FAR and DFARS › FAR Part 11: Describing Agency Needs › Subpart 11.5

FAR 11.501 Policy.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section sets policy for when and how contracting officers may use liquidated damages clauses. It matters to contractors because it explains that liquidated damages are meant to compensate the Government for probable harm from late or untimely performance, not to punish the contractor, and that the Government must take reasonable steps to mitigate them.

Applies to: Contracting officers using liquidated damages clauses in Government contracts

What it requires

  • Consider the potential impact on pricing, competition, and contract administration before using a liquidated damages clause
  • Use liquidated damages clauses only when timely delivery or performance is so important that the Government may reasonably expect damage from delinquency, and the extent or amount of that damage would be difficult or impossible to estimate accurately or prove
  • Ensure the liquidated damages rate is a reasonable forecast of just compensation for harm caused by late delivery or untimely performance
  • Take all reasonable steps to mitigate liquidated damages

Key terms: liquidated damages · contracting officer · delinquent · terminating the contract for default · mitigate

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) The contracting officer must consider the potential impact on pricing, competition, and contract administration before using a liquidated damages clause. Use liquidated damages clauses only when—

(1) The time of delivery or timely performance is so important that the Government may reasonably expect to suffer damage if the delivery or performance is delinquent; and

(2) The extent or amount of such damage would be difficult or impossible to estimate accurately or prove.

(b) Liquidated damages are not punitive and are not negative performance incentives (see 16.402-2). Liquidated damages are used to compensate the Government for probable damages. Therefore, the liquidated damages rate must be a reasonable forecast of just compensation for the harm that is caused by late delivery or untimely performance of the particular contract. Use a maximum amount or a maximum period for assessing liquidated damages if these limits reflect the maximum probable damage to the Government. Also, the contracting officer may use more than one liquidated damages rate when the contracting officer expects the probable damage to the Government to change over the contract period of performance.

(c) The contracting officer must take all reasonable steps to mitigate liquidated damages. If the contract contains a liquidated damages clause and the contracting officer is considering terminating the contract for default, the contracting officer should seek expeditiously to obtain performance by the contractor or terminate the contract and repurchase (see subpart 49.4). Prompt contracting officer action will prevent excessive loss to defaulting contractors and protect the interests of the Government.

(d) The head of the agency may reduce or waive the amount of liquidated damages assessed under a contract, if the Commissioner, Financial Management Service, or designee approves (see Treasury Order 145-10).

Sections it refers to

Sections that refer to it

← 11.500 Scope. · 11.502 Procedures. →