PHILPOTT LANDSLIDE MITIGATION
Up for re-bid: ends 2027-02-26. Recompete brief → · USACE National Enterprise Dredging Center Scope Dredge to Budget Contract ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
5 subawards totaling $12.67M (51.4% of what was obligated), as David Boland Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| J.F. Allen Company | $7.00M | 1 | WV | 2023-09-28 | 2023-09-28 |
| Drill Tech Drilling & Shoring, Inc. | $3.51M | 1 | CA | 2024-01-12 | 2024-01-12 |
| Access Limited Construction | $1.55M | 1 | CA | 2023-12-04 | 2023-12-04 |
| Procon, Inc. | $553.1K | 1 | VA | 2024-01-25 | 2024-01-25 |
| Triangle Electric Corporation | $68.8K | 1 | VA | 2024-01-10 | 2024-01-10 |
| Date | To | Amount | For |
|---|---|---|---|
| 2023-09-28 | J.F. Allen Company | $7.00M | EARTHWORK, ROCK SLOPE SCALING, DEMOLITION, CLEARING AND GRUBBING, AGGREGATES, STORM DRAINAGE SYSTEMS, ASPHALT PAVING, SEEDING, AND PRECAST T-WALL ERECTION |
| 2024-01-12 | Drill Tech Drilling & Shoring, Inc. | $3.51M | SECANT PILES, STRAND ROCK ANCHORS, STEEL WALER, BLOCKOUT CAPS, AND SECANT PILE GUIDE WALL |
| 2023-12-04 | Access Limited Construction | $1.55M | TEMPORARY ROCKFALL PROTECTION, ANCHORS FOR T-WALLS, CABLE SYSTEM FOR T-WALLS, SPOT TREATMENT ROCK BOLTS, SPOT TREATMENT 100K ANCHORS, SPOT TREATMENT MESH/GROUT, SLOPE DRAPE, AND ROCKFALL FENCE |
| 2024-01-25 | Procon, Inc. | $553.1K | CONCRETE PARAPET WALL, CONCRETE WALER ENCASEMENT, DETENTION VAULT |
| 2024-01-10 | Triangle Electric Corporation | $68.8K | ELECTRICAL |
12 actions since 2023-09-28. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-15 | P00010 | Supplemental agreement (work within scope) | $521.5K | W912PM23C0020 P00009 IS NEEDED TO INCREASE THE QUANTITY OF CREW DAYS BY 10 FROM 14 TO 24 DAYS. |
| 2026-05-14 | P00009 | Change order | $1.05M | W912PM23C0020 P00009 IS NEEDED TO INCREASE THE QUANTITY OF CREW DAYS BY 10 FROM 14 TO 24 DAYS. |
| 2026-03-16 | P00008 | Change order | $2.60M | W912PM23C0020 P00008 ADDITIONAL ROCK SCALING AND GEOLOGICAL FIELD WORK. THE ADDITIONAL WORK WILL INCREASE THE PERIOD OF PERFORMANCE AN ADDITIONAL 306 DAYS. |
| 2025-12-09 | P00007 | Supplemental agreement (work within scope) | $6.6K | W912PM23C0020 P00005 INCREASE LF FOR SECANT PILES THIS CHANGE IS MADE BASED UPON THE REQUEST OF THE CONTRACTOR, DAVID BOLAND, BASED UPON THE ACTUAL LF EXCEEDED FOR THE ESTIMATED LINEAR FOOTAGE (DEPTH) STATED AT AWARD FOR THE PRIMARY AND SECONDARY S |
| 2025-11-18 | P00006 | Change order | $77.6K | W912PM23C0020 P00005 INCREASE LF FOR SECANT PILES THIS CHANGE IS MADE BASED UPON THE REQUEST OF THE CONTRACTOR, DAVID BOLAND, BASED UPON THE ACTUAL LF EXCEEDED FOR THE ESTIMATED LINEAR FOOTAGE (DEPTH) STATED AT AWARD FOR THE PRIMARY AND SECONDARY S |
| 2025-05-20 | P00005 | Administrative change | $576.0K | SECONDARY SECANT PILE |
| 2024-09-24 | P00004 | Change order | $0 | REVISE WD TO CAPTURE WD IN EFFECT AT TIME OF AWARD - VA20230025 |
| 2024-09-24 | P00003 | Change order | $0 | WAGE DETERMINATION CHANGE |
| 2024-05-17 | A00001 | Administrative change | $83.2K | SECONDARY SECANT PILE |
| 2023-12-04 | P00002 | Change order | $0 | ADD OMITTED WEATHER CLAUSE. |
| 2023-11-09 | P00001 | Administrative change | $0 | ISSUE NOTICE TO PROCEED - SET CCD AS 26APR2026 |
| 2023-09-28 | 0 | $19.73M | PHILPOTT LANDSLIDE MITIGATION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗