CALCASIEU LOCK NEW MAINTENANCE BUILDING & ALGIERS LOCK NEW MAINTENANCE BUILDING - PREPARATION OF A DESIGN REPORT AND PLANS AND SPECIFICATIONS FOR NEW MAINTENANCE BUILDING
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2022-12-05. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-02-25 | P00003 | Close-out | -$31.1K | CALCASIEU LOCK NEW MAINTENANCE BUILDING - DE-OBLIGATE AND CLOSE |
| 2023-10-24 | P00002 | Administrative change | $0 | ALGIERS AND CALCASIEU LOCK NEW MAINTENANCE BUILDING NO COST TIME EXTENSION, PERIOD OF PERFORMANCE CHANGED TO MAY 2024. |
| 2023-08-01 | P00001 | Administrative change | $0 | CALCASIEU LOCK NEW MAINTENANCE BUILDING |
| 2022-12-05 | 0 | $1.37M | CALCASIEU LOCK NEW MAINTENANCE BUILDING & ALGIERS LOCK NEW MAINTENANCE BUILDING - PREPARATION OF A DESIGN REPORT AND PLANS AND SPECIFICATIONS FOR NEW MAINTENANCE BUILDING |