FAR and DFARS › FAR Part 13: Simplified Acquisition Procedures › Subpart 13.3
FAR 13.302-1 General.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section sets the general rules for issuing purchase orders under simplified acquisition procedures. It says purchase orders are generally fixed-price and lists what they must contain, such as quantity, a required delivery or performance date, and inspection terms. It also covers signature, distribution, and electronic funds transfer requirements.
Applies to: Contracting officers issuing purchase orders and the contractors receiving them
What it requires
- Specify the quantity of supplies or scope of services ordered
- Contain a determinable date by which delivery or performance is required
- Provide for inspection as prescribed in part 46
- Specify f.o.b. destination for supplies delivered within the United States, except Alaska or Hawaii, unless there are valid reasons to the contrary
Key terms: purchase order · fixed-price basis · unpriced purchase order method · f.o.b. destination · electronic funds transfer (EFT)
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Except as provided under the unpriced purchase order method (see 13.302-2), purchase orders generally are issued on a fixed-price basis. See 12.207 for acquisition of commercial products and commercial services.
(b) Purchase orders shall—
(1) Specify the quantity of supplies or scope of services ordered;
(2) Contain a determinable date by which delivery of the supplies or performance of the services is required;
(3) Provide for inspection as prescribed in part 46. Generally, inspection and acceptance should be at destination. Source inspection should be specified only if required by part 46. When inspection and acceptance will be performed at destination, advance copies of the purchase order or equivalent notice shall be furnished to the consignee(s) for material receipt purposes. Receiving reports shall be accomplished immediately upon receipt and acceptance of supplies;
(4) Specify f.o.b. destination for supplies to be delivered within the United States, except Alaska or Hawaii, unless there are valid reasons to the contrary; and
(5) Include any trade and prompt payment discounts that are offered, consistent with the applicable principles at 14.408-3.
(c) The contracting officer's signature on purchase orders shall be in accordance with 4.101 and the definitions at 2.101. Facsimile and electronic signature may be used in the production of purchase orders by automated methods.
(d) Limit the distribution of copies of purchase orders and related forms to the minimum deemed essential for administration and transmission of contractual information.
(e) In accordance with 31 U.S.C. 3332, electronic funds transfer (EFT) is required for payments except as provided in 32.1110. See Subpart 32.11 for instructions for use of the appropriate clause in purchase orders. When obtaining oral quotes, the contracting officer shall inform the quoter of the EFT clause that will be in any resulting purchase order.
← 13.302 Purchase orders. · 13.302-2 Unpriced purchase orders. →
Rule changes for FAR Part 13
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Prohibition on Certain Semiconductor Products and Services ↗ · proposed 2026-02-17 · comments due 2026-04-20
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Prohibition on Unmanned Aircraft Systems From Covered Foreign Entities ↗ · final rule 2024-12-30
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on Unmanned Aircraft Systems From Covered Foreign Entities ↗ · final rule 2024-11-12 · effective 2024-11-12
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.