69056724D000011↗

M.A. Deatley Construction, Inc. received this contract vehicle from 690567 Western Federal Lands Div, Federal Highway Administration: $0 obligated so far for construction of highways, roads, streets, bridges, and railways. It runs to 2029-05-13.

Key facts · data as of Oct 25, 2026

Recipient
M.A. Deatley Construction, Inc.
Awarding agency
Federal Highway Administration (Department of Transportation)
Contracting office
690567 Western Federal Lands Div (690567)
Obligated to date
$0
Potential value
$600.00M
Ends
2029-05-13

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 69056724D000011, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_IDV_69056724D000011_6925

YELLOWSTONE GRTE MATOC 2024: CONSTRUCTION, MULTIPLE AWARD TASK ORDER CONTRACT (MATOC) COVERING A 5-YEAR PERIOD FOR HIGHWAY/BRIDGE/ROAD PROJECTS IN YELLOWSTONE NATIONAL PARK, GRAND TETON NATIONAL PARK, AND PROJECTS IN THE SURROUNDING AREA.

Idc · Federal Highway Administration · to M.A. Deatley Construction, Inc. (UEI KNGSERLXHV27) · data as of 2026-10-25

Obligated to date$06 actions
Potential value$600.00Mif every option is used
Period2024-05-14 → 2029-05-13current end date

What it is

Product or service
Construction of Highways, Roads, Streets, Bridges, and Railways (PSC Y1LB)
Industry
Highway, Street, and Bridge Construction (NAICS 237310)
Contracting office
690567 Western Federal Lands Div (690567)
Competition
Full and open competition · 6 offers received
Pricing
Order dependent (set on each order)
How it was bought
Contract vehicle (IDV) itself
Solicitation
69056723R000013

Obligations by fiscal year

FY2024$25.0K
FY2025-$25.0K
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Orders under this vehicle

2 orders worth $27.05M (current value). The largest:

Every action

6 actions since 2024-05-14. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-06P00005Administrative change$0YELLOWSTONE, GRAND TETON, AND SURROUNDING AREA MATOC- M.A. DEATLEY CONSTRUCTION, INC. THIS MODIFICATION INCORPORATES THE FAR OVERHAUL IN SUPPORT OF EXECUTIVE ORDER 14275 ON RESTORING COMMON SENSE TO FEDERAL PROCUREMENT AND EO 14398, ADDRESSING DEI DI
2025-10-07P00004Supplemental agreement (work within scope)$0IN COMPLIANCE WITH EXECUTIVE ORDER 14173, THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE DEVIATED TAR CLAUSE; 1252.232-70 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2022) [(DEVIATION AUG 2025)]
2025-09-11P00003Funding only-$25.0KTHIS CONTRACT MODIFICATION (P00003) DEOBLIGATES THE GUARANTEED MINIMUM OF $25,000 THAT WAS MET WITH THE AWARD OF A TASK ORDER FOR MT FLAP PARK 2021(1), OLD YELLOWSTONE TRAIL SOUTH IMPROVEMENTS & PRESERVATION (69056725F00047N).
2025-05-20P00002Administrative change$0THIS MODIFICATION (P00002) UPDATES BASE IDIQ CONTRACT CLAUSES TO INCORPORATE DOT CLASS DEVIATION NO.2025-01 AND 2025-02. THE CLAUSE UPDATES ARE APPLICABLE TO ALL FUTURE TASK ORDERS.
2024-12-17P00001Administrative change$0THIS MODIFICATION INCORPORATES FAR CLAUSE 52.240-1 PROHIBITION ON UNMANNED AIRCRAFT SYSTEMS MANUFACTURED OR ASSEMBLED BY AMERICAN SECURITY DRONE ACT-COVERED FOREIGN ENTITIES (NOV 2024) INTO THE BASE IDIQ CONTRACT. THIS CLAUSE IS APPLICABLE TO ALL FUT
2024-05-140$25.0KYELLOWSTONE GRTE MATOC 2024: CONSTRUCTION, MULTIPLE AWARD TASK ORDER CONTRACT (MATOC) COVERING A 5-YEAR PERIOD FOR HIGHWAY/BRIDGE/ROAD PROJECTS IN YELLOWSTONE NATIONAL PARK, GRAND TETON NATIONAL PARK, AND PROJECTS IN THE SURROUNDING AREA.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗