CONSTRUCT A 10MW GENERATION PLANT, WITH MICROGRID CONTROLS
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2025-10-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-21 | P00003 | Change order | $49.8K | CONSTRUCT A 10MW GENERATION PLANT, WITH MICROGRID CONTROLS |
| 2026-01-06 | P00002 | Administrative change | $0 | CONSTRUCT A 10MW GENERATION PLANT, WITH MICROGRID CONTROLS |
| 2025-12-31 | P00001 | Change order | $0 | CONSTRUCT A 10MW GENERATION PLANT, WITH MICROGRID CONTROLS |
| 2025-10-31 | 0 | $54.28M | CONSTRUCT A 10MW GENERATION PLANT, WITH MICROGRID CONTROLS |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗