Sak Construction LLC received this contract from W07V Endist ST Louis, Department of the Army: $8.42M obligated so far for construction of sewage and waste facilities. Its period of performance ended 2026-06-01.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award W912P924C0005, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W912P924C0005_9700_-NONE-_-NONE-
Sak Construction LLC: all federal awards · Department of Defense: spending · W07V Endist ST Louis: what it buys
MSD INFRASTRUCTURE REPAIR
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
11 actions since 2024-01-24. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-30 | A00005 | Change order | $0 | ADDITIONAL POINT REPAIRS, VEQ #2 CONTRACT FOR ST. LOUIS COMBINED SEWER OVERFLOW AT ST. LOUIS, MOREFERENCE NO. R00007 |
| 2026-03-04 | P00005 | Funding only | $273.9K | ADDITIONAL POINT REPAIRS, VEQ #2 CONTRACT FOR ST. LOUIS COMBINED SEWER OVERFLOW AT ST. LOUIS, MOREFERENCE NO. R00007 |
| 2026-02-17 | P00004 | Administrative change | $0 | ADDITIONAL POINT REPAIRS, VEQ #2 CONTRACT FOR ST. LOUIS COMBINED SEWER OVERFLOW AT ST. LOUIS, MOREFERENCE NO. R00007 |
| 2025-06-11 | A00004 | Change order | $50.5K | MSD INFRASTRUCTURE REPAIR MOD A00004 |
| 2025-04-23 | A00003 | Change order | $5.6K | MSD INFRASTRUCTURE REPAIR MOD A00003 |
| 2024-12-11 | A00002 | Change order | $228.2K | MSD INFRASTRUCTURE REPAIR MOD A00002 |
| 2024-11-12 | P00003 | Change order | -$107.4K | MSD INFRASTRUCTURE REPAIR-CCTV INSPECTION FOR CLEANING AND LINING |
| 2024-05-01 | P00002 | Option exercised | $21.0K | MSD INFRASTRUCTURE REPAIR EXERCISE OF OPTION 2 D001 HEAVY CLEANING |
| 2024-03-14 | A00001 | Change order | $250 | MSD INFRASTRUCTURE REPAIR MOD A00001 |
| 2024-02-20 | P00001 | Administrative change | $0 | ST. LOUIS COMBINED SEWER OVERFLOW REHABILITATION PROJECT - NOTICE TO PROCEED - CONTRACT COMPLETION DATE ESTABLISHED |
| 2024-01-24 | 0 | $7.94M | MSD INFRASTRUCTURE REPAIR |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗