Research the market · bid results
Past bid results: what similar work went for
Every bidder and amount on past public bids, from the bid tabulations governments publish as open data. Price your bid against what won, see how many firms bid, and how far apart they were. These are bids as opened, not awards: the low bidder usually, not always, wins.
Work type: Material Maintenance Project · any work type
820 past solicitations match: the low bid came in at a median 97% of the engineer's estimate (middle half 91%–103%); a median of 2 bidders; the second bid was typically 6% above the low one.
- 6474-05-001 LRA Refugio MaintCorpus Christi District · Refugio County · Material Maintenance Project · opened Oct 15, 2024
Low bid $305.1K by MARTIN MARIETTA MATERIALS, INC. · estimate $312.9K (98%) · 2 bids · range $305.1K–$328.0K
Every bid (2)
- MARTIN MARIETTA MATERIALS, INC. $305.1K
- VULCAN CONSTRUCTION MATERIALS, LLC $328.0K
Source: TxDOT Bid Tabulations ↗ · project A00212306
- 6474-06-001 LRA Rockport MaintCorpus Christi District · Aransas County · Material Maintenance Project · opened Oct 15, 2024
Low bid $316.2K by MARTIN MARIETTA MATERIALS, INC. · estimate $327.9K (96%) · 2 bids · range $316.2K–$342.8K
Every bid (2)
- MARTIN MARIETTA MATERIALS, INC. $316.2K
- VULCAN CONSTRUCTION MATERIALS, LLC $342.8K
Source: TxDOT Bid Tabulations ↗ · project A00212307
- WINTER WEATHER MATERIAL FY25San Angelo District · Tom Green County · Material Maintenance Project · opened Oct 10, 2024
Low bid $418.7K by NSG LOGISTICS, LLC · estimate $486.8K (86%) · 2 bids · range $418.7K–$467.5K
Every bid (2)
- NSG LOGISTICS, LLC $418.7K
- SOUTHWEST ENVIROTX PARTNERS, LLC $467.5K
Source: TxDOT Bid Tabulations ↗ · project A00212381
- FRACKING BRINE FY 25San Angelo District · Reagan County · Material Maintenance Project · opened Oct 10, 2024
Low bid $165.6K by TOUCHSTONE RESOURCES, LLC · estimate $230.4K (72%) · 3 bids · range $165.6K–$263.0K
Every bid (3)
- TOUCHSTONE RESOURCES, LLC $165.6K
- SOUTHWEST ENVIROTX PARTNERS, LLC $246.7K
- NSG LOGISTICS, LLC $263.0K
Source: TxDOT Bid Tabulations ↗ · project A00212382
- Brine Salt FY 25San Angelo District · Tom Green County · Material Maintenance Project · opened Oct 10, 2024
Low bid $72.6K by NSG LOGISTICS, LLC · estimate $80.0K (91%) · 3 bids · range $72.6K–$97.8K
Every bid (3)
- NSG LOGISTICS, LLC $72.6K
- SOUTHWEST ENVIROTX PARTNERS, LLC $87.6K
- THE BARGAIN SOURCE $97.8K
Source: TxDOT Bid Tabulations ↗ · project A00212383
- 04 Limestone Rock Asphalt - 10/24Dallas District · Denton County · Material Maintenance Project · opened Oct 9, 2024
Low bid $79.4K by MARTIN MARIETTA MATERIALS, INC. · estimate $82.5K (96%) · 2 bids · range $79.4K–$82.8K
Every bid (2)
- MARTIN MARIETTA MATERIALS, INC. $79.4K
- VULCAN CONSTRUCTION MATERIALS, LLC $82.8K
Source: TxDOT Bid Tabulations ↗ · project A00210539
- Aggregate FY 25Atlanta District · Harrison County · Material Maintenance Project · opened Oct 9, 2024
Low bid $1.12M by RK HALL, LLC · estimate $972.6K (115%) · 2 bids · range $1.12M–$1.80M
Every bid (2)
- RK HALL, LLC $1.12M
- MARTIN MARIETTA MATERIALS, INC. $1.80M
Source: TxDOT Bid Tabulations ↗ · project A00212253
- Hot Mix FY 25 - LindenAtlanta District · Cass County · Material Maintenance Project · opened Oct 9, 2024
Low bid $415.2K by RK HALL, LLC · estimate $415.2K (100%) · 1 bid
- Hot Mix FY 25 - CarthageAtlanta District · Panola County · Material Maintenance Project · opened Oct 9, 2024
Low bid $396.5K by LONGVIEW ASPHALT, INC. · estimate $380.5K (104%) · 1 bid
- Hot Mix FY 25 - DaingerfieldAtlanta District · Morris County · Material Maintenance Project · opened Oct 9, 2024
Low bid $377.0K by RK HALL, LLC · estimate $377.0K (100%) · 1 bid
- Hot Mix FY 25 - GilmerAtlanta District · Upshur County · Material Maintenance Project · opened Oct 9, 2024
Low bid $387.0K by RK HALL, LLC · estimate $349.0K (111%) · 2 bids · range $387.0K–$393.3K
Every bid (2)
- RK HALL, LLC $387.0K
- LONGVIEW ASPHALT, INC. $393.3K
Source: TxDOT Bid Tabulations ↗ · project A00212257
- Hot Mix FY 25 - JeffersonAtlanta District · Marion County · Material Maintenance Project · opened Oct 9, 2024
Low bid $396.5K by LONGVIEW ASPHALT, INC. · estimate $380.5K (104%) · 1 bid
- Hot Mix FY 25 - MarshallAtlanta District · Harrison County · Material Maintenance Project · opened Oct 9, 2024
Low bid $396.5K by LONGVIEW ASPHALT, INC. · estimate $380.5K (104%) · 1 bid
- Hot Mix FY 25 - Mt. PleasantAtlanta District · Titus County · Material Maintenance Project · opened Oct 9, 2024
Low bid $377.0K by RK HALL, LLC · estimate $377.0K (100%) · 1 bid
- Hot Mix FY 25 - New BostonAtlanta District · Bowie County · Material Maintenance Project · opened Oct 9, 2024
Low bid $412.7K by RK HALL, LLC · estimate $412.4K (100%) · 1 bid
- Hot Mix FY 25 - TexarkanaAtlanta District · Bowie County · Material Maintenance Project · opened Oct 9, 2024
Low bid $402.7K by RK HALL, LLC · estimate $322.0K (125%) · 1 bid
- FY25 - Bryan AO Cutback AsphaltBryan District · Brazos County · Material Maintenance Project · opened Oct 8, 2024
Low bid $130.3K by MARTIN RESOURCE MANAGEMENT CORPORATION · estimate $153.0K (85%) · 3 bids · range $130.3K–$143.5K
Every bid (3)
- MARTIN RESOURCE MANAGEMENT CORPORATION $130.3K
- WRIGHT ASPHALT PRODUCTS COMPANY LLC $133.4K
- CLEVELAND ASPHALT PRODUCTS, INC. $143.5K
Source: TxDOT Bid Tabulations ↗ · project A00212340
- FY25 - Huntsville AO CutbackBryan District · Walker County · Material Maintenance Project · opened Oct 8, 2024
Low bid $175.0K by MARTIN RESOURCE MANAGEMENT CORPORATION · estimate $204.0K (86%) · 3 bids · range $175.0K–$190.2K
Every bid (3)
- MARTIN RESOURCE MANAGEMENT CORPORATION $175.0K
- WRIGHT ASPHALT PRODUCTS COMPANY LLC $178.4K
- CLEVELAND ASPHALT PRODUCTS, INC. $190.2K
Source: TxDOT Bid Tabulations ↗ · project A00212341
- FY25-26 Flexible BaseChildress District · Childress County · Material Maintenance Project · opened Oct 8, 2024
Low bid $247.0K by TOUCHSTONE RESOURCES, LLC · estimate $284.5K (87%) · 3 bids · range $247.0K–$284.4K
Every bid (3)
- TOUCHSTONE RESOURCES, LLC $247.0K
- DIGG COMMERCIAL, LLC $267.4K
- B & G ELECTRIC $284.4K
Source: TxDOT Bid Tabulations ↗ · project A00212411
- East ACP Hot-mix Cold LaidAustin District · Hays County · Material Maintenance Project · opened Oct 2, 2024
Low bid $2.04M by LONE STAR PAVING COMPANY · estimate $2.12M (96%) · 4 bids · range $2.04M–$2.23M
Every bid (4)
- LONE STAR PAVING COMPANY $2.04M
- RHINO HOTMIX, LLC $2.08M
- BRAUNTEX MATERIALS, INC. $2.15M
- COLORADO MATERIALS, LTD. $2.23M
Source: TxDOT Bid Tabulations ↗ · project A00210066
← Newer · 801–820 of 820
Where this comes from
- TxDOT Bid Tabulations ↗: Texas highway lettings and maintenance contracts, the last 24 months; newest bid opening 2026-10-20. Source: TxDOT. Official TxDOT sources take precedence.
- Cook County IL bid tabulations ↗: Cook County goods, services and construction bids since 2016; newest bid opening 2026-10-07. Public domain.