Putting the award page together from the records…
Putting the award page together from the records…
REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI)
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
1 subaward totaling $3.50M (350000000.0% of what was obligated), as Tetra Tech, Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Mannik & Smith Group, Inc. | $3.50M | 1 | OH | 2024-11-21 | 2024-11-21 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-11-21 | Mannik & Smith Group, Inc. | $3.50M | GENERAL TEAM SUB AWARD FOR SUPPORT UNDER START VI, REGION 5 TOLINS - PROVIDE AS NEEDED TECHNICAL SUPPORT FOR EMERGENCY RESPONSE OPERATIONS, REMOVAL ACTIONS, PREVENTION AND PREPAREDNESS ACTIVITIES, SITE ASSESSMENT… |
24 orders worth $40.09M (current value). The largest:
10 actions since 2024-11-21. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-18 | P00009 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). |
| 2026-02-23 | P00008 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). ADMINISTRATIVE MODIFICATION. |
| 2025-11-07 | P00007 | Change order | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). MODIFICATION 7; INCORPORATE SUBJECT MATTER EXPERT LABOR CATEGORIES AND RATES. |
| 2025-07-02 | P00006 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). MODIFICATION 6; CHANGE THE KEY PERSONNEL FOR THE HAZARDOUS RANKING SYSTEM SPECIALIST TO BRIAN KOLODNE. |
| 2025-06-23 | P00005 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). MODIFICATION 5; THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CLAUSES IN ACCORDANCE WITH IPN 25-01 AND IPN 25-02. |
| 2025-05-20 | P00004 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE ALTERNATE COR. |
| 2025-02-25 | P00003 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI). THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE ADDITIONAL FIXED STANDARD RATES, HALF TIME AND DOUBLE OVERTIME RATES FOR THE CALIFORNIA WILDFIRES EFFORTS. |
| 2025-02-11 | P00002 | Supplemental agreement (work within scope) | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI), MODIFICATION TO INCREASE THE CAPACITY UNDER THIS CONTRACT FOR THE R9 TO R5 CROSSOVER ACTION. |
| 2024-12-03 | P00001 | Administrative change | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI), MODIFICATION TO ADD BRAND NAMES TO EQUIPMENT LIST |
| 2024-11-21 | 0 | $0 | REGION 5, SUPERFUND TECHNICAL ASSESSMENT & RESPONSE TEAM VI (START VI) |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗