W58RGZ18D0001↗

Defense Systems and Solutions received this contract vehicle from W6QK Acc-Rsa, Department of the Army: $0 obligated so far for aircraft, rotary wing. It runs to 2027-11-30.

Key facts · data as of Nov 10, 2026

Recipient
Defense Systems and Solutions
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W6QK Acc-Rsa (W58RGZ)
Obligated to date
$0
Potential value
$4.73B
Ends
2027-11-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 10, 2026.

Cite this page: SpendQuery, Award W58RGZ18D0001, data as of Nov 10, 2026, https://spendquery.com/award?id=CONT_IDV_W58RGZ18D0001_9700

PIF-3 BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF)

Idc · Department of the Army · to Defense Systems and Solutions (UEI NWKQVQED4C81) · data as of 2026-11-10

Obligated to date$013 actions
Potential value$4.73Bif every option is used
Period2018-05-22 → 2027-11-30current end date

Up for re-bid: ends 2027-11-30. Recompete brief → · SCREW ASSEMBLY PANEL ↗

What it is

Product or service
Aircraft, Rotary Wing (PSC 1520)
Industry
Other Aircraft Parts and Auxiliary Equipment Manufacturing (NAICS 336413)
Contracting office
W6QK Acc-Rsa (W58RGZ)
Competition
Full and open after exclusion of sources · 2 offers received
Set-aside
8(a)
Pricing
Order dependent (set on each order)
How it was bought
Contract vehicle (IDV) itself
Solicitation
W58RGZ17R0001

Obligations by fiscal year

FY2023$0
FY2024$0
FY2025$0
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Orders under this vehicle

333 orders worth $3.40B (current value). The largest:

Every action

13 actions since 2022-12-20. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-15P00028Supplemental agreement (work within scope)$0THIS STATEMENT OF WORK DESCRIBES THE REQUIREMENT TO PROVIDE LABOR, MATERIALS, AND FACILITIES TO SUPPORT THE PROTOTYPE INTEGRATION FACILITY AT REDSTONE ARSENAL.
2026-04-24P00027Supplemental agreement (work within scope)$0TECHNICAL SUPPORT OF THE AVIATION AND MISSILE RESEARCH, DEVELOPMENT, AND ENGINEERING CENTER PROTOTYPE INTEGRATION FACILITY.
2025-12-02P00026Supplemental agreement (work within scope)$0TECHNICAL SUPPORT OF THE AVIATION AND MISSILE RESEARCH, DEVELOPMENT, AND ENGINEERING CENTER PROTOTYPE INTEGRATION FACILITY
2025-04-22P00025Change order$0PROTOTYPE INTEGRATIION FACILITY 3 BASE INDEFINITE DELIVERY, INDEFINITE QUANTITY FOR TECHNICAL SUPPORT OF THE AVIATION AND MISSILE RESEARCH, DEVELOPMENT, AND ENGINEERING CENTER PROTOTYPE INTEGRATION FACILITY.
2024-09-24P00024Change order$0PIF-3 BASE IDIQ FOR TECHNICAL SUPPORT OF THE AVIATION AND MISSILE RESEARCH, DEVELOPMENT, AND ENGINEERING CENTER PROTOTYPE INTEGRATION FACILITY.
2024-06-24P00023Administrative change$0PIF-3 BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF)
2024-03-05P00022Supplemental agreement (work within scope)$0PIF BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF)
2024-02-09P00021Administrative change$0PIF BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF)
2023-06-20P00020Supplemental agreement (work within scope)$0PIF-3 BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF)/ IDIQ CLAUSE UPDATE
2023-05-09P00019Supplemental agreement (work within scope)$0PIF-3 BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF)
2023-01-12P00018Supplemental agreement (work within scope)$0PIF-3 BASE IDIQ FOR TECHNICAL SUPPORT FOR PROTOTYPE INTEGRATION FACILITY (PIF). REVISED DD254
2023-01-06P00017Supplemental agreement (work within scope)$0THIS STATEMENT OF WORK (SOW) DESCRIBES THE REQUIREMENT TO PROVIDE LABOR, MATERIALS, AND FACILITIES TO SUPPORT THE PIF AT RSA. TERM 2 OPTION EXERCISE.
2022-12-20P00016Supplemental agreement (work within scope)$0THIS STATEMENT OF WORK DESCRIBES THE REQUIREMENT TO PROVIDE LABOR, MATERIALS, AND FACILITIES TO SUPPORT THE PROTOTYPE INTEGRATION FACILITY AT REDSTONE ARSENAL.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-10). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗