Past bid results: what similar work went for
Every bidder and amount on past public bids, from the bid tabulations governments publish as open data. Price your bid against what won, see how many firms bid, and how far apart they were. These are bids as opened, not awards: the low bidder usually, not always, wins.
Try: janitorial · mowing · overlay · bridge · roof · HVAC · signal · striping
5,598 past solicitations: the low bid came in at a median 90% of the engineer's estimate (middle half 79%–100%); a median of 4 bidders; the second bid was typically 8% above the low one.
- Fannin County HSIPParis District · Fannin County · Safety Improvement Projects · opened Mar 5, 2025 · TxDOT
Low bid $86.7K by RHINO EQUITY, LLC · estimate $130.3K (67%) · 9 bids · range $86.7K–$145.0K
Every bid (9)
- RHINO EQUITY, LLC $86.7K
- MARCOM'S MOWING SERVICE, LLC $91.5K
- TRAFFIC HIGHWAY MAINTENANCE, LLC $98.4K
- TWELVE STARS CONSTRUCTION COMPANY LLC $102.4K
- 12TWELVE ROAD AND BRIDGE LLC $109.2K
- SYNERGY SIGNS & SERVICES LLC $113.0K
- SOUTHERN CROSS CONTRACTORS, LLC $125.3K
- LAKEY, INC. $132.4K
- RISE UP CONSTRUCTION LLC $145.0K
Source: TxDOT Bid Tabulations ↗ · project A00209768
- FM 1660 - King Ln to FM 973Austin District · Williamson County · Overlay · opened Mar 5, 2025 · TxDOT
Low bid $3.85M by LONE STAR PAVING COMPANY · estimate $5.71M (68%) · 5 bids · range $3.85M–$6.53M
Every bid (5)
- LONE STAR PAVING COMPANY $3.85M
- TEXAS MATERIALS GROUP, INC. $4.57M
- HUNTER INDUSTRIES, LTD. $4.66M
- CLARK CONSTRUCTION OF TEXAS, INC. $5.01M
- ALLEN KELLER COMPANY $6.53M
Source: TxDOT Bid Tabulations ↗ · project A00209808
- SFT | FM 933 | Patton Lake Rd | FM 1133Waco District · Hill County · Safety Improvement Projects · opened Mar 5, 2025 · TxDOT
Low bid $927.0K by CENTERLINE TECHNOLOGIES, LLC · estimate $1.67M (56%) · 8 bids · range $927.0K–$2.33M
Every bid (8)
- CENTERLINE TECHNOLOGIES, LLC $927.0K
- DOUBLE A CONTRACTING, L.P. $948.7K
- STRIPE-A-ZONE, LLC $1.00M
- TRP INFRASTRUCTURE SERVICES, LLC $1.10M
- STRIPING TECHNOLOGY, L.P. $1.11M
- TRAFFIC HIGHWAY MAINTENANCE, LLC $1.31M
- PROFESSIONAL TRAFFIC CONTROL LLC $1.44M
- LAKEY, INC. $2.33M
Source: TxDOT Bid Tabulations ↗ · project A00210443
- 2025 DISTRICT WIDE THERMO #4Tyler District · Smith County · Traffic Control Devices · opened Mar 5, 2025 · TxDOT
Low bid $2.00M by STRIPE-A-ZONE, LLC · estimate $3.44M (58%) · 7 bids · range $2.00M–$3.92M
Every bid (7)
- STRIPE-A-ZONE, LLC $2.00M
- CENTERLINE TECHNOLOGIES, LLC $2.03M
- STRIPING TECHNOLOGY, L.P. $2.19M
- PROFESSIONAL TRAFFIC CONTROL LLC $2.68M
- TRP INFRASTRUCTURE SERVICES, LLC $3.26M
- GREY SKY CONSTRUCTION LLC $3.35M
- LAKEY, INC. $3.92M
Source: TxDOT Bid Tabulations ↗ · project A00210821
- FY25 Traffic Control RMCBeaumont District · Orange County · Routine Maintenance Project - Sealed · opened Mar 5, 2025 · TxDOT
Low bid $3.67M by ROSS SA ENTERPRISE LLC · estimate $3.78M (97%) · 2 bids · range $3.67M–$5.00M
Every bid (2)
- ROSS SA ENTERPRISE LLC $3.67M
- AWP SAFETY $5.00M
Source: TxDOT Bid Tabulations ↗ · project A00212359
- FY 2025 BRIDGE MAINT (ELP COUNTYWIDE)El Paso District · El Paso County · Bridge Maintenance · opened Mar 5, 2025 · TxDOT
Low bid $2.37M by INTERNATIONAL EAGLE ENTERPRISES, INC. · estimate $2.60M (91%) · 7 bids · range $2.37M–$3.47M
Every bid (7)
- INTERNATIONAL EAGLE ENTERPRISES, INC. $2.37M
- B & MS CONSTRUCTION, INC. $2.51M
- THE TRUESDELL CORPORATION $2.57M
- SYNERGY PROJECT CONTRACTORS, INC. $2.73M
- DAN WILLIAMS COMPANY $2.80M
- HORIZONE CONSTRUCTION I, LTD $3.04M
- BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC $3.47M
Source: TxDOT Bid Tabulations ↗ · project A00212610
- SL 12 at Forsythe Drive to Mystic TrailDallas District · Dallas County · Traffic Control Devices · opened Mar 5, 2025 · TxDOT
Low bid $4.44M by GARRET SHIELDS INFRASTRUCTURE · estimate $5.09M (87%) · 2 bids · range $4.44M–$6.02M
Every bid (2)
- GARRET SHIELDS INFRASTRUCTURE $4.44M
- GREY SKY CONSTRUCTION LLC $6.02M
Source: TxDOT Bid Tabulations ↗ · project A00212937
- FY25 - Washington US 290Bryan District · Washington County · Routine Maintenance Project - Sealed · opened Mar 5, 2025 · TxDOT
Low bid $1.30M by CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. · estimate $1.45M (89%) · 9 bids · range $1.30M–$1.90M
Every bid (9)
- CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. $1.30M
- BIG CREEK CONSTRUCTION, LTD. $1.36M
- ELITE KINGS CONSTRUCTION, LLC $1.37M
- KNIFE RIVER CORPORATION - SOUTH $1.41M
- TEXAS MATERIALS GROUP, INC. $1.62M
- ENVIRONMENTAL ALLIES, INC. $1.68M
- FORDE CONSTRUCTION COMPANY, INC. $1.79M
- VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC $1.81M
- BRAZOS PAVING, INC. $1.90M
Source: TxDOT Bid Tabulations ↗ · project A00213021
- FY 25 Hot Mix Superpave Smith CountyTyler District · Smith County · Material Maintenance Project · opened Mar 5, 2025 · TxDOT
Low bid $2.97M by BIG CREEK CONSTRUCTION, LTD. · estimate $2.79M (106%) · 2 bids · range $2.97M–$2.99M
Every bid (2)
- BIG CREEK CONSTRUCTION, LTD. $2.97M
- TEXAS MATERIALS GROUP, INC. $2.99M
Source: TxDOT Bid Tabulations ↗ · project A00213856
- FY 25 Hot Mix Superpave Van Zandt CountyTyler District · Van Zandt County · Material Maintenance Project · opened Mar 5, 2025 · TxDOT
Low bid $1.20M by TEXAS MATERIALS GROUP, INC. · estimate $1.32M (91%) · 3 bids · range $1.20M–$1.34M
Every bid (3)
- TEXAS MATERIALS GROUP, INC. $1.20M
- BIG CREEK CONSTRUCTION, LTD. $1.25M
- LONGVIEW ASPHALT, INC. $1.34M
Source: TxDOT Bid Tabulations ↗ · project A00213858
- Orange TIC Restroom RenovationMaintenance Division District · Orange County · Routine Maintenance Project · opened Mar 5, 2025 · TxDOT
Low bid $835.7K by APEX ALLIANCE, LLC · estimate $1.26M (66%) · 6 bids · range $835.7K–$1.47M
Every bid (6)
- APEX ALLIANCE, LLC $835.7K
- CONSTRUCTION MANAGERS OF SOUTHEAST TEXAS, LLC $1000.0K
- MB WESTERN INDUSTRIAL CONTRACTING CO. $1.05M
- SCOUT 5 CONSTRUCTION LLC $1.19M
- C. E. BARKER, LTD. $1.24M
- K. TILLMAN CONSTRUCTION LLC $1.47M
Source: TxDOT Bid Tabulations ↗ · project A00213863
- Hot Mix 1692 FDRSan Angelo District · Tom Green County · Material Maintenance Project · opened Mar 5, 2025 · TxDOT
Low bid $1.14M by CSA MATERIALS, INC. · estimate $1.25M (91%) · 1 bid
- Alamo Road Drainage (Improvements)Pharr District · Hidalgo County · Routine Maintenance Project - Sealed · opened Mar 5, 2025 · TxDOT
Low bid $1.18M by LUCANIA CONTRACTORS LLC · estimate $1.40M (85%) · 7 bids · range $1.18M–$2.20M
Every bid (7)
- LUCANIA CONTRACTORS LLC $1.18M
- RBM CONTRACTORS LLC $1.27M
- TEXAS CORDIA CONSTRUCTION, LLC $1.37M
- CLORE EQUIPMENT LLC $1.44M
- ARTILLERY L.L.C. $1.46M
- STX CIVIL $1.81M
- IOC COMPANY LLC $2.20M
Source: TxDOT Bid Tabulations ↗ · project A00213980
- FM 879 IH 45 to FM 813Dallas District · Ellis County · Restoration · opened Mar 4, 2025 · TxDOT
Low bid $9.17M by KNIFE RIVER CORPORATION - SOUTH · estimate $11.18M (82%) · 6 bids · range $9.17M–$16.30M
Every bid (6)
- KNIFE RIVER CORPORATION - SOUTH $9.17M
- A. L. HELMCAMP, INC. $9.84M
- ED BELL CONSTRUCTION COMPANY $10.97M
- BIG CREEK CONSTRUCTION, LTD. $11.02M
- GREY SKY CONSTRUCTION LLC $13.76M
- TEXAS MATERIALS GROUP, INC. $16.30M
Source: TxDOT Bid Tabulations ↗ · project A00058758
- US 380 W of BRIDGE FARMER to 4TH STDallas District · Collin County · Widen Non-Freeway · opened Mar 4, 2025 · TxDOT
Low bid $141.41M by WEBBER, LLC · estimate $138.61M (102%) · 3 bids · range $141.41M–$147.97M
Every bid (3)
- WEBBER, LLC $141.41M
- INDUS ROAD & BRIDGE, INC. $142.37M
- ZACHRY CONSTRUCTION CORPORATION $147.97M
Source: TxDOT Bid Tabulations ↗ · project A00063250
- US 84-FM 2458 to CR 386 CCSJLubbock District · Garza County · Rehabilitation of Existing Road · opened Mar 4, 2025 · TxDOT
Low bid $13.31M by A. L. HELMCAMP, INC. · estimate $15.39M (87%) · 5 bids · range $13.31M–$18.37M
Every bid (5)
- A. L. HELMCAMP, INC. $13.31M
- DUININCK, INC. $16.16M
- RK HALL, LLC $16.25M
- JAMES HAMILTON CONSTRUCTION CO. $17.31M
- KIEWIT INFRASTRUCTURE SOUTH CO. $18.37M
Source: TxDOT Bid Tabulations ↗ · project A00120208
- FM 1301 SURFACING RESTORATION 2304Yoakum District · Matagorda County · Rehabilitation of Existing Road · opened Mar 4, 2025 · TxDOT
Low bid $7.13M by CLARK CONSTRUCTION OF TEXAS, INC. · estimate $6.94M (103%) · 6 bids · range $7.13M–$11.25M
Every bid (6)
- CLARK CONSTRUCTION OF TEXAS, INC. $7.13M
- CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. $7.15M
- HUNTER INDUSTRIES, LTD. $7.83M
- CK NEWBERRY, LLC $8.50M
- VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC $9.61M
- STERLING DELAWARE HOLDING COMPANY $11.25M
Source: TxDOT Bid Tabulations ↗ · project A00124556
- BS 35C, SH 35 N to FM 1462Houston District · Brazoria County · Overlay · opened Mar 4, 2025 · TxDOT
Low bid $5.08M by DURWOOD GREENE CONSTRUCTION CO. · estimate $6.87M (74%) · 3 bids · range $5.08M–$5.75M
Every bid (3)
- DURWOOD GREENE CONSTRUCTION CO. $5.08M
- TEXAS MATERIALS GROUP, INC. $5.52M
- VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC $5.75M
Source: TxDOT Bid Tabulations ↗ · project A00129802
- BUS 287; E Rosedale St to Miller AveFort Worth District · Tarrant County · Overlay · opened Mar 4, 2025 · TxDOT
Low bid $11.94M by FOUTSCO PAVING COMPANY, LLC · estimate $16.11M (74%) · 4 bids · range $11.94M–$14.04M
Every bid (4)
- FOUTSCO PAVING COMPANY, LLC $11.94M
- JAGOE-PUBLIC COMPANY $13.13M
- PEACHTREE CONSTRUCTION, LTD. $13.76M
- TEXAS MATERIALS GROUP, INC. $14.04M
Source: TxDOT Bid Tabulations ↗ · project A00129824
- SH 225, IH 610E to W of S RicheyHouston District · Harris County · Overlay · opened Mar 4, 2025 · TxDOT
Low bid $21.98M by TEXAS MATERIALS GROUP, INC. · estimate $27.32M (81%) · 5 bids · range $21.98M–$32.77M
Every bid (5)
- TEXAS MATERIALS GROUP, INC. $21.98M
- ISI CONTRACTING, INC. $22.43M
- POSILLICO CIVIL, INC. $22.66M
- DURWOOD GREENE CONSTRUCTION CO. $30.31M
- VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC $32.77M
Source: TxDOT Bid Tabulations ↗ · project A00130736
- FY 26 BSSP-HR SH 23 Gilaloo Creek BridgeAmarillo District · Lipscomb County · Bridge Replacement · opened Mar 4, 2025 · TxDOT
Low bid $18.73M by EARTH BUILDERS, L.P. · estimate $19.10M (98%) · 5 bids · range $18.73M–$31.67M
Every bid (5)
- EARTH BUILDERS, L.P. $18.73M
- COPPELL CONSTRUCTION CO., INC. $21.09M
- WEBBER, LLC $22.99M
- KIEWIT INFRASTRUCTURE SOUTH CO. $23.15M
- C. E. BARKER, LTD. $31.67M
Source: TxDOT Bid Tabulations ↗ · project A00130847
- CR 270; AT TRIBUTARY TO NORTH BOSQUEFort Worth District · Erath County · Bridge Replacement · opened Mar 4, 2025 · TxDOT
Low bid $1.42M by KNIFE RIVER CORPORATION - SOUTH · estimate $1.56M (91%) · 8 bids · range $1.42M–$1.86M
Every bid (8)
- KNIFE RIVER CORPORATION - SOUTH $1.42M
- TALBERT COMPANIES LLC $1.47M
- PMCO CONSTRUCTION LLC $1.47M
- SCOTT TUCKER CONSTRUCTION COMPANY, LLC $1.50M
- PROJECT ALLIED RESOURCES, LLC $1.53M
- SKYLINE BRIDGE LLC $1.54M
- YOKO EXCAVATING, LLC $1.57M
- LAKEY, INC. $1.86M
Source: TxDOT Bid Tabulations ↗ · project A00133339
- IH 45 at SH 34Dallas District · Ellis County · Intersection & Operational Imprv · opened Mar 4, 2025 · TxDOT
Low bid $8.08M by GREY SKY CONSTRUCTION LLC · estimate $7.68M (105%) · 4 bids · range $8.08M–$9.18M
Every bid (4)
- GREY SKY CONSTRUCTION LLC $8.08M
- ED BELL CONSTRUCTION COMPANY $8.47M
- XIT PAVING AND CONSTRUCTION INC. $8.74M
- RAGLE CONSTRUCTION, INC. $9.18M
Source: TxDOT Bid Tabulations ↗ · project A00134955
- VA; DISTRICTWIDE ITS 2025Fort Worth District · Tarrant County · Transportation Non-Roadway · opened Mar 4, 2025 · TxDOT
Low bid $4.20M by ELECNOR BELCO ELECTRIC, INC. · estimate $3.90M (108%) · 3 bids · range $4.20M–$5.17M
Every bid (3)
- ELECNOR BELCO ELECTRIC, INC. $4.20M
- LIGHT IT UP ELECTRIC $4.98M
- MICA CORPORATION $5.17M
Source: TxDOT Bid Tabulations ↗ · project A00135507
- FM 2499 (Justin Road) At FM 407Dallas District · Denton County · Intersection & Operational Imprv · opened Mar 4, 2025 · TxDOT
Low bid $3.14M by GARRET SHIELDS INFRASTRUCTURE · estimate $3.50M (90%) · 6 bids · range $3.14M–$4.05M
Every bid (6)
- GARRET SHIELDS INFRASTRUCTURE $3.14M
- O. TREVINO CONSTRUCTION, LLC $3.41M
- ED BELL CONSTRUCTION COMPANY $3.77M
- RAGLE CONSTRUCTION, INC. $3.82M
- GREY SKY CONSTRUCTION LLC $3.89M
- JAGOE-PUBLIC COMPANY $4.05M
Source: TxDOT Bid Tabulations ↗ · project A00177327
← Newer · 3526–3550 of 5,598 · Older →
TxDOT work types
Routine Maintenance Project - Sealed 1020 · Material Maintenance Project 834 · Routine Maintenance Project 459 · Safety Improvement Projects 337 · Overlay 196 · Bridge Replacement 181 · Bridge Preventative Maintenance - Sealed 156 · Rehabilitation of Existing Road 150 · Traffic Control Devices 133 · Material Maintenance Project - Sealed 126 · Bridge Maintenance 100 · Seal Coat 76 · Pedestrian, Sidewalks & Curb Ramps 65 · Landscape & Scenic Enhancement 47 · Widen Non-Freeway 44 · State Use Project 43 · Intersection & Operational Imprv 37 · Bridge Preventative Maintenance 30 · Restoration 26 · Bridge Widening or Rehabilitation 24 · Super-2 Highway 19 · Interchange (New or Reconstructed) 18 · Culvert & Storm Drainage Work 14 · Widen Freeway 14
Where this comes from
- TxDOT Bid Tabulations ↗: Texas highway lettings and maintenance contracts, the last 24 months; newest bid opening 2026-10-28. Source: TxDOT. Official TxDOT sources take precedence.
- Cook County IL bid tabulations ↗: Cook County goods, services and construction bids since 2016; newest bid opening 2026-10-28. Public domain.
- Michigan DOT bid tabulations ↗: Michigan highway lettings since 2024: every bidder's total and the engineer's estimate; newest bid opening 2024-03-06.
- NCDOT bid results as read ↗: North Carolina highway lettings since October 2026 (the feed holds the latest letting only); newest bid opening 2026-10-20.
More states and cities publish bid tabulations only as PDFs; we add sources that publish them as data. Open Texas lettings show what similar ones went for on their own page: Texas DOT lettings.