A00017 | Supplemental agreement (work within scope) | $12.1K | CR 3C001-CONCRETE TESTING- INSTALLATION OF CONCRETE OF MONITORING CLASS 2. CLASSIFICATIONS IN THE MONITORING CLASSES AND MONITORING OF THE INSTALLATION ACCORDING TO DIN 1045-3. MONITORING CONCRETE QUALITY FROM C25/C30. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2026-04-16 | A00016 | Supplemental agreement (work within scope) | $237.5K | CR018 - UXO INVESTIGATIONS- FURNISH ALL NECESSARY PLANT, LABOR, MATERIAL, EQUIPMENT, TRANSPORTATION, AND SUPERVISION TO CONDUCT ADDITIONAL SURVEYS/SOUNDING TO DETERMINE THE EXTENT OF UXO PRESENCE AND DENSITY ON THE ORTC 1.1A CONSTRUCTION AREA. |
| 2026-04-16 | A00015 | Supplemental agreement (work within scope) | $25.1K | CR035 SEALING OF CABLE CONDUIT-PROVIDE ADDITIONAL CABLE CONDUIT SEALS, AND QTY REDUCTIONS: LOW VOLTAGE CABLES CR037 FLEX CONDUIT TO TRANSFORMERS-PROVIDE A FLEXIBLE CONDUIT SYSTEM FOR POWER CABLES FROM MANHOLES TO TRANSFORMER STATIONS |
| 2026-04-07 | P00017 | Change order | $4.46M | ABG-3 INCREASE ESTIMATED CONSTRUCTION COSTS AND FEES FOR PART 6 EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC) - PHASE 1.1A GRAFENWOEHR-PART 6 DINING FACILITY (DFAC) |
| 2026-04-06 | A00014 | Supplemental agreement (work within scope) | $32.1K | CR042 - NA 91.30 - REPLACE HV/MV CABLE VAULT COVERS- FURNISH ALL NECESSARY PLANT, LABOR, MATERIAL, EQUIPMENT, TRANSPORTATION, AND SUPERVISION TO REPLACE TWENTY-SIX (26) INSTALLED HV/MV MANHOLE VAULT COVERS WITH NEW WATERTIGHT COVERS. |
| 2026-04-01 | A00013 | Supplemental agreement (work within scope) | $196.0K | CR014 NA-91.09, RE-ROUTE EXISTING SIGNALS COMM CABLE CR027 NA-91.18, MANHOLE ENTRY LADDERSCR028 NA-91.19, CONTAMINATED MATERIAL DISPOSALCR029 NA-91.20, LOWER DISTRICT HEATING LINES A VMS |
| 2026-03-31 | P00016 | Supplemental agreement (work within scope) | $1.97M | DISPOSE OF APPROX. 20,000 M OF LIGHTLY TO HEAVILY CONTAMINATED TOPSOIL, INCLUDING LOADING, TRANSPORT, AND FINAL DISPOSAL AT CERTIFIED DISPOSAL SITES. |
| 2026-03-26 | A00012 | Supplemental agreement (work within scope) | $10.2K | SOIL REPLACEMENT IS NECESSARY TO ENSURE THE PLATE LOAD TESTS PASS. DURING THE EXCAVATION WORK, WATER ACCUMULATED FROM THE EMPTY PIPELINES EXISTING IN THE SUBSOIL LEAKED INTO THE SUBSOIL. |
| 2026-03-24 | A00011 | Supplemental agreement (work within scope) | $0 | CHANGE REQUIRED TO IMPLEMENT CURRENT UFC CRITERIA FOR FACILITY BATTERY SYSTEMS. |
| 2026-03-24 | A00010 | Supplemental agreement (work within scope) | $0 | CHANGE REQUIRED TO IMPLEMENT CURRENT UFC CRITERIA FOR FACILITY BATTERY SYSTEMS. |
| 2026-03-23 | A00009 | Supplemental agreement (work within scope) | $0 | CHANGE REQUIRED TO IMPLEMENT CURRENT UFC CRITERIA FOR FACILITY BATTERY SYSTEMS. |
| 2026-03-18 | A00008 | Supplemental agreement (work within scope) | $0 | CHANGE REQUIRED TO IMPLEMENT CURRENT UFC CRITERIA FOR FACILITY BATTERY SYSTEMS. |
| 2026-03-05 | P00015 | Change order | $0 | ABG-3 INCREASE ECC AND ASSOCIATED FEES FOR PART 6 |
| 2025-11-17 | P00014 | Change order | -$258.0K | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC) PHASE 1.1A, EAST CAMP GRAFENWOEHR |
| 2025-09-30 | P00013 | Change order | -$86.2K | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC) PHASE 1.1A, GRAFENWOEHR |
| 2025-09-12 | P00012 | Change order | -$1.61M | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC) PHASE 1.1A, EAST CAMP GRAFENWOEHR |
| 2025-09-12 | A00007 | Supplemental agreement (work within scope) | $84.2K | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMANY AT GRAFENWOHR, GERMANY. REFERENCE NO. R00018. TOTAL CONTRACT PRICE INCREASED BY 73,565.78 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-07-18 | A00006 | Supplemental agreement (work within scope) | $283.8K | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMANY. REFERENCE NO. R00015. TOTAL CONTRACT PRICE INCREASED BY 248,127.58 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-07-17 | P00011 | Change order | $393.8K | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX, ORTC, PHASE 1.1A GRAFENWOEHR |
| 2025-07-17 | A00005 | Supplemental agreement (work within scope) | $444.3K | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMANY. REFERENCE NO. R00014. TOTAL CONTRACT PRICE INCREASED BY 388,348.75 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-05-27 | P00010 | Change order | $31.15M | SOFA ABG-X CONSTRUCT EDI OPERATIONAL READINESS TRAINING COMPLEX ORTC PHASE 1.1A |
| 2025-05-13 | A00004 | Supplemental agreement (work within scope) | $283.6K | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMANY, REFERENCE NO. R00012. TOTAL CONTRACT PRICE INCREASED BY 247,947.66 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-12-12 | P00009 | Change order | $1.46M | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX ORTC PHASE 1.1A GRAFENWOEHR |
| 2024-09-20 | A00003 | Supplemental agreement (work within scope) | $1.15M | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMANY AT GRAFENWHR, GERMANY. REFERENCE NO. R00009 CR002 ABG5-01, ADDITIONAL UXO CLEARANCE. CONTRACT AMOUNT IS INCREASED BY 999,807.99 EU, CONTRACT DURATION IS UNCHANGED. |
| 2024-09-12 | A00002 | Supplemental agreement (work within scope) | $87.1K | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMAN AT GRAFENWOHR, GERMANY. REFERENCE NO. R00008 CR023 NA 92.06, NORTH/COMPACT XFMR STN CHANGES. CONTRACT AMOUNT IS INCREASED BY 75,820.86, CONTRACT DURATION IS UNCHANGED. |
| 2024-07-31 | A00001 | Supplemental agreement (work within scope) | $457.0K | CONTRACT FOR ABG4 EDI OPERATIONAL READINESS TRAINING COMPLEX GRAFENWOEHR GERMANY AT GRAFENWHR, GERMANY. REFERENCE NO. R00007 CR013 ABG5-02, REVISE RAINWATER DRAIN SYSTEM. CONTRACT AMOUNT IS INCREASED BY 397,975.47 EU, CONTRACT DURATION IS UNCHANGED. |
| 2024-05-08 | P00008 | Change order | $9.35M | PART 5: CONSTRUCTION |
| 2024-04-26 | P00007 | Change order | $25.27M | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC) PHASE 1.1A GRAFENWOEHR |
| 2023-07-25 | P00006 | Change order | $227.2K | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC), GRAFENWOEHR |
| 2023-04-14 | P00005 | Change order | $14.61M | SOFA ABG-X EDI OPERATIONAL READINESS TRAINING COMPLEX (ORTC PHASE 1.1A |