FAR 11.402 Factors to consider in establishing schedules.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section lists factors the Government must consider when setting contract delivery, performance, or construction completion schedules. It matters to contractors because these schedules determine when work must be finished, and the factors include things like production time, small business capabilities, and contractor capacity to perform.

Applies to: Contracting officers establishing contract delivery, performance, or construction completion schedules

Key terms: delivery schedule · performance schedule · conditions precedent · multiple completion dates · extension of time

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) Supplies or services. When establishing a contract delivery or performance schedule, consideration shall be given to applicable factors such as the—

(1) Urgency of need;

(2) Industry practices;

(3) Market conditions;

(4) Transportation time;

(5) Production time;

(6) Capabilities of small business concerns;

(7) Administrative time for obtaining and evaluating offers and for awarding contracts;

(8) Time for contractors to comply with any conditions precedent to contract performance; and

(9) Time for the Government to perform its obligations under the contract; e.g., furnishing Government property.

(b) Construction. When scheduling the time for completion of a construction contract, the contracting officer shall consider applicable factors such as the—

(1) Nature and complexity of the project;

(2) Construction seasons involved;

(3) Required completion date;

(4) Availability of materials and equipment;

(5) Capacity of the contractor to perform; and

(6) Use of multiple completion dates. (In any given contract, separate completion dates may be established for separable items of work. When multiple completion dates are used, requests for extension of time must be evaluated with respect to each item, and the affected completion dates modified when appropriate.)

← 11.401 General. · 11.403 Supplies or services. →