Putting the award page together from the records…
Putting the award page together from the records…
ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA
Up for re-bid: ends 2026-11-30. Recompete brief → · Rendezvous Proximity Operations, and Capture (RPOC) VI ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
8 subawards totaling $2.67M (6.1% of what was obligated), as The Charles Stark Draper Laboratory, Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Helios Defense Solutions LLC | $2.63M | 7 | MD | 2023-01-25 | 2026-04-27 |
| The Mathworks, Inc. | $41.5K | 1 | MA | 2022-11-15 | 2022-11-15 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-10-15 | Helios Defense Solutions LLC | $1.33M | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2023-05-02 | Helios Defense Solutions LLC | $617.2K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2026-04-27 | Helios Defense Solutions LLC | $320.2K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2025-10-30 | Helios Defense Solutions LLC | $214.0K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2023-10-16 | Helios Defense Solutions LLC | $85.5K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2022-11-15 | The Mathworks, Inc. | $41.5K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2023-08-07 | Helios Defense Solutions LLC | $34.8K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
| 2023-01-25 | Helios Defense Solutions LLC | $33.6K | COMPANY WILL PROVIDE DRAPER WITH TECHNICAL SUPPORT FOR PROGRAM. |
66 actions since 2022-10-06. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-10 | P00094 | Funding only | $750.7K | UPDATE THE FUNDED AMOUNT ON CONTRACT BY OBLIGATING: $750,718.57 PR: 4200941087DE-OBLIGATING ($176,257.54) 2) UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $52,331,678.78 TO $53,082,397.35 AN INCREASE OF $750,718.57. |
| 2026-06-15 | P00093 | Administrative change | $1.50M | INCREMENTAL FUNDING MOD AND CONTRACT VALUE UPDATE |
| 2026-06-15 | P00092 | Administrative change | $0 | ADMINISTRATIVE ACTION. |
| 2026-06-11 | P00091 | Administrative change | $1.08M | INCREMENTAL FUNDING MOD |
| 2026-06-02 | P00090 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CLAUSE INTO THE CONTRACT SECTION I - CONTRACT CLAUSES: FAR 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS |
| 2026-05-06 | P00089 | Funding only | $2.45M | UPDATE THE FUNDED AMOUNT ON CONTRACT BY OBLIGATING: $2,451,524.30, PR: 4200932686 2) UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $47,296,367.50 TO $49,747,891.80 AN INCREASE OF $2,451,524.30 |
| 2026-04-22 | P00088 | Funding only | $369.2K | UPDATE THE FUNDED AMOUNT ON CONTRACT BY OBLIGATING: $369,167.94, PR: 4200930776 2) UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $46,927,199.56 TO $47,296,367.50 AN INCREASE OF $369,167.94 |
| 2026-04-10 | P00087 | Funding only | $230.6K | UPDATE THE FUNDED AMOUNT ON CONTRACT BY OBLIGATING: $322,034.26, PR: 42009230082 | $3,601.94 PR: 4200930658 * DE-OBLIGATING: $45,036.23 PR: 4200922714, $50,000.00, PR: 4200924678 |
| 2026-03-30 | P00086 | Funding only | $0 | INCREASE CONTRACT VALUE |
| 2026-03-05 | P00085 | Funding only | $1.35M | FUNDING ACTION |
| 2026-02-03 | P00084 | Funding only | $591.4K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE THE FUNDED AMOUNT ON CONTRACT BY OBLIGATING: $591,393.66, PR: 4200924678. 2) UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $44,756,830.84 TO $45,348,224.50 AN INCREASE OF $591,393.66 |
| 2026-01-08 | P00083 | Funding only | $482.3K | UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $44,274,557.47 TO $44,756,830.84 AN INCREASE OF $482,273.37 |
| 2025-12-15 | P00082 | Funding only | $619.9K | UPDATE THE FUNDED AMOUNT ON CONTRACT BY PROCESSING: A) OBLIGATING: $648,899.93 PR: 4200921049 B) DE OBLIGATING $29,044.00 PR: 4200919108-4200919266 |
| 2025-11-19 | P00081 | Funding only | $2.60M | UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $41,044,701.55 TO $43,654,701.55 AN INCREASE OF $2,601,000.00 |
| 2025-10-31 | P00080 | Funding only | $252.0K | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE FUNDED AMOUNT ON CONTRACT BY PROCESSING PR: 4200919266, UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $40,792,713.55 TO $41,044,701.55 AN INCREASE OF $251,988.00. |
| 2025-10-31 | P00079 | Funding only | $533.7K | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE FUNDED AMOUNT ON CONTRACT BY PROCESSING PR: 4200919108 UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $40,259,021.54 TO $40,792,713.54 AN INCREASE OF $533,692.00. |
| 2025-09-23 | P00078 | Funding only | $222.6K | 1) UPDATE THE FUNDED AMOUNT ON CONTRACT BY PROCESSING EXPIRED FUNDS: A) OBLIGATING: $222,609.36 PR: 4200917355 2) UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $40,036,412.18 TO $40,259,021.54 AN INCREASE OF $222,609.36 |
| 2025-09-08 | P00077 | Funding only | $1.92M | A) OBLIGATING: $1,920,487.27.91 PR: 4200916236 B) DE OBLIGATING: $77,355.03 PR: 4200894900 $13,684.99 PR:4200914081 2) UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $38,115,924.91 TO $40,036,412.18 AN INCREASE OF $1,920,487.27 |
| 2025-08-15 | P00076 | Administrative change | $1.02M | INCREMENTAL FUNDING, DEOBLIGATION, AND CONTRACT VALUE MOD. |
| 2025-06-12 | P00075 | Funding only | $715.9K | FUNDING ACTION TO OBLIGATE EXPIRED FUNDS |
| 2025-06-12 | P00074 | Funding only | $1.7K | FUNDING ACTION TO OBLIGATE EXPIRED FUNDS |
| 2025-06-12 | P00073 | Funding only | $666.9K | INCREMENTAL FUNDING |
| 2025-04-03 | P00072 | Funding only | $809.0K | INCREMENTAL FUNDING |
| 2025-04-03 | P00071 | Funding only | $33.0K | INCREMENTAL FUNDING FOR ENGINEERING SERVICES. |
| 2025-04-03 | P00070 | Funding only | $1.16M | THE SCOPE OF THE CONTRACT CONSISTS OF ENGINEERING DESIGN, DEVELOPMENT, INTEGRATION, TEST, ANALYSIS, VERIFICATION AND VALIDATION, CERTIFICATION, AND SPACEFLIGHT SUPPORT ACTIVITIES. |
| 2025-01-21 | P00069 | Funding only | $419.7K | OBLIGATING: $419,681,94 - PR: 4200898525 UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $33,296,961.93 TO $33,716,643.87 AN INCREASE OF ($419,681.94) UPDATE THE FUND THROUGH DATE FROM MAY 23,2025 TO JUNE 06,2025 |
| 2025-01-21 | P00068 | Funding only | $1.07M | OBLIGATING: $1,117,775.00 - PR: 4200894900 DE-OBLIGATING: ($43,293.09) UPDATE THE FUND THROUGH DATE FROM APRIL 4,2025 TO MAY 23,2025 |
| 2025-01-21 | P00067 | Funding only | -$158.3K | UPDATE THE FUNDED AMOUNT ON CONTRACT BY:A) OBLIGATING: $134,657.52 B) DE-OBLIGATING: ($93,000.00) ($200,000.00) - PR: 4200880460 2) CONTRACT FUNDING (JUNE 1990) FROM $32,235,096.71 TO $32,222,480.02 AN DECREASE OF ($158,342.48) |
| 2025-01-21 | P00066 | Funding only | $1.59M | UPDATE CLAUSE B.5 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $30,792,739.86 TO $32,380,822.50 AN INCREASE OF $1,588,082.64.3) UPDATE THE FUND THROUGH DATE FROM FEBRUARY 7, 2025 TO APRIL 9,2025. |
| 2024-09-26 | P00065 | Administrative change | $424.5K | UPDATE B.5 CLAUSE 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $30,368,283.39 TO $30,792,739.86 |
| 2024-09-26 | P00064 | Administrative change | $2.22M | UPDATE B.5 CLAUSE 1852.232-81 CONTRACT FUNDING (JUNE 1990) FROM $28,148,929.97 TO $30,368,283.39 |
| 2024-09-26 | P00063 | Funding only | $718.2K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANALYSIS |
| 2024-09-18 | P00062 | Funding only | $31.9K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANALYSIS |
| 2024-09-12 | P00061 | Supplemental agreement (work within scope) | $575.5K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANALYSIS |
| 2024-08-14 | P00060 | Funding only | $920.2K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANALYSIS |
| 2024-07-18 | P00059 | Funding only | $315.4K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANALYSIS |
| 2024-07-02 | P00058 | Supplemental agreement (work within scope) | $0 | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANALYSIS |
| 2024-06-13 | P00057 | Funding only | $1.31M | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2024-05-10 | P00056 | Funding only | $1.53M | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2024-04-23 | P00055 | Funding only | $319.9K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2024-04-01 | P00054 | Funding only | $965.7K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2024-03-11 | P00053 | Funding only | $472.5K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2024-02-13 | P00052 | Funding only | $615.7K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2024-01-11 | P00051 | Funding only | $94.3K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-12-13 | P00050 | Funding only | $939.3K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-11-15 | P00049 | Funding only | $297.7K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-11-01 | P00048 | Funding only | $526.1K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-09-21 | P00047 | Funding only | $230.0K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-09-19 | P00046 | Funding only | $271.2K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-09-13 | P00045 | Funding only | $846.3K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-09-11 | P00044 | Funding only | -$21.2K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-08-18 | P00043 | Funding only | $622.7K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2023-07-13 | P00042 | Funding only | $986.5K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-06-14 | P00041 | Funding only | $841.5K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-06-01 | P00040 | Supplemental agreement (work within scope) | $0 | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-05-17 | P00039 | Funding only | $672.9K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-04-18 | P00038 | Funding only | $355.0K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-03-24 | P00037 | Funding only | $83.8K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-02-22 | P00036 | Funding only | $2.27M | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-02-13 | P00035 | Administrative change | $0 | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2023-01-10 | P00034 | Funding only | $360.5K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2022-12-09 | P00033 | Funding only | $357.7K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND AN |
| 2022-11-15 | P00032 | Funding only | $90.0K | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2022-11-07 | P00031 | Funding only | $1.14M | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2022-10-11 | P00030 | Administrative change | $0 | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
| 2022-10-06 | P00029 | Administrative change | $0 | ADVANCED GUIDANCE, NAVIGATION AND CONTROL (GN&C) AND AVIONICS TECHNOLOGY DEVELOPMENT AND ANA |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗