WEST SHORE LAKE PONTCHARTRAIN, LA HURRICANE AND STORM DAMAGE RISK REDUCTION PROJECT, WSLP-114A, ST. JOHN THE BAPTIST AND ST. CHARLES PARISH, LOUISIANA
Up for re-bid: ends 2028-06-14. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
7 actions since 2024-09-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-04-30 | P00005 | Administrative change | $1.22M | WEST SHORE LAKE PONTCHARTRAIN, LA, HURRICANE AND STORM DAMAGE RISK REDUCTION PROJECT, WSLP-114A, ST. JOHN THE BAPTIST AND ST. CHARLES PARISH, LOUISIANA (ED 22-019) IS HEREBY MODIFIED TO DEF. C001A SAND BASE REVISION. REFERENCE NO. R00004. |
| 2026-01-27 | P00004 | Change order | $682.2K | WEST SHORE LAKE PONTCHARTRAIN, LA, HURRICANE AND STORM DAMAGE RISK REDUCTION PROJECT, WSLP-114A, ST. JOHN THE BAPTIST AND ST. CHARLES PARISH, LOUISIANA (ED 22-019) IS HEREBY MODIFIED TO DEF. C001A SAND BASE REVISION. REFERENCE NO. R00004. |
| 2025-11-18 | A00002 | Supplemental agreement (work within scope) | $139.0K | CLEARING & GRUBBING & CANAL EXCAVATION CONTRACT FOR WEST SHORE LAKE PONTCHARTRAIN, LA, HURRICANE AND STORM DAMAGE RISK REDUCTION PROJECT, WSLP-114A, ST. JOHN THE BAPTIST AND ST. CHARLES PARISH, LOUISIANA (ED 22-019) REFERENCE NO. R00003 |
| 2025-09-22 | A00001 | Supplemental agreement (work within scope) | $0 | WEATHER (10/7/2024 - 8/31/2025) CONTRACT FOR WEST SHORE LAKE PONTCHARTRAIN, LA, HURRICANE AND STORM DAMAGE RISK REDUCTION PROJECT, WSLP-114A, ST. JOHN THE BAPTIST AND ST. CHARLES PARISH, LOUISIANA (ED 22-019) REFERENCE NO. R00002 |
| 2025-06-18 | P00003 | Change order | $401.8K | CO001 SAND BASE REVISE QUANTITIES FOR SAND FILL |
| 2025-06-13 | P00002 | Administrative change | $0 | STEEL H-PILING (HP14 X 89) - PC |
| 2024-09-23 | 0 | $71.69M | WEST SHORE LAKE PONTCHARTRAIN, LA HURRICANE AND STORM DAMAGE RISK REDUCTION PROJECT, WSLP-114A, ST. JOHN THE BAPTIST AND ST. CHARLES PARISH, LOUISIANA |