REHABILITATION OF OLD HICKORY TURBINE GENERATORS
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
32 actions since 2023-02-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-10 | P00025 | Supplemental agreement (work within scope) | $550.0K | MODIFICATION P00025: OLD-TG-OH018 - UNITS 1 TO 4 DATA RECORDERS REPLACEMENT |
| 2026-05-21 | PZ0024 | Change order definitized | $1.79M | MODIFICATION P00024: OLD -TG PROVIDE ALL NECESSARY EQUIPMENT, DESIGNS, ENGINEERING AND LABOR TO CONVERT THE EXISTING MECHANICAL GOVERNORS AT OLD HICKORY POWER PLANT TO NEW DIGITAL PROGRAMMABLE LOGIC CONTROLLERS CONTROLLED GOVERNORS FOR UNITS 1-4. |
| 2026-05-07 | P00023 | Supplemental agreement (work within scope) | $88.3K | MODIFICATION P00023: OLD-TG-OH035 EXTENDED WARRANTY AND OH064 BRAKE JACK ASSEMBLY |
| 2026-05-01 | P00022 | Supplemental agreement (work within scope) | $711.6K | OLD-TG - OH024 OIL PURIFICATION SYSTEM |
| 2026-04-09 | P00021 | Option exercised | $143.4K | OLD TG - EXERCISE OPTION CLIN 2222 TO SHIFT THE STATOR FRAME, EXERCISE OPTION CLIN 2228 FOR WELD ROTOR POLE LAMINATIONS, QUANTITIES FOR CLINS 5001, 5003, 5005, AND 5011 ARE INCREASED TO 115% AT THEIR CONTRACT UNIT PRICES. |
| 2026-03-31 | P00020 | Option exercised | $153.5K | OLD TG - EXERCISE OPTIONS 1207, 2207, 3207 AND 2211 |
| 2026-03-02 | P00019 | Administrative change | $718.8K | OLD-TG - REIMBURSEMENT OF INCURRED REA TARIFFS MODIFICATION |
| 2026-02-19 | P00018 | Option exercised | $779.5K | EXERCISE OPTIONS 5000, 5002, 5003, 5004, 5005, 5006, 5007, 5008, AND 5009. |
| 2026-02-05 | P00017 | Change order | $2.51M | PART 1 MODIFICATION FOR DIGITAL GOVERNORS |
| 2026-01-09 | P00016 | Change order | $389.5K | PART 2 MODIFICATION FOR DSC TURBINE SHAFT |
| 2025-12-04 | P00015 | Change order | $102.3K | P00015 OH-050 DSC TURBINE SHAFT, PART 1 NTE |
| 2025-12-01 | A00006 | Supplemental agreement (work within scope) | $37.3K | A00006 OH-045 U3 ROTOR POLE ABATEMENT |
| 2025-09-12 | P00014 | Option exercised | $250.0K | EXERCISE OPTION CLIN 5013 |
| 2025-09-09 | A00005 | Change order | $129.0K | A00005 OH030 UNITS 1-3 ANNUNCIATOR PANEL ADDITION |
| 2025-09-03 | P00013 | Option exercised | $32.2K | EXERCISE OPTION CLIN 2225 |
| 2025-06-27 | P00012 | Option exercised | $46.4K | EXERCISE OPTION CLIN 3214 |
| 2025-06-02 | A00004 | Supplemental agreement (work within scope) | $156.9K | MODIFICATION A00004 OH26 & OH027 "UNITS RESEQUENCE & PARTERNING MEETING 2025" |
| 2025-05-07 | P00011 | Administrative change | $0 | ADMINISTRATION MODIFICATION TO ADD WAGE DETERMINATION TN20220205 |
| 2025-03-06 | P00010 | Option exercised | $307.9K | EXERCISE OPTIONS 1223 AND 3223 PISTON OPTIONS. |
| 2025-02-18 | A00003 | Supplemental agreement (work within scope) | $292.5K | CASE OH012 OH015 OH019 A00003 MISC. CHANGES |
| 2024-10-03 | P00009 | Change order | $0 | ADDING PAYMENT PROCEDURES FOR OFF-SITE MATERIALS. |
| 2024-08-20 | P00008 | Option exercised | $19.8K | EXERCISE OPTION 5011 |
| 2024-08-14 | A00002 | Supplemental agreement (work within scope) | -$12.5K | CASE OH003 MODIFICATION A00002 "SHAFT SLEEVE MANDREL DESCOPE" |
| 2024-07-01 | P00007 | Option exercised | $157.6K | OPTION 0201 MANDRELS AND CLAMPS |
| 2024-06-25 | A00001 | Supplemental agreement (work within scope) | $10.4K | 61,600 HP KAPLAN RUNNER ASSEMBLY |
| 2024-05-21 | P00006 | Change order | $153.8K | OH TG REHAB, OPTION 2223 SERVOMOTOR BLADE |
| 2024-05-17 | P00005 | Change order | -$8.0K | 61,600 HP KAPLAN RUNNER ASSEMBLY - CLIN RE-SEQUENCE. |
| 2024-03-21 | P00004 | Option exercised | $397.0K | EXERCISE OPTION CLINS FOR UNIT #2 (0210, 2200, 2201, 2202, 2203, 2215, 2216, 2226.) |
| 2023-12-22 | P00003 | Option exercised | $51.1K | EXERCISE A QTY OF 1 EACH OF OPTION CLINS: 1212, 2212, 3212, 1217, 2217, 3217, 1219, 2219, 3219 FOR WG FINAL HEIGHT. |
| 2023-09-26 | P00002 | Change order | $153.0K | EXERCISE OPTION 0209 WICKET GATE, SPARE AND INCLUDE 52.204-27 BYTEDANCE CLAUSE |
| 2023-03-23 | P00001 | Change order | $0 | NOTICE TO PROCEED MODIFICATION |
| 2023-02-02 | 0 | $81.62M | REHABILITATION OF OLD HICKORY TURBINE GENERATORS |