SAN FRANCISCO VA MEDICAL CENTER BUILDING 8 SEISMIC RETROFIT PROJECT
Up for re-bid: ends 2027-03-24. Recompete brief → · OAKLAND INNER AND OUTER HARBOR FY26 MAINTENANCE DREDGING ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
81 actions since 2023-02-14. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-15 | P00014 | Supplemental agreement (work within scope) | $0 | REPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT. |
| 2026-05-18 | P00013 | Change order | $737.7K | REPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT. |
| 2026-05-12 | P00012 | Change order | $200.0K | REPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT. |
| 2026-04-21 | P00011 | Change order | $400.0K | CONTRACTOR SHALL REBUILD END WING SLAB TO BE FLUSH WITH THE EXISTING STRUCTURAL SLAB AND PROVIDE PRODUCT DATA AND SHOP DRAWINGS FOR FINAL APPROVAL PRIOR TO START OF WORK. REBUILD THE END WING SLABS AND PLACE FLOOR LEVELING MATERIAL ON THE NEW SLAB. |
| 2026-04-03 | P00010 | Change order definitized | $192.6K | CONTRACTOR SHALL REBUILD END WING SLAB TO BE FLUSH WITH THE EXISTING STRUCTURAL SLAB AND PROVIDE PRODUCT DATA AND SHOP DRAWINGS FOR FINAL APPROVAL PRIOR TO START OF WORK. REBUILD THE END WING SLABS AND PLACE FLOOR LEVELING MATERIAL ON THE NEW SLAB. |
| 2026-03-24 | P00009 | Supplemental agreement (work within scope) | $1.60M | COST ESCALATION FOR SIERRA ELECTRIC AND PETERSON MECHANICAL FOR DELAY. NO CHANGE IN DRAWINGS OR SPECIFICATIONS. |
| 2026-03-10 | A00066 | Supplemental agreement (work within scope) | $38.8K | AS A RESULT OF MODIFICATION P00007 THE PERIOD OF PERFORMANCE AND CONTRACT REQUIRED COMPLETION DATE WAS EXTENDED TO 3/20/2027. THIS CHANGE COMPENSATES ALL BRB SUBCONTRACTORS FOR ESCALATION COSTS. |
| 2026-03-03 | P00008 | Supplemental agreement (work within scope) | $448.2K | AS A RESULT OF MODIFICATION P00007 THE PERIOD OF PERFORMANCE AND CONTRACT REQUIRED COMPLETION DATE WAS EXTENDED TO 3/20/2027. THIS CHANGE COMPENSATES ALL BRB SUBCONTRACTORS FOR ESCALATION COSTS. |
| 2026-02-19 | A00065 | Supplemental agreement (work within scope) | $68.8K | CONTRACTOR IS TO COMPLETE WORK PER RFI-0272, RFI-0279, RFI-0265, RFI-0291. |
| 2026-02-19 | A00064 | Supplemental agreement (work within scope) | $219.0K | CONTRACTOR IS TO FURNISH LOW PROFILE LIGHTS IN CORRIDORS PER RFI-0267 |
| 2026-02-11 | P00007 | Supplemental agreement (work within scope) | $1.87M | VR081-INCREASE THE PERIOD OF PERFORMANCE BY 361 CALENDAR DAYS, TO INCLUDE SHOTCRETE REMOBILIZATION AND SUPPORT, MECHANICAL/ELECTRICAL/PLUMBING STORAGE COSTS, MOBILIZATION COSTS, ADDITIONAL SHORING RENT, AND ADDITIONAL QUALITY CONTROL OVERSIGHT. |
| 2026-02-04 | P00006 | Change order | $104.6K | VR086-1: RFI-0303 END ROOM SLAB REBUILD CONTRACTOR IS TO BACKFILL THE SLABS ON THE WINGS PER RFI-0303. CONTRACTOR IS TO ENSURE FINAL ELEVATION OF NEW SLAB ASSEMBLY IS FLUSH WITH EXISTING STRUCTURAL SLAB. |
| 2026-01-22 | A00063 | Change order | $269.1K | CONTRACTOR TO DEMO ADDITIONAL MATERIAL AROUND EXISTING WINDOWS TO ACHIEVE A SUITABLE INSTALLATION SURFACE FOR THE NEW WINDOWS. |
| 2026-01-15 | A00062 | Supplemental agreement (work within scope) | $50.4K | CONTRACTOR IS TO PROVIDE FIRE DAMPERS PER UPDATED SPECIFICATION 23 31 00. ADDITIONALLY, FIRE DAMPER LOCATIONS WERE REMOVED FROM THE FIRE ALARM SHEETS AND ADDED TO THE MECHANICAL POWER SHEETS. |
| 2026-01-06 | A00061 | Supplemental agreement (work within scope) | $33.7K | PER RFI-0262 CONTRACTOR IS TO INFILL JOIST AS SHOWN IN UPDATED DETAIL 08/08-SS6.01. ANY INTERRUPTED BARS ARE TO FOLLOW DETAIL 02/08-SS0.22. PER RFI-0257 CONTRACTOR IS TO PROVIDE EXTERIOR STAIR ANCHOR PLATES AS SHOWN IN UPDATED DETAILS ON SHEETS. |
| 2025-12-18 | A00060 | Supplemental agreement (work within scope) | $46.8K | CONTRACTOR IS TO DEMOLISH JOIST IN WAY OF COLLECTOR BARS AND INFILL RESULTING VOID ON GRIDLINE 8 ON THE FOURTH FLOOR. DEMO AND RESULTING INFILL ARE TO FOLLOW DETAIL 15B/08-SS3.42. |
| 2025-12-16 | A00059 | Supplemental agreement (work within scope) | $80.4K | CONTRACTOR IS TO DEMOLISH TOPPING LAYERS DOWN TO BOTTOM STRUCTURAL LAYER WITH LARGE AGGREGATE. ONCE FLOOR IS DOWN TO STRUCTURE, CONTRACTOR IS TO SURVEY ELEVATIONS OF STRUCTURAL SLAB. THIS IS TO OCCUR ON ALL FLOOR BOTH NORTH AND SOUTH. |
| 2025-12-15 | A00058 | Supplemental agreement (work within scope) | $104.9K | ALL INTERIOR DOORS ARE TO BE 7FT. TALL PER UPDATED DOOR SCHEDULE AND INTERIOR ELEVATIONS. CONTRACTOR IS TO MOVE THE UFER GROUND IN THE NORTH STAIR TOWER TO A SECTION OF CONCRETE THAT IS NOT WRAPPED IN WATERPROOFING. |
| 2025-12-03 | A00057 | Supplemental agreement (work within scope) | $9.3K | CONTRACTOR IS TO VACATE THE LAYDOWN YARD TO THE WEST OF BLDG. 209. THE MEDICAL CENTER AWARDED A NEW CONTRACT AND HAS RESCINDED THE RIGHT TO USE THE LAYDOWN SPACE. BRICE HAS TO MOVE OUT BY 01 NOVEMBER 2025. |
| 2025-10-20 | A00056 | Supplemental agreement (work within scope) | $19.1K | SF VA BUILDING 8 |
| 2025-10-10 | A00055 | Supplemental agreement (work within scope) | $65.3K | SF VA BUILDING 8 |
| 2025-10-09 | A00054 | Supplemental agreement (work within scope) | $59.0K | SF VA BUILDING 8 |
| 2025-08-13 | A00053 | Change order | $100.0K | SF VA BUILDING 8. BILATERAL. VR053 RFP0053 WINDOW UPDATE. |
| 2025-07-25 | A00052 | Change order | $129.2K | SF VA BUILDING 8 VR070 ELEVATOR LOBBY SLAB REFERENCE NO. R00057 TOTAL CONTRACT PRICE INCREASED BY $129,194.76. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-07-17 | A00051 | Change order | $77.4K | SF VA BUILDING 8 VR055 ENTRYWAY DRAIN REFERENCE NO. R00056 TOTAL CONTRACT PRICE INCREASED BY $77,355.63. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-07-15 | A00050 | Change order | -$15.1K | SF VA BUILDING 8 |
| 2025-06-06 | A00049 | Change order | $199.2K | SF VA BUILDING 8 VR063 SLAB JOIST INFILLS UPDATES REFERENCE NO. R00054 TOTAL CONTRACT PRICE INCREASED BY $199,216.12. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-06-04 | A00048 | Change order | -$4.5K | SF VA BUILDING 8 VR062 PULL TEST CREDIT TOTAL CONTRACT PRICE DECREASED BY $4500. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-06-04 | A00047 | Change order | $45.1K | SF VA BUILDING 8 VR067 RAT SLAB REMOVAL REFERENCE NO. R00052 TOTAL CONTRACT PRICE INCREASED BY $45,102.45. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-06-03 | A00046 | Change order | $65.0K | SF VA BUILDING 8, CHANGE VR054/RFP055 |
| 2025-05-07 | A00045 | Change order | $13.4K | SF VA BUILDING 8 ADDITIONAL MEP CURB RFI-0201 VR061 +$13,432.38 |
| 2025-03-27 | A00044 | Change order | $3.5K | SF VA BUILDING 8 VR060 DEDICATED TMS CIRCUITS (REFERENCE NO. R00049) TOTAL CONTRACT PRICE IS INCREASED BY $3,546.61. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-03-25 | A00043 | Change order | $42.0K | SF VA BUILDING 8 VR057 CHILLER UPDATE, REFERENCE NO. R00048 TOTAL CONTRACT PRICE IS INCREASED BY $41,957.93. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-03-21 | A00042 | Change order | $318.2K | SF VA BUILDING 8 VR056 ADDITIONAL FLOOR FLOAT & CHILLER WELL REFERENCE NO R00047 THE TOTAL CONTRACT PRICE IS INCREASED BY $ 318,234.28 THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-03-20 | A00041 | Change order | $7.3K | SF VA BUILDING 8, CHANGE VR058/RFP-059 |
| 2025-02-19 | A00040 | Change order | $42.1K | SF VA BUILDING 8 VR050 NEW CAMPUS NETWORK CONNECTION REFERENCE NO. R00045 |
| 2025-02-10 | A00039 | Supplemental agreement (work within scope) | $36.5K | SF VA BUILDING 8, CHANGE VR044/RFP-054 |
| 2024-12-18 | A00038 | Change order | $15.7K | VR047 GRAVITY BEAM CHANGES CONTRACT FOR BLDG 8 SEISMIC RETROFIT AT 4150 CLEMENT STREET, SAN FRANCISCO. REFERENCE NO. R00043 TOTAL CONTRACT PRICE IS INCREASED BY $15,736.06. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-12-13 | A00037 | Change order | $151.5K | SF VA BUILDING 8 VR024 PLUMBING CHANGE REFERENCE NO.R00042 TOTAL CONTRACT PRICE IS INCREASED BY $151,537.04 THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-11-20 | A00036 | Change order | $11.2K | SF VA BUILDING 8 REFERENCE NO. R00041 VR043 DOOR CHANGES |
| 2024-11-12 | A00035 | Change order | $165.2K | SF VA BUILDING 8 REFERENCE NO. R00040 VR037 SHEARWALLS AT GL 4&10 TOTAL CONTRACT PRICE IS INCREASED BY $165,230.04. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-11-07 | A00034 | Change order | $54.7K | SF VA BUILDING 8 BIM MODEL INTEGRATION CONTRACT FOR BLDG 8 SEISMIC RETROFIT AT 4150 CLEMENT STREET, SAN FRANCISCO, CA 94121. REFERENCE NO. R00039 VR048 BIM MODEL INTEGRATION (+$54,695.69, 0 CD) |
| 2024-10-22 | A00033 | Change order | $165.5K | SF VA BUILDING 8 VR 038 MEP SHAFT GS 5 & A |
| 2024-10-18 | A00032 | Change order | $57.4K | SF VA BUILDING 8 VR046 MICROPILE WATERPROOFING |
| 2024-10-04 | P00005 | Change order definitized | $2.09M | SF VA BUILDING 8 SEISMIC RETROFIT- DEFINITIZE P00003 FOR PILE CAP AND GRADE BEAM DEPTHS. |
| 2024-10-03 | A00031 | Change order | $212.9K | SF VA BUILDING 8 VR041 ADDITIONAL DOBIE DATA |
| 2024-09-19 | A00030 | Change order | $0 | SF VA BUILDING 8 VR045 ELECTRICAL ROOM SWITCH |
| 2024-09-06 | A00029 | Change order | $126.8K | SF VA BUILDING 8 VR035 JANITOR'S CLOSETS |
| 2024-09-03 | A00028 | Change order | $59.8K | SF VA BUILDING 8 VR036 MEP ROOF STRUCTURE INFILL |
| 2024-08-14 | A00027 | Change order | $0 | SF VA BUILDING 8 VR042 SPALLING INVESTIGATION |
| 2024-08-07 | A00026 | Change order | $18.5K | SF VA BUILDING 8 VR040, EXISTING ELEVATOR SHAFT CHANGES |
| 2024-08-06 | A00025 | Change order | $361.4K | SF VA BUILDING 8 VR032 ADDITIONAL JOIST INFILL |
| 2024-08-05 | P00004 | Supplemental agreement (work within scope) | $568.9K | SF VA BUILDING 8 VR034 WESTERN STAIR GRADEBEAM ACCESS |
| 2024-07-30 | A00024 | Change order | $0 | SF VA BUILDING 8 VR025, FIRE SAFETY UPDATES |
| 2024-06-04 | A00023 | Change order | $14.8K | SF VA BUILDING 8 VR031, DCP REVISION REQUEST |
| 2024-06-04 | A00022 | Change order | $108.0K | REFERENCE NO. R00025 VR029 ADDITIONAL ACM TOTAL CONTRACT PRICE IS INCREASED BY $108,027.91. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-05-30 | P00003 | Change order | $588.4K | R00024 VR030-1 PILE CAP AND GRADE BEAM DEPTH TOTAL CONTRACT PRICE IS INCREASED BY $588,364.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-05-28 | A00021 | Change order | $16.4K | REFERENCE NO. R00023 VR023 SLAB THICKNESS TOTAL CONTRACT PRICE IS INCREASED BY $16,438.17. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-05-23 | A00020 | Change order | $36.2K | SF VA BUILDING 8 |
| 2024-05-22 | A00019 | Change order | $8.4K | REFERENCE NO. R00021 VR026 RFI-0122 RWL/OFC FURRED WALL AT PENTHOUSE TOTAL CONTRACT PRICE IS INCREASED BY $8,377.81. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-05-21 | P00002 | Change order definitized | $1.57M | DEFINITIZE UNILATERAL MOD P00001 FOR COST AND TIME & W/BILATERAL AGREEMENT. |
| 2024-05-13 | A00018 | Change order | $93.4K | SF VA BUILDING 8 VR027 ADDITIONAL JOIST ROUGHENING |
| 2024-05-13 | A00017 | Change order | $103.0K | SF VA BUILDING 8 VR019 VAPOR BARRIER TESTING AND COMMISSIONING |
| 2024-05-13 | A00016 | Change order | $7.8K | SF VA BUILDING 8 VR017 & VR020 |
| 2024-03-08 | A00015 | Change order | $262.7K | SF VA BUILDING 8 VR022 REMOVAL OF ADDITIONAL CONCRETE COURSE |
| 2024-03-05 | A00014 | Change order | $7.2K | SF VA BUILDING 8 VR016 & VR018 |
| 2024-01-24 | P00001 | Change order | $356.4K | SF VA BUILDING 8 VR014 - BUILDING #24 UTILITY CONFLICT RESOLUTION. |
| 2024-01-17 | A00013 | Change order | $14.1K | SF VA BUILDING 8 |
| 2024-01-16 | A00012 | Change order | $0 | SF VA BUILDING 8 |
| 2024-01-09 | A00011 | Change order | $0 | BUILDING 8 |
| 2023-10-17 | A00010 | Supplemental agreement (work within scope) | $18.8K | CONTRACT NO. W912P723C0005 VR011 RFI-0026 ELECTRICAL TRENCH VR014 BLDG 24 FOUNDATION LOCATION |
| 2023-10-10 | A00009 | Supplemental agreement (work within scope) | $4.1K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR013 (RFP-013) RFI-0030 FLOOR 2 DIAPHRAGM DEMO |
| 2023-10-04 | A00008 | Supplemental agreement (work within scope) | $435.0K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR009 (RFP-009) RFI-21 PROTECT FA FIBER B8 TEMP FA B212 SEE PAGE 2. |
| 2023-10-04 | A00007 | Supplemental agreement (work within scope) | $20.0K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR012 (RFP-012) REMOVE GOVERNMENT FIELD OFFICE VR010 (RFP-010) EXISTING UTILITY LOCATION |
| 2023-08-10 | A00006 | Change order | $0 | BUILDING 8 SEISMIC RETROFIT REFERENCE NO. R00005 VR005 SPECIFICATIONS - CONFORMED SOLICITATION |
| 2023-08-08 | A00005 | Supplemental agreement (work within scope) | $2.2K | VR007, TEMP POWER WORK - MC DELAYS |
| 2023-06-30 | A00004 | Change order | $913 | CONTRACT NO. W912P723C0005 BUILDING 8 SEISMIC RETROFIT |
| 2023-06-14 | A00003 | Supplemental agreement (work within scope) | $9.8K | CONTRACT NO. W912P723C0005 BLDG. 8 SEISMIC RETROFIT VR004 (RFP-0004) SECOND LAYER OF SIDEWALK SEE PAGE 2. |
| 2023-05-08 | A00002 | Supplemental agreement (work within scope) | $41.8K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR002 (RFP-002) GOVERNMENT FIELD OFFICE SEE PAGE 2. |
| 2023-03-24 | A00001 | Change order | $0 | VR001 CONTRACTOR FIELD OFFICE LOCATION |
| 2023-02-14 | 0 | $49.99M | SAN FRANCISCO VA MEDICAL CENTER BUILDING 8 SEISMIC RETROFIT PROJECT |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗