GS00Q17NSD3009↗

Verizon Business Network Services LLC received this contract vehicle from Gsa/Fas Itc Office of Acquisition Operations, Interagency Contracts, Federal Acquisition Service: $0 obligated so far for it and telecom- telecommunications and transmission. It runs to 2032-07-30.

Key facts · data as of Oct 23, 2026

Recipient
Verizon Business Network Services LLC
Awarding agency
Federal Acquisition Service (General Services Administration)
Contracting office
Gsa/Fas Itc Office of Acquisition Operations, Interagency Contracts (47QTCB)
Obligated to date
$0
Potential value
$50.00B
Ends
2032-07-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award GS00Q17NSD3009, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_IDV_GS00Q17NSD3009_4732

IGF::CT::IGF PROVIDE TELECOMMUNICATIONS AND IT SERVICES TO THE FEDERAL GOVERNMENT.

Idc · Federal Acquisition Service · to Verizon Business Network Services LLC (UEI GEYFS4D96R55) · data as of 2026-10-23

Obligated to date$01147 actions
Potential value$50.00Bif every option is used
Period2017-07-31 → 2032-07-30current end date

What it is

Product or service
IT and Telecom- Telecommunications and Transmission (PSC D304)
Industry
Wired Telecommunications Carriers (NAICS 517110)
Contracting office
Gsa/Fas Itc Office of Acquisition Operations, Interagency Contracts (47QTCB)
Competition
Full and open competition · 14 offers received
Pricing
Fixed price with economic price adjustment
How it was bought
Contract vehicle (IDV) itself
Solicitation
QTA0015THA3003

Obligations by fiscal year

FY2023$0
FY2024$0
FY2025$0
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Orders under this vehicle

123 orders worth $3.72B (current value). The largest:

Every action

1147 actions since 2022-10-11 (the newest 200 shown). Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-30P02302Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05554.02A DATED SEPTEMBER 23, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN P
2026-09-30P02301Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05428.01A DATED SEPTEMBER 21, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN P
2026-09-30P02300Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05495.01A DATED SEPTEMBER 21, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS PRICING AND ASSOCIATED MAPPING RELATIONSHIPS REQUIRED TO ADD ACCESS ARRANGEMENTS (AA) TO NETWORK
2026-09-23P02299Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05553.01A DATED SEPTEMBER 16, 2026, INTO THE CONTRACT. THIS SUBMISSION CHANGES THE MAPPING FOR THE NETWORK SITE CODE (NSC) TO PHYSICAL CONCENTRATION LOCATION (PCL) TABLE A
2026-09-23P02298Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05519.02A DATED SEPTEMBER 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-23P02297Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05538.01A DATED SEPTEMBER 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN P
2026-09-23P02296Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05547.01A DATED SEPTEMBER 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-09-23P02295Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05544.01A DATED SEPTEMBER 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-09-23P02294Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05529.02A DATED SEPTEMBER 17, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-09-16P02293Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05531.01A DATED SEPTEMBER 8, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02292Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05521.03A DATED SEPTEMBER 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02291Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05520.01A DATED SEPTEMBER 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02290Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05525.01A DATED SEPTEMBER 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02289Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05526.01A DATED SEPTEMBER 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02288Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05518.02A DATED SEPTEMBER 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02287Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05515.01A DATED SEPTEMBER 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02286Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05505.01A DATED SEPTEMBER 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02285Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05497.01A DATED SEPTEMBER 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-09-16P02284Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05514.01A DATED SEPTEMBER 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-16P02283Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05516.01A DATED SEPTEMBER 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-16P02282Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05508.01A DATED SEPTEMBER 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-11P02281Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05493.02A DATED SEPTEMBER 8, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PR
2026-09-11P02280Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05498.01A DATED SEPTEMBER 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-11P02279Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05507.01A DATED SEPTEMBER 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-11P02278Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05511.01A DATED SEPTEMBER 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-11P02277Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05506.01A DATED SEPTEMBER 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-10P02276Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05532.01A DATED SEPTEMBER 8, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-10P02275Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05467.03A DATED SEPTEMBER 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-09-04P02274Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05502.01A DATED AUGUST 31, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-09-03P02273Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05478.01A DATED AUGUST 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-09-03P02272Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05440.01A DATED AUGUST 26, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-09-03P02271Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05494.01A DATED AUGUST 26, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-08-26P02270Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05412.01A DATED AUGUST 21, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-08-25P02269Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05475.02A DATED AUGUST 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-08-25P02268Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05487.01A DATED AUGUST 13, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-08-25P02267Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05485.01A DATED AUGUST 13, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-08-25P02266Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05483.01A DATED AUGUST 18, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-08-25P02265Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05474.01A DATED AUGUST 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-08-20P02264Terminated for convenience$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05480.01A DATED AUGUST 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-08-20P02263Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05481.01A DATED AUGUST 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-08-11P02262Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05465.01A DATED AUGUST 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-08-11P02261Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05468.01A DATED AUGUST 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-08-11P02260Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05472.01A DATED AUGUST 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-08-11P02259Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05459.01A DATED AUGUST 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-08-11P02258Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05456.01A DATED JULY 28, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-08-11P02257Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05415.03A DATED JULY 13, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-08-05P02256Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05427.02A DATED JULY 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS A POP (PERIOD OF PERFORMANCE) TO TABLE 4.1.1, GEN_DOM_POPS, IN SUPPORT OF THE TRANSPORT CALCULATION F
2026-08-05P02255Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05422.01A DATED JULY 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-08-05P02254Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05444.01A DATED JULY 16, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-08-05P02253Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05439.01A DATED JULY 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-08-05P02252Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05445.01A DATED JULY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-08-05P02251Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05446.01A DATED JULY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-08-05P02250Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05437.01A DATED, JULY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-08-05P02249Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05436.01A DATED, JULY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-08-05P02248Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05435.01A DATED, JULY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-08-03P02168Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REVOLUTIONARY FAR OVERHAUL (RFO) CHANGES INCLUDING IMPLEMENTING EO 14398
2026-07-27P02247Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05351.04A DATED, JULY 17, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-27P02246Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05389.01A DATED, JUNE 17, 2026, INTO THE CONTRACT. THE SUBMISSION UPDATES TABLE 4.1.5, GEN_PCL_TO_POP, TO ADD MISSING BANDWIDTH GROUPS FROM SUBMISSION VZ05328.01A INTO VER
2026-07-27P02245Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05416.04A DATED, JULY 17, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-07-20P02244Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05429.01A DATED, JULY 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-07-20P02243Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05424.01A DATED, JULY 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-07-20P02242Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05430.01A DATED, JULY 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-20P02241Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05423.01A DATED, JULY 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-07-20P02240Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05343.04A DATED, JULY 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-07-20P02239Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05400.01A DATED, JUNE 29, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-20P02238Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05421.01A DATED, JULY 7, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-07-07P02237Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05404.01A DATED, JUNE 29, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-07-07P02236Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05274.06A DATED, JUNE 29, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-01P02235Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05409.01A DATED, JUNE 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-01P02234Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05408.01A DATED, JUNE 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-07-01P02233Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05406.01A DATED, JUNE 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-01P02232Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05366.04A DATED, JUNE 29, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-01P02231Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05399.01A DATED, JUNE 16, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-01P02230Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05395.01A DATED, JUNE 18, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-07-01P02229Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05381.01A DATED, JUNE 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-25P02228Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05199.06A DATED, JUNE 18, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-25P02227Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05350.01A DATED, JUNE 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-25P02226Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05370.01A DATED, JUNE 5, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-22P02225Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05367.01A DATED, JUNE 5, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-22P02224Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05384.01A DATED, JUNE 12, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-06-22P02223Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05345.03A DATED, JUNE 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-22P02222Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05383.01A DATED, JUNE 8, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-22P02221Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05362.01A DATED, JUNE 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-22P02220Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05388.01A DATED, JUNE 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA)TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-22P02219Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05355.01A DATED, JUNE 8, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-22P02218Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05386.01A DATED, JUNE 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-22P02217Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05382.01A DATED, JUNE 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-22P02215Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05369.01A DATED, JUNE 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-17P02216Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05393.01A DATED, JUNE 12, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-06-15P02214Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05312.01A DATED, MAY 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-15P02213Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05377.02A DATED, JUNE 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-11P02212Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05360.01A DATED, JUNE 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-11P02211Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05374.01A DATED, JUNE 3 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-06-11P02210Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05371.01A DATED, JUNE 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-11P02209Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05365.01A DATED, JUNE 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-09P02208Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05047.02A DATED, JUNE 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-09P02207Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05338.02A DATED, MAY 22, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-09P02206Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05342.01A DATED, MAY 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-09P02205Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05272.01A DATED, MAY 20, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-09P02204Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05341.01A DATED, MAY 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-09P02203Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05346.01A DATED, MAY 21, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-09P02202Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05356.01A DATED, MAY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-09P02201Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05357.01A DATED, MAY 28, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-09P02200Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05295.06A DATED, MAY 21, 2026, INTO VERIZON'S ENTERPRISE INFRASTRUCTURE SOLUTIONS (EIS) CONTRACT. THE SUBMISSION ADDS WEB CONFERENCING SERVICES (WCS) INTO THE CONTRAC
2026-06-04P02199Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05337.01A DATED, MAY 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-04P02198Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05240.03A DATED, MAY 20, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS A DEVICE CLASS DISCOUNT FOR SERVICE RELATED EQUIPMENT (SRE), DEVICE CLASS ID 6167, TO VERIZON'S
2026-06-04P02197Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05328.01A DATED, MAY 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-06-04P02196Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05329.01A DATED, MAY 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-06-01P02195Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05340.01A DATED, MAY 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIO
2026-05-25P02187Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05315.01A DATED, MAY 8, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-21P02194Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05305.01A DATED, MAY 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED ST
2026-05-21P02193Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05309.01A DATED, MAY 5, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-21P02192Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05298.01A DATED, MAY 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-21P02191Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05311.01A DATED, MAY 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-19P02185Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05245.03A DATED, APRIL 28, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-05-18P02190Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05303.02A DATED, MAY 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED STA
2026-05-18P02189Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05035.01A DATED, MAY 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-18P02188Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05302.01A DATED, MAY 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-18P02186Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05202.01A DATED, APRIL 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-05-18P02184Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05299.01A DATED, APRIL 30, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-05-12P02183Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05297.01A DATED, APRIL 28, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-05-11P02182Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05304.03A DATED, MAY 5, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-07P02180Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05280.01A DATED, APRIL 23, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-05-06P02181Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05268.03A DATED, MAY 5, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOU
2026-05-06P02179Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05291.01A DATED, APRIL 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-05-06P02178Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05106.01A DATED, APRIL 28, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-05-06P02177Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05267.01A DATED, APRIL 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-05-06P02172Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05251.04A DATED, MAY 5, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED STA
2026-05-05P02175Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05269.01A DATED, APRIL 16, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-30P02176Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05284.01A DATED, APRIL 16, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-04-30P02174Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05262.01A DATED, APRIL 17, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-30P02173Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05273.01A DATED, APRIL 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-30P02171Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05277.01A DATED, APRIL 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-30P02170Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05279.01A DATED, APRIL 15, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-30P02169Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05283.01A DATED, APRIL 16, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-30P02167Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05227.04A DATED, APRIL 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-04-16P02166Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05252.02A DATED, APRIL 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-16P02165Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05057.04A DATED, APRIL 14, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-04-16P02163Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05118.03A DATED, APRIL 7, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-04-15P02164Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05266.01A DATED, APRIL 13, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-04-14P02162Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05246.02A DATED, MARCH 30, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-14P02161Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05196.03A DATED, MARCH 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-13P02160Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05167.04A DATED, MARCH 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-13P02159Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05259.01A DATED, MARCH 31, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-13P02158Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05205.02A DATED, APRIL 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-04-13P02157Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05257.01A DATED, APRIL 1, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-04-13P02156Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05242.01A DATED, MARCH 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-13P02155Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05247.01A DATED, MARCH 26, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-04-01P02154Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05243.01A DATED, MARCH 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-03-30P02153Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05004.03A DATED, MARCH 24, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-03-30P02152Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05147.02A DATED, MARCH 24, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-03-30P02151Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05160.01A DATED, MARCH 20, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-30P02150Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05159.01A DATED, MARCH 20, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-30P02149Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05097.02A DATED, MARCH 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-26P02148Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05236.01A DATED, MARCH 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-03-25P02147Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05170.03A DATED, MARCH 18, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-25P02146Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05200.02A DATED, MARCH 18, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-25P02145Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05221.01A DATED, MARCH 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-25P02144Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05215.01A DATED, MARCH 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-03-25P02143Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05211.02A DATED, MARCH 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-25P02142Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05176.03A DATED, MARCH 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-03-25P02141Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05224.01A DATED, MARCH 12, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREV
2026-03-25P02140Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05175.02A DATED, MARCH 4, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-03-25P02139Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05135.01A DATED, MARCH 18, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS OPTIONAL VIRTUAL PRIVATE NETWORK (VPN) CLINS TO VERIZON'S ENTERPRISE INFRASTRUCTURE SOLUTIONS
2026-03-20P02137Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05210.01A DATED, MARCH 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-20P02129Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05190.02A DATED, MARCH 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-20P02122Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05173.01A DATED, FEBRUARY 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-19P02138Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05214.01A DATED, MARCH 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02136Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05206.01A DATED, MARCH 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02135Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05162.01A DATED, MARCH 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02134Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05163.01A DATED, MARCH 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02133Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05165.01A DATED, MARCH 3, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02132Supplemental agreement (work within scope)$0,THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05197.01A DATED, MARCH 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED
2026-03-19P02131Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05192.01A DATED, MARCH 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02130Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05195.01A DATED, MARCH 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) AND MAPPING RELATIONSHIPS TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVI
2026-03-19P02128Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05191.02A DATED, MARCH 2, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASED S
2026-03-19P02127Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05193.01A DATED, FEBRUARY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-19P02126Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05194.01A DATED, FEBRUARY 26, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-19P02125Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05169.01A DATED, FEBRUARY 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-19P02124Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05168.01A DATED, FEBRUARY 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-19P02123Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05172.01A DATED, FEBRUARY 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-10P02121Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05154.01A DATED, FEBRUARY 23, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-10P02120Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05153.01A DATED, FEBRUARY 23, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-10P02119Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05157.01A DATED, FEBRUARY 23, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-10P02118Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05158.01A DATED, FEBRUARY 23, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-10P02117Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05171.04A DATED, FEBRUARY 25, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-10P02116Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05166.01A, DATED FEBRUARY 24, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-05P02113Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05174.01A DATED, FEBRUARY 19, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-05P02112Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05152.01A DATED, FEBRUARY 11, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-02P02115Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05119.01A DATED, JANUARY 26, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-03-02P02114Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05100.01A DATED, FEBRUARY 12, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-02P02111Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05098.01A DATED, FEBRUARY 12, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BA
2026-03-02P02110Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05099.01A DATED, FEBRUARY 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-03-02P02109Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05114.02A DATED, FEBRUARY 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-02-25P02108Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05128.01A DATED, FEBRUARY 10, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BAS
2026-02-25P02107Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05123.01A DATED, JANUARY 27, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-02-25P02106Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05145.01A DATED, FEBRUARY 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-02-25P02105Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05134.01A DATED, FEBRUARY 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-02-25P02104Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05131.01A DATED, FEBRUARY 9, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE
2026-02-25P02103Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE VERIZON SUBMISSION NUMBER VZ05140.01A DATED, FEBRUARY 6, 2026, INTO THE CONTRACT. THE SUBMISSION ADDS ACCESS ARRANGEMENTS (AA) TO NETWORK SITE CODES (NSCS) LOCATED WITHIN PREVIOUSLY AWARDED CORE BASE

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗