DESIGN AND CONSTRUCT A 1,519 SM (16,352 SF) SINGLE STORY STAGE PROCESSING FACILITY AT NORTH BASE, VANDENBERG SFB TO SUPPORT GROUND BASED STRATEGIC DETERRENT (GBSD) TEST OPERATIONS.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
13 actions since 2023-03-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-20 | P00001 | Administrative change | $0 | IN ACCORDANCE WITH FAR 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS, ADMINISTRATIVE MODIFICATION IS BEING ISSUED TO CORRECT THE PAYMENT TERMS FROM 30 DAYS TO 14 DAYS. |
| 2026-01-29 | A00012 | Supplemental agreement (work within scope) | $198.1K | INCREASE PCC PAVEMENT THICKNESS 4-INCHES TOTAL CONTRACT PRICE INCREASED BY $198,116.44. COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-06-23 | A00011 | Change order | $0 | WC013 TITLE: 149-CALENDAR DAY NO COST TIME EXT ADD 149-CALENDAR DAY TIME EXTENSION AT NO COST TO THE GOVERNMENT. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE COMPLETION DATE SHALL BE EXTENDED BY 149 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| 2025-06-04 | A00010 | Supplemental agreement (work within scope) | -$139.0K | CONTRACT NO. W912PL22C0014 B6825 SPF MILCON-SENTINEL- (PVWC) MODIFICATION NO. R00011 - MOD DESCOPE SITE WATER UTILITY LINES. TOTAL CONTRACT PRICE DECREASED BY $138,974.87. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-02-20 | A00009 | Supplemental agreement (work within scope) | $32.9K | ADD $32,865. CONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY AT VANDENBERG SFB REFERENCE NO. R00009TOTAL CONTRACT PRICE IS INCREASED BY $32,865.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2025-02-19 | A00008 | Supplemental agreement (work within scope) | $0 | R00010 WC012 FOR SEWER HOLDING TANK +75-CALENDAR DAYS AT NO COST TO THE GOVERNMENT NOT INCLUDED IN WC008/R00008. TOTAL CONTRACT PRICE IS UNCHANGED. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 75 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| 2025-02-10 | A00007 | Supplemental agreement (work within scope) | $77.4K | TRANSITION TO SEWER HOLDING TANK CONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY GBSD SPF, VSFB R00008. TOTAL CONTRACT PRICE IS INCREASED BY $77,426.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2024-12-23 | A00006 | Supplemental agreement (work within scope) | $0 | MOD ADD 53-CD NO COST EXTENSION (TIA-05) CONTRACT FOR FY22 GBSD AT VANDENBERG REFERENCE NO. R00007 TOTAL CONTRACT PRICE IS UNCHANGED.THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 53 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| 2024-10-24 | A00005 | Change order | $115.3K | CONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY AT VANDENBERG SFB, CA. REFERENCE NO. R00006, WC004 STORMWATER RETENTION BASIN REDESIGN. CONTRACT PRICE IS INCREASED BY $115,297.21. THE COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| 2024-07-31 | A00004 | Change order | $0 | REFERENCE NO. R00004 WC007 125-CALENDAR DAY NO COST TIME EXTENSION. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 125 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| 2024-04-09 | A00003 | Supplemental agreement (work within scope) | $189.9K | PRIMARY FACILITY, GBSD SPF, VSFB CONTRACT FOR FY22 GBSD STAGE FACILITY AT VSFB. R00003, WC002 FACILITY REQUIREMENTS. TOTAL CONTRACT PRICE IS INCREASED BY $189,950.00. CONTRACT DURATION REMAINS UNCHANGED BY THIS MODFICIATION. |
| 2024-02-12 | A00002 | Supplemental agreement (work within scope) | $0 | CONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY AT VANDENBERG SFB. REFERENCE NO. R00002 WC003 168-CALENDAR DAY NO COST TIME EXTENSION. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 168 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| 2023-03-13 | A00001 | Supplemental agreement (work within scope) | $0 | PRIMARY FACILITY, GBSD SPF, VSFB CONTRACT FOR GBSD REFERENCE R00001. WC001 67-CALENDAR DAY NO COST TIME EXTENSION. CONTRACT COST REMAINS UNCHANGED. |