36C24124D0103↗
Cornerstone Construction Services, LLC received this contract vehicle from 241-Network Contract Office 01 (36C241), Department of Veterans Affairs: $0 obligated so far for repair or alteration of hospitals and infirmaries. It runs to 2029-11-11.
Key facts · data as of Oct 25, 2026
- Recipient
- Cornerstone Construction Services, LLC
- Awarding agency
- Department of Veterans Affairs
- Contracting office
- 241-Network Contract Office 01 (36C241) (36C241)
- Obligated to date
- $0
- Potential value
- $100.00M
- Ends
- 2029-11-11
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 36C24124D0103, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_IDV_36C24124D0103_3600
Cornerstone Construction Services, LLC: all federal awards · Department of Veterans Affairs: spending · 241-Network Contract Office 01 (36C241): what it buys
VISN 1 CONSTRUCTION MATOC FOR ALL HEALTHCARE FACILITIES WITHIN THE VISN 1 NEW ENGLAND HEALTHCARE SYSTEM
What it is
- Product or service
- Repair or Alteration of Hospitals and Infirmaries (PSC Z2DA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- 241-Network Contract Office 01 (36C241) (36C241)
- Competition
- Full and open after exclusion of sources · 24 offers received
- Set-aside
- SDVOSB
- Pricing
- Firm fixed price
- How it was bought
- Contract vehicle (IDV) itself
- Solicitation
- 36C24123R0073
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Orders under this vehicle
5 orders worth $6.12M (current value). The largest:
- 36C24126N0109 · $4.00M · ends 2027-06-26
- 36C24125N1398 · $1.71M · ends 2026-10-02
- 36C24125N0909 · $323.4K · ends 2026-01-26
- 36C24125N0976 · $87.0K · ends 2025-10-17
- 36C24124N1259 · $2.0K · ends 2025-09-09
Every action
5 actions since 2024-09-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-13 | P00004 | Supplemental agreement (work within scope) | $0 | VISN 1 CONSTRUCTION MATOC FOR ALL HEALTHCARE FACILITIES WITHIN THE VISN 1 NEW ENGLAND HEALTHCARE SYSTEM-MODIFICATION TO INCORPORATE EO 14398 |
| 2026-03-16 | P00003 | Supplemental agreement (work within scope) | $0 | VISN 1 CONSTRUCTION MATOC FOR ALL HEALTHCARE FACILITIES WITHIN THE VISN 1 NEW ENGLAND HEALTHCARE SYSTEM-MODIFICATION TO INCORPORATE CONSTRUCTION CLASS DEVIATION VAAR 852.204-70 AND NEW CLAUSE VAAR 852.204-72 |
| 2025-05-01 | P00002 | Supplemental agreement (work within scope) | $0 | VISN 1 CONSTRUCTION MATOC FOR ALL HEALTHCARE FACILITIES WITHIN THE VISN 1 NEW ENGLAND HEALTHCARE SYSTEM-MODIFICATION TO INCORPORATE VAAR 852.222-71 IN ACCORDANCE WITH EO 13899. |
| 2024-11-18 | P00001 | Administrative change | $0 | VISN 1 CONSTRUCTION MATOC FOR ALL HEALTHCARE FACILITIES WITHIN THE VISN 1 NEW ENGLAND HEALTHCARE SYSTEM-MOD TO ALIGN THE POP WITH THE NTP. |
| 2024-09-10 | 0 | $0 | VISN 1 CONSTRUCTION MATOC FOR ALL HEALTHCARE FACILITIES WITHIN THE VISN 1 NEW ENGLAND HEALTHCARE SYSTEM |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗