FAR 16.207-1 Description.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section describes a firm-fixed-price, level-of-effort term contract. Under this contract type, the contractor provides a specified level of effort over a stated period on work that can only be described in general terms, and the Government pays a fixed dollar amount. It matters because it tells contractors what this contract type requires and how payment works.
Applies to: Contractors considering or performing a firm-fixed-price, level-of-effort term contract
What it requires
- Provide a specified level of effort over a stated period of time
- Perform work that can be stated only in general terms
Key terms: firm-fixed-price, level-of-effort term contract · level of effort · stated period of time · fixed dollar amount
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
A firm-fixed-price, level-of-effort term contract requires (a) the contractor to provide a specified level of effort, over a stated period of time, on work that can be stated only in general terms and (b) the Government to pay the contractor a fixed dollar amount.
← 16.207 Firm-fixed-price, level-of-effort term contracts. · 16.207-2 Application. →
Rule changes for FAR Part 16
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Protests of Orders Under Certain Multiple-Award Contracts ↗ · proposed 2025-06-12
- Federal Acquisition Regulation: Small Business Participation on Certain Multiple-Award Contracts ↗ · proposed 2025-06-12
- Federal Acquisition Regulation: Protests of Orders Under Certain Multiple-Award Contracts ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Small Business Participation on Certain Multiple-Award Contracts ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Rerepresentation of Size and Socioeconomic Status ↗ · final rule 2025-01-03 · effective 2025-01-17
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.