CONSTRUCTION PROJECT KNMD189008 F-22 COMPOSITE REPAIR FACILITY FOR THE HAWAII ANG, JBPHH-HI. -CONSTRUCT LO/CRF BAY ADDITION -RECONFIGURE EXISTING MECHANICAL AREAS -SITEWORK AND UTILITIES -OPTION 7 KNMD162546 REPAIR FIRE SUPPRESSION B3408
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
13 actions since 2023-01-26. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-01 | P00023 | Supplemental agreement (work within scope) | $0 | KNMD189008 F-22 LO/CRF 3RD BAY |
| 2026-02-04 | P00022 | Funding only | $0 | KNMD189008 F-22 LO/CRF 3RD BAY |
| 2025-11-07 | P00021 | Supplemental agreement (work within scope) | $0 | KNMD189008 F-22 LO/CRF 3RD BAY |
| 2025-09-24 | P00020 | Supplemental agreement (work within scope) | $28.1K | MODIFICATION IS TO INCORPORATE VARIOUS WITHIN SCOPE CHANGES. ADD CLIN 013 FOR $28,122.71. THE PERIOD OF PERFORMANCE WILL NOT BE EXTENDED FOR THIS WORK. THE TOTAL CONTRACT AMOUNT IS INCREASED BY $28,122.71 FROM $22,569,649.25 TO $22,597,771.96. |
| 2025-08-06 | P00019 | Administrative change | $0 | ADMINISTRATIVE MODIFICATION TO IMPLEMENT EXECUTIVE ORDER 14168. |
| 2025-02-12 | P00018 | Supplemental agreement (work within scope) | $0 | EXTEND THE PERIOD OF PERFORMANCE 267 NON-COMPENSABLE DAYS AS A RESULT OF UNFORESEEN DELAYS. REFERENCE CONTRACTOR'S VARIOUS PROGRESS SCHEDULE UPDATES MOST RECENT SCHEDULE WITH A DATA DATE OF 31-JAN-2025. |
| 2024-03-25 | P00017 | Supplemental agreement (work within scope) | $71.6K | KNMD189008 F22 COMPOSITE REPAIR FACILITY. INCORPORATE VARIOUS WITHIN SCOPE CHANGES TO THE PROJECT. THE PERIOD OF PERFORMANCE WILL NOT BE EXTENDED FOR THIS WORK. |
| 2023-09-27 | P00016 | Supplemental agreement (work within scope) | $1.63M | KNMD189008 F22 COMPOSITE REPAIR FACILITY. INCORPORATE FIRE SUPPRESSION SYSTEM (FSS) REDESIGN. $1,625,000.00. THE PERIOD OF PERFORMANCE WILL BE EXTENDED 463 CALENDAR DAYS FOR THIS WORK. |
| 2023-09-07 | P00015 | Supplemental agreement (work within scope) | $0 | EXTEND THE PERIOD OF PERFORMANCE 60 NON-COMPENSABLE DAYS AS A RESULT OF A DELAYED FINISH FROM UNFORESEEN DELAYS OF INSTALLATION OF THE PCC PAVEMENT, AND THE DELAYED START IN HANGAR DOOR INSTALLATION. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2023-07-10 | P00014 | Supplemental agreement (work within scope) | $0 | EXTEND THE PERIOD OF PERFORMANCE 60 NON-COMPENSABLE DAYS AS A RESULT ON UNFORESEEN SHIPPING DELAYS, AND THE DELAYED START IN UNIFORMITY TESTING. |
| 2023-05-10 | P00013 | Supplemental agreement (work within scope) | $0 | EXTEND THE PERIOD OF PERFORMANCE 60 NON-COMPENSABLE DAYS AS A RESULT ON UNFORESEEN SHIPPING DELAYS, AND THE DELAYED START IN TESTING RELATED TO PROJECT'S STRINGENT AIRFIELD PAVEMENT REQUIREMENTS. |
| 2023-02-15 | P00012 | Change order | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE ADDENDUM NO. 05, DATED 17-JUN-2022. ADDENDUM NO. 05 MADE TO DRAWINGS AND SPECIFICATIONS FOR PROJECT NO. KNMD189008, CONSTRUCTION ADDITION TO LO/CRF, B3408 |
| 2023-01-26 | P00011 | Change order | $207.9K | KNMD189008 F22 COMPOSITE REPAIR FACILITY. INCORPORATE CHANGE ORDER NO. 08. THE PERIOD OF PERFORMANCE WILL BE EXTENDED 215 CALENDAR DAYS FOR THIS WORK. ADD CLIN 0010 TO INCORPORATE CHANGE ORDER NO. 08 FOR $207,900.00. |