FAR 16.307 Contract clauses.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section tells contracting officers which contract clauses to include in solicitations and contracts for various cost-reimbursement, time-and-materials, and related contract types. It matters to contractors because the clauses determine how costs are reimbursed, fees are set, and indirect rates are applied.

Applies to: Contracting officers and contractors in cost-reimbursement, time-and-materials, and related contracts

Key terms: cost-reimbursement contract · time-and-materials contract · labor-hour contract · cost-plus-fixed-fee contract · cost-sharing contract

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a)(1) The contracting officer shall insert the clause at 52.216-7, Allowable Cost and Payment, in solicitations and contracts when a cost-reimbursement contract or a time-and-materials contract (other than a contract for a commercial product or commercial service) is contemplated. If the contract is a time-and-materials contract, the clause at 52.216-7 applies in conjunction with the clause at 52.232-7, but only to the portion of the contract that provides for reimbursement of materials (as defined in the clause at 52.232-7) at actual cost. Further, the clause at 52.216-7 does not apply to labor-hour contracts.

(2) If the contract is a construction contract and contains the clause at 52.232-27, Prompt Payment for Construction Contracts, the contracting officer shall use the clause at 52.216-7 with its Alternate I.

(3) If the contract is with an educational institution, the contracting officer shall use the clause at 52.216-7 with its Alternate II.

(4) If the contract is with a State or local government, the contracting officer shall use the clause at 52.216-7 with its Alternate III.

(5) If the contract is with a nonprofit organization other than an educational institution, a State or local government, or a nonprofit organization exempted under the OMB Uniform Guidance at 2 CFR part 200, appendix VIII, the contracting officer shall use the clause at 52.216-7 with its Alternate IV.

(b) The contracting officer shall insert the clause at 52.216-8, Fixed Fee, in solicitations and contracts when a cost-plus-fixed-fee contract (other than a construction contract) is contemplated.

(c) The contracting officer shall insert the clause at 52.216-9, Fixed-Fee—Construction, in solicitations and contracts when a cost-plus-fixed-fee construction contract is contemplated.

(d) The contracting officer shall insert the clause at 52.216-10, Incentive Fee, in solicitations and contracts when a cost-plus-incentive-fee contract is contemplated.

(e)(1) The contracting officer shall insert the clause at 52.216-11, Cost Contract—No Fee, in solicitations and contracts when a cost-reimbursement contract is contemplated that provides no fee and is not a cost-sharing contract.

(2) If a cost-reimbursement research and development contract with an educational institution or a nonprofit organization that provides no fee or other payment above cost and is not a cost-sharing contract is contemplated, and if the contracting officer determines that withholding of a portion of allowable costs is not required, the contracting officer shall use the clause with its Alternate I.

(f)(1) The contracting officer shall insert the clause at 52.216-12, Cost-Sharing Contract—No Fee, in solicitations and contracts when a cost-sharing contract is contemplated.

(2) If a cost-sharing research and development contract with an educational institution or a nonprofit organization is contemplated, and if the contracting officer determines that withholding of a portion of allowable costs is not required, the contracting officer shall use the clause with its Alternate I.

(g) The contracting officer shall insert the clause at 52.216-15, Predetermined Indirect Cost Rates, in solicitations and contracts when a cost-reimbursement research and development contract with an educational institution (see 42.705-3(b)) is contemplated and predetermined indirect cost rates are to be used.

Sections it refers to

Sections that refer to it

← 16.306 Cost-plus-fixed-fee contracts. · 16.401 General. →

Rule changes for FAR Part 16