Congressional earmarks in VA

Projects Congress paid for by name in the annual spending laws: House Community Project Funding and Senate Congressionally Directed Spending, FY2022–FY2024. 7 provisions worth $48.19M match.

Clear

By year

FY2025: none (a full-year continuing resolution). FY2026: enacted, not yet in GAO's data.

Requesting members

A project with several requesters counts for each of them.

By agency

Largest provisions

FYProject and recipientAgencyRequested byAmount
2023Norfolk Harbor and Channels, Craney Island, VA U.S. Army Corps of Engineers · VAArmy Corps of Engineers · ConstructionSenator Mark Warner VA, Senator Timothy Kaine VA$30.00M
$0 obligated by 9/30/23
2023James River Channel, VA U.S. Army Corps of Engineers · VAArmy Corps of Engineers · Operation and MaintenanceSenator Mark Warner VA, Senator Timothy Kaine VA$10.70M
$277.6K obligated by 9/30/23
2023Atlantic Intracoastal Waterway, North Landing Bridge, VA U.S. Army Corps of Engineers · VAArmy Corps of Engineers · InvestigationsSenator Mark Warner VA, Senator Timothy Kaine VA$5.00M
$95.6K obligated by 9/30/23
2023Little Machipongo River, VA U.S. Army Corps of Engineers · VAArmy Corps of Engineers · Operation and MaintenanceRepresentative Elaine Luria VA$1.95M
$2.2K obligated by 9/30/23
2023Baltimore Harbor & Channels (50 foot), MD (Tangier Island Beneficial Use, VA) U.S. Army Corps of Engineers · VAArmy Corps of Engineers · Operation and MaintenanceSenator Mark Warner VA, Senator Timothy Kaine VA$300.0K
$6.0K obligated by 9/30/23
2023Hampton Roads Beneficial Use, VA U.S. Army Corps of Engineers · VAArmy Corps of Engineers · Construction/Section 204Senator Mark Warner VA, Senator Timothy Kaine VA$200.0K
$0 obligated by 9/30/23
2023North Beach Boardwalk Erosion Control & Shoreline Resiliency, VA U.S. Army Corps of Engineers · VAArmy Corps of Engineers · Construction/Section 103Senator Mark Warner VA, Senator Timothy Kaine VA$50.0K
$0 obligated by 9/30/23

Enacted earmarks from GAO's Tracking the Funds data (FY2022-FY2024). FY2025 had none (a full-year continuing resolution); FY2026's are enacted but not yet in GAO's data. Amounts are what the law provided, not what was spent. Source: GAO, Tracking the Funds. Requesters are matched to today's members of Congress by name and state; former members show as GAO wrote them.