FAR and DFARS › FAR Part 11: Describing Agency Needs › Subpart 11.7

FAR 11.702 Construction contracts.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section applies to construction contracts and allows estimated quantities of unit-priced items to vary. If the actual quantity differs from the estimate by more than plus or minus 15 percent, either party can demand an equitable price adjustment. The contractor may also request more time if the quantity change increases the time needed to finish.

Applies to: Construction contracts with unit-priced items

What it requires

  • The contracting officer must receive a written request for a time extension within 10 days from the beginning of the period of delay.
  • The contracting officer shall ascertain the facts and make any adjustment for extending the completion date that the findings justify.

Key terms: unit-priced items · equitable adjustment · contract price · extension of time · final settlement

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

Construction contracts may authorize a variation in estimated quantities of unit-priced items. When the variation between the estimated quantity and the actual quantity of a unit-priced item is more than plus or minus 15 percent, an equitable adjustment in the contract price shall be made upon the demand of either the Government or the contractor. The contractor may request an extension of time if the quantity variation is such as to cause an increase in the time necessary for completion. The contracting officer must receive the request in writing within 10 days from the beginning of the period of delay. However, the contracting officer may extend this time limit before the date of final settlement of the contract. The contracting officer shall ascertain the facts and make any adjustment for extending the completion date that the findings justify.

← 11.701 Supply contracts. · 11.703 Contract clauses. →

Rule changes for FAR Part 11

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.